Bundled Average Retail Rate

¢/kWh, January 1 each year · bundled utility customers

CPUC Distribution Rate Base

$B · CPUC-jurisdictional distribution · dashed = pending proceedings

Source: CPUC Historical Electric Cost Data, pursuant to SB 695. Projected = cumulative Distribution RRQ from pending CPUC applications.


Applications Filed

Current Period
Oct 16 – Oct 31, 2026
2 filings
A.26-10-016 · Filed Oct 21, 2026 · Application · Liberty Utilities (CalPeco Electric) · Short-Term Debt

Liberty Utilities (CalPeco Electric) Seeks Authority to Issue Short-Term Indebtedness

Liberty Utilities (CalPeco Electric) LLC (U 933-E) filed an application on October 21, 2026 for authorization to issue evidence of short-term indebtedness, together with related relief. A financing application of this type sets the authorized ceiling on short-term borrowing and does not itself change rates; the cost of the resulting debt reaches customers later, through the cost of capital adopted in a general rate proceeding.

A.26-10-013 · Filed Oct 19, 2026 · Application · ERRA Trigger · PHC Nov 12

PG&E Files an ERRA Trigger Application Without Seeking a Rate Change

PG&E filed an Energy Resource Recovery Account trigger application on October 19 because its overcollection is not expected to fall below the regulatory trigger within 120 days, which compels a filing under D.02-10-062. PG&E seeks no rate change in the trigger case, proposing instead to address the balance through its pending ERRA forecast proceeding (A.26-05-007), expected to conclude by December 2026, with the overcollection amortised into 2027 rates. An ALJ ruling of October 26 set an expedited schedule: protests and responses November 2, PG&E replies November 6, and a virtual prehearing conference November 12. Parties must address whether the two proceedings should be consolidated.

► Details
A trigger filing is a procedural obligation rather than a request for relief: once the balance breaches the threshold the utility must come in, even with nothing to ask for. PG&E’s position is that the right venue is the annual forecast case, which avoids a second rate change late in 2026.

An October 22 ruling already directs parties to address the substance of the balance in the forecast proceeding, so the live question here is consolidation. Neither the ruling nor the application specifies the overcollection amount or estimated rate impact — the $306 million figure comes from PG&E’s separate October 16 procurement update, carded under Miscellaneous.
Prior Period
Oct 1 – Oct 15, 2026
0 filings
No new energy applications were docketed at the CPUC in this period.
Earlier Period
Sep 16 – Sep 30, 2026
0 filings
No new energy applications were docketed at the CPUC in this period. The Commission’s new-filings list for the week of September 14–18 shows one application, A.26-09-005 — a telephone-corporation registration filed September 14, outside both this period and CalReg’s scope.
No matches for selected IOU.

Advice Letters

Utility advice-letter filings — rate and revenue updates, tariff changes, compliance filings and non-standard interconnection packages. Commission resolutions disposing of these filings are carded under Proposed Decisions & Rulings.

Current Period
Oct 16 – Oct 31, 2026
3 filings
AL 5279-G · Filed Oct 28, 2026 · Advice Letter · Effective Nov 1 · Protests Nov 17

PG&E Confirms Readiness for Revised Gas Curtailment Rules; Dispatchable Generators Cut First

PG&E filed Advice Letter 5279-G on October 28 confirming readiness to implement revised natural gas curtailment rules on November 1 under D.25-10-042, aligning its curtailment priorities with California’s other gas utilities in a six-step framework. Idle dispatchable generators are curtailed first, then operating generators, whose gas use may be cut up to 60% from November through March and 40% from April through October. Step 3 covers up to 100% of other noncore usage pro rata, including industrial customers, cogeneration and non-dispatchable generators. Refineries keep documented minimum usage until Step 4, when those volumes become curtailable alongside remaining dispatched generation. Non-residential core customers follow at Step 5, with residential customers last. PG&E reports completed employee training and documented minimum usage requirements with all refinery customers.

► Details
The order of operations is the whole substance: putting dispatchable generation first means a winter gas shortage is absorbed by the electric sector before it reaches industrial or core customers, which transfers the constraint onto electric reliability. PG&E may reduce Step 2 curtailment if grid operators warn of firm load shedding, but retains final discretion — so the coupling between the gas and electric systems is managed by the utility rather than by tariff.

PG&E may also depart from the prescribed order during emergencies or planned maintenance. The filing implements previously approved tariff revisions ahead of the 2026–27 winter.
AL 5274-G · Filed Oct 2026 · Advice Letter · Protests Nov 5 · $33.7M Interest

PG&E Seeks $33.7M of Accrued Interest on 2011–2014 Gas Transmission Costs It Never Billed

PG&E filed Advice Letter 5274-G seeking approval to recover $33.7 million of accrued interest associated with gas transmission and storage capital expenditures incurred between 2011 and 2014. PG&E cites D.22-07-007, which approved a settlement authorising recovery of $356.3 million of previously incurred GT&S costs — a $60 million reduction from its original $416.3 million request. PG&E began recovering the authorised costs in August 2022 but has not included the associated accrued interest in any recovery request since. It calculates the interest under existing tariff and balancing-account provisions and seeks recovery through the Annual Gas True-Up.

► Details
PG&E’s tariffs require interest to be recorded on the applicable balancing account amounts, and the utility has not included it since the 2022 settlement was implemented. The filing does not explain the omission. That is the question Energy Division review has to reach: whether a four-year gap in billing an amount the tariff required to be recorded is recoverable later under the same settlement, or whether the delay itself bears on recovery. The amount would be added to future gas rates.
AL 7785-E-A · Filed Oct 26, 2026 · Supplemental Advice Letter · Protests Nov 16

PG&E Refiles the Google Data-Center Agreement With a $150M Refundable Advance and an Early Termination Fee

PG&E filed supplemental Advice Letter 7785-E-A on October 26, submitting a revised interconnection agreement with Google for the proposed 250 MW San Jose data center and incorporating the ratepayer protections sought in Draft Res. E-5455. Google will provide a $150 million revenue support advance — refundable under the draft resolution, and corresponding to its $600,000/MW requirement — plus the applicable Income Tax Component of Contribution, and the agreement adds minimum demand charges and an early termination fee. Google will build a 230 kV switching station for transfer to PG&E and pay actual construction costs billed as work progresses. Refunds are capped at 100% of net transmission revenue, with further provisions addressing construction overruns and cancellation risk. The supplemental filing replaces the original advice letter and sets a new protest deadline of November 16.

► Details
The revisions answer the Commission’s concern that existing ratepayers could carry transmission costs if Google’s demand falls short or the project is cancelled. The advance is refundable, so it functions as security rather than a contribution — it protects ratepayers against a demand shortfall without charging Google for capacity it ultimately uses. PG&E may seek to adjust the advance by Tier 2 advice letter within a year of a decision in the pending Rule 30 proceeding (A.24-11-007).

The schedule is now the binding problem. PG&E sought approval by June 1, 2026 to start construction in January 2027 and service in December 2028. That date has passed, the new protest period runs to November 16, and the resolution has been held at six consecutive voting meetings — so each further deferral puts the construction start, not just the paperwork, at risk.
Prior Period
Oct 1 – Oct 15, 2026
8 filings
Advice-Letter Submissions · Filed Oct 1–9, 2026 · Advice Letters · Routine Rate and Tariff Filings

Ten Routine Advice Letters Filed in the First Week of October

Beyond the major rate and clean-fuels filings carded separately, the utilities submitted ten routine advice letters between October 1 and October 9, recorded in the Commission’s Daily Calendars. They cover monthly gas cash-out and cross-over rates, two West Coast Gas rate decreases, PG&E’s updated SB 1221 maps, a revision to PG&E’s solar sizing requirement under D.26-05-033, and SDG&E modifications to three generation and portfolio balancing accounts.

► Details
Oct 1 — PG&E AL 5265-G, updated SB 1221 maps per the assigned commissioner’s ruling directing large gas corporations to update them; PG&E AL 7995-E, updating the VDT-NBT system sizing requirement and implementation date per D.26-05-033.

Oct 2 — SDG&E AL 4840-E-A, supplement reporting first-quarter 2026 procurement transactions per D.02-10-062.

Oct 5 — SoCalGas AL 6704-G, Schedule G-CPS September 2026 cash-out rates.

Oct 8 — SDG&E AL 4906-E, modifications to the Electric Distribution Fixed Cost Account, the Non-Fuel Generation Balancing Account and the Portfolio Allocation Balancing Account; PG&E AL 5270-G, Schedule G-CPX crossover gas procurement service rates effective October 10; West Coast Gas AL 729-G and AL 730-G, rate decreases at Mather Field and Castle.

Oct 9 — SDG&E AL 3561-G and SoCalGas AL 6708-G, October 2026 cross-over rate revisions effective October 10.

Separately, four earlier advice letters were suspended on October 19 for additional review time, with the suspension running to February 15, 2027: PG&E AL 7986-E and AL 7988-E, SDG&E AL 4899-E and SCE AL 5891-E.

Cash-out and cross-over rate filings are monthly mechanical updates that pass through gas commodity costs; the two West Coast Gas filings reduce rates at the two military-adjacent systems it serves.
AL 5897-E · Filed Oct 2026 · Advice Letter · GRC Phase 2 · Rates Effective Oct 1 · Protests Oct 19

SCE Revenue Requirement Falls $378.8M as Wildfire Recoveries Roll Off — but Residential Bundled Rates Rise 0.4%

SCE filed an advice letter implementing an October 1 rate change that reduces its authorized revenue requirement by $378.8 million from the June 1 level, largely because about $628 million in temporary wildfire and memorandum-account recoveries, net of an expiring Creek Fire credit, rolled off September 30. New amounts entering rates include the 2022 ERRA adjustment, Woolsey Fire CEMA recovery, and fixed recovery charges tied to about $1.95 billion of Woolsey Fire recovery bonds. The GRC Phase 2 decision (D.26-04-033) reallocated the revenue requirement among customer classes: bundled system-average rates fall 0.8% while residential bundled rates rise 0.4%, and a typical non-CARE residential customer using 500 kWh would see an estimated $2.79 monthly increase, or 1.5%. Protests are due October 19.

► Details
SCE is collecting less overall, but residential customers are assigned a larger share of a smaller revenue requirement. Unbundled residential rates rise 2.4% while the overall unbundled average falls 2.2% — the clearest expression of the Phase 2 reallocation.

The filing also begins a four-year residential time-of-use transition. PRIME adds a super-off-peak period; PRIME and TOU-D-5-8PM receive wider seasonal spreads; and TOU differentials move toward Commission-approved marginal-cost levels through 2029.

Note on the citation: the source newsletter renders the advice-letter number as “Advice 7-E,” which appears truncated. The substantive figures and the underlying decision (D.26-04-033) are as reported; confirm the advice-letter number against SCE’s filing index before citing it.
AL 7996-E · Filed Oct 2026 · Advice Letter · FERC ER26-3859-000 · Protests Oct 22

PG&E 2027 Transmission Rates — $174.2M TRBAA Credit, but the Per-kWh Credit Shrinks About 42%

PG&E filed Advice Letter 7996-E notifying the Commission of its September 25 FERC filing in Docket ER26-3859-000 updating three transmission rate components for 2027: the Transmission Revenue Balancing Account Adjustment (TRBAA), Reliability Services rates, and the End-Use Customer Refund Balancing Account Adjustment (ECRBAA). The retail TRBAA would provide a $174.2 million credit, producing a rate of negative $0.0024/kWh against negative $0.00412/kWh today. Reliability Services would carry an $11.0 million charge and the ECRBAA a $5.9 million charge. PG&E asked FERC for a November 25 effective date with the new rates suspended until January 1, 2027. Protests are due October 22.

► Details
A $117.4 million TRBAA undercollection offsets a large share of the $288.9 million in forecast transmission revenue credits. After a small fee-and-uncollectibles adjustment, the 2027 retail credit lands at $174.2 million. The per-kWh TRBAA credit therefore falls about 42% even though the headline credit remains substantial — the undercollection is what erodes it.

Reliability Services and ECRBAA charges of $17 million combined bring the net retail credit across the three adjustments to about $157.2 million. PG&E would typically fold the new rates into its year-end retail rate change, which is why the requested November effective date is paired with suspension to January 1.
AL 4904-E · Filed Oct 2026 · Advice Letter · Public Purpose Programs · Effective Jan 1, 2027

SDG&E Public Purpose Program Rates Rise 2.34% — CARE Alone Accounts for $91.9M of a $92.7M Increase

SDG&E filed Advice Letter 4904-E proposing to raise its electric Public Purpose Program rates on January 1, 2027. System-average delivery rates would rise 0.493 cents/kWh, or 2.34%, while bundled rates would increase 1.26%. The filing seeks $428.8 million in disclosed PPP revenue requirements, up $92.7 million from current rates, excluding the confidential Tree Mortality charge. CARE accounts for the largest single increase: its revenue requirement rises $91.9 million to $246.8 million, mostly from a $64.3 million balancing-account swing as a $38.2 million credit in 2026 rates became a $26.1 million undercollection for 2027.

► Details
Forecast discounts add $28.5 million. Medical Baseline discounts add $26.4 million as a new PPP recovery line, while Diablo Canyon, EPIC and SDREN together add about $24 million. SDG&E offsets collections with $13 million of unspent ESA funds and $20 million of unspent energy-efficiency funds.

About $28 million of the $92.7 million increase recovers prior-year balances rather than funding current programs; the remainder funds 2027 programs and discounts. CARE’s $91.9 million increase exceeds the entire $72 million increase in low-income PPP costs, because reductions in ESA, RUBA-AMP, PIPP and the Concurrent Application System Balancing Account absorb part of it.
AL 5903-E · Filed Oct 2026 · Advice Letter · Vehicle-to-Grid Export

SCE Proposes Export Compensation for Bidirectional EVs in the Expanded Dynamic Rate Pilot — Implementation Not Until Mid-to-Late 2027

SCE filed Advice Letter 5903-E proposing to modify its Expanded Dynamic Rate Pilot to compensate eligible customers for electricity exported from bidirectional electric vehicles. Export compensation would use only the time-varying marginal-cost components of the dynamic rate and would flow through the pilot’s existing shadow-bill credit calculation rather than appear as a separate payment on the customer’s regular bill. Eligibility would be limited to customers whose export-capable EVs and charging equipment are not co-located behind the meter with other exporting technologies. Implementation is expected mid-to-late 2027.

► Details
SCE also proposes to exclude rates requiring manual billing or transfers of credits between accounts, including NBT-V, NBT-A, NEM-V, NEM-A, RES-BCT and SOMAH.

This is a limited test of vehicle-to-grid export compensation following the Commission’s rejection of a permanent export-rate proposal over concerns about shifting costs to other customers. Valuing exports at marginal cost and keeping the compensation inside the dynamic-rate pilot addresses that objection directly, since a marginal-cost credit does not by construction recover more than the value the export provides.

The timing constrains what the Commission can learn. SCE does not expect the export feature to be available until mid-to-late 2027, while the pilot is currently scheduled to end in December 2027 — leaving a short window of operating data before the pilot closes.
AL 5902-E · Filed Oct 2026 · Advice Letter · Port Electrification · Protests Oct 20

SCE Would Cut the Port of Long Beach Capacity-Cost Discount From 50% to 45%, Citing Thousands of MW of New Procurement Need

SCE filed Advice Letter 5902-E proposing to reduce the Marginal Generation Capacity Cost discount used in calculating rate discounts for qualifying new maritime load at the Port of Long Beach from 50% to 45%. SCE cites the Commission’s 4,000 MW supplemental mid-term reliability order (D.23-02-040) and its 6,000 MW 2030–2032 procurement order (D.26-02-057) as evidence of increased generation-capacity need, while arguing a 45% discount still supports port electrification. Protests are due October 20; the 45% discount would remain until the next review at the conclusion of SCE’s 2033 General Rate Case Phase 2.

► Details
SCE withdrew an earlier July filing and refiled after settlement discussions with the Port, which approved the submission on a non-precedential basis without conceding the merits of any issue.

The underlying argument is that a 50% capacity-cost discount no longer fits a system under orders to procure thousands of megawatts of new capacity: the discount was calibrated when marginal capacity cost was lower, and holding it constant shifts a growing share of that cost to other customers. The July withdrawal and subsequent settlement talks indicate the proposal drew resistance, and the Port’s express reservation of every issue leaves the dispute open to return at the next review.
AL 5900-E · Filed Oct 2026 · Advice Letter · Clean Fuel Reward

California Clean Fuel Reward Drops to $200M for 2027 and Pivots From Light-Duty EV Rebates to Commercial Trucks and Electric Motorcycles

SCE filed Advice Letter 5900-E forecasting $200 million in California Clean Fuel Reward funding for 2027, down from $250 million in 2026. The redesigned program now offers incentives for commercial medium- and heavy-duty vehicles and battery-electric motorcycles instead of light-duty EV rebates. SCE expects $5.72 million in administrative costs and $1 million for marketing, education and outreach, including retailer training and possibly direct-to-fleet advertising. SCE redacted its contribution and reward-distribution forecasts as market-sensitive LCFS information.

► Details
Because the contribution figures are redacted, the public filing does not show whether the $6.72 million in combined administrative and outreach costs stays within CARB’s 5% limit.

The program’s Steering Committee proposed annual funding levels through 2028 and approved scheduled funding windows by vehicle class. Those choices followed demand that outran funding in the light-duty program and stakeholder complaints that HVIP vouchers often sold out within a week. The last 2026 window stays open through February 2027, so the two funding schedules overlap.

Revenue remains uncertain. The filing characterises the planned amounts as a conservative estimate of LCFS proceeds, and the Steering Committee may release additional funds the following year if proceeds exceed projections.
2027 LCFS Forecasts · Filed Sep 30, 2026 · Advice Letters · Res. E-5463 Cycle

2027 Low Carbon Fuel Standard Filings — SCE Counts 98% of $132.6M as Equity Spending; PG&E Limits Pre-Owned EV Rebates to Income-Qualified Buyers

California’s investor-owned utilities filed their 2027 Low Carbon Fuel Standard forecasts on September 30. Under Resolution E-5463, the forecasts now also carry budget and extension requests. SCE plans $132.6 million in LCFS holdback spending and counts 98% as equity-related, requesting no additional funding. PG&E expects to distribute $57.8 million to electric customers and requests $32 million for its Pre-Owned EV Rebate program, which becomes income-qualified only, with $4,000 rebates for battery EVs and $2,000 for plug-in hybrids. SDG&E seeks a two-year extension of its Pre-Owned EV program with an additional $15 million for 2028–2029. On the gas side, SoCalGas projects a $29.3 million balancing-account overcollection entering 2027.

► Details
About half of SCE’s equity spending is for drayage trucks and shared medium- and heavy-duty charging, which CARB counts as equity regardless of location. SCE pauses standard, non-income-qualified pre-owned EV rebates and some non-income-qualified home-electrification incentives, and plans no new drayage rebates.

CARB’s revised rules redirect the statewide Clean Fuel Reward toward commercial medium- and heavy-duty vehicles, with SCE and PG&E contributing 50% of applicable base-credit proceeds and SDG&E at least 25%.

On the gas side, SoCalGas proposes to amortize $3.72 million of its $29.3 million overcollection through the pooled Sempra LCFS rate credit, with SDG&E contributing another $782,000 from its own accumulated balance. The two utilities will pool their balances into a Sempra-wide credit of about 41.1 cents/therm before utility-specific adjustments.

The filings show LCFS spending concentrating on income-qualified residential customers and commercial fleet electrification: PG&E and SCE both limit pre-owned EV rebates to lower-income buyers, while CARB’s revised Clean Fuel Reward shifts statewide funding from passenger vehicles to trucks. SoCalGas’s accumulated balance remains large relative to its planned 2027 amortization.
Earlier Period
Sep 16 – Sep 30, 2026
1 filing
AL 6693-G · Filed Sep 16, 2026 · Advice Letter · Biomethane Procurement

SoCalGas Seeks Approval of Biomethane Contracts With United Energy Trading and Rialto Bioenergy — First Test of the Reduced 36.4 Bcf RGS Target

SoCalGas filed Advice Letter 6693-G asking the CPUC to approve biomethane procurement agreements with United Energy Trading and Rialto Bioenergy Solutions, negotiated with projects carried over from its 2025 solicitation. The contracts would help SoCalGas and SDG&E meet combined annual targets of about 9.9 Bcf of biomethane from diverted organic waste and 21.7 Bcf under the overall Renewable Gas Standard by 2035. One selected project would use pyrolysis to convert landfill-diverted walnut shells into biomethane. SoCalGas says the agreements pass the program’s 3% annual increase cap and 1% annual average program cost cap. Protests are due October 1.

► Details
Prices, volumes, contract terms, project milestones and cost calculations are confidential. SoCalGas proposes recovering net above-market costs from all gas end-use customers through a non-bypassable, equal-cents-per-therm transportation charge, subject to the outcome of the pending biomethane cost-allocation proceeding — see the competing Houck and Reynolds proposed decisions carded under Proposed Decisions & Rulings.

The agreements are an early test of the revised Renewable Gas Standard. In D.26-04-044 the CPUC reduced the overall RGS target from 72.8 to 36.4 Bcf annually, extended the compliance deadline from 2030 to 2035 and added cost-containment limits. SoCalGas states both agreements pass those limits, but confidentiality prevents independent assessment of the prices and calculations.

The bilateral negotiations illustrate the difficulty of converting eligible projects into completed contracts: both projects qualified during the 2025 solicitation but needed additional time to conclude negotiations. Approval would advance the utilities’ procurement targets while spreading the resulting above-market costs across all gas customers.
No matches for selected IOU.

Proposed Decisions & Rulings

Current Period
Oct 16 – Oct 31, 2026
18 items
R.21-06-017 · Track 3 · PD Oct 20, 2026 · Proposed Decision · Comments Nov 9 · Earliest Dec 3

Track 3 Proposed Decision Would Make Flexible Service Connections a Standing Alternative to Distribution Upgrades

A proposed decision from Commissioner Darcie Houck, filed October 20, 2026, would direct PG&E, SCE and SDG&E to expand flexible service connections so customers can use available distribution capacity without triggering an immediate grid upgrade. Utilities would have to evaluate flexible connections before undertaking ratepayer-funded upgrades and consider limited-power arrangements where a distribution transformer is the constraint. The PD extends the existing Standard Offer to SDG&E, directs SCE to implement variable operating envelopes modelled on PG&E’s Flex Connect program, requires SDG&E to demonstrate comparable capability at a minimum of two sites, and requires PG&E to extend its non-bridging Flex Connect option to load customers. Comments are due November 9; the earliest the Commission may act is December 3.

► Details
This is the Track 3 successor to Commissioner Houck’s July 2026 assigned-commissioner proposal, carded in an earlier period. The shift that matters is from flexible connection as a temporary accommodation for customers awaiting an upgrade to a standing option under ongoing capacity limits — which is what lets a utility defer or avoid the capital altogether rather than merely sequence it. The PD also directs the utilities to propose expanded grid-edge DERMS programs and cybersecurity measures, and adds reporting and affordability tracking to test whether the arrangements actually produce measurable infrastructure savings.

Read alongside the DER orchestration decision adopted October 29 in the same docket: one sets the process for coordinating DERs, the other the terms on which load can connect under limits. Together they are the principal non-firm pathway available to large new loads, so both bear directly on data-center energization timelines.
R.18-07-005 · Phase 2 · PD Oct 16, 2026 · Proposed Decision · Disconnections

Disconnections Proposed Decision Would Conditionally Lift the SoCalGas Cap and Reset the Caps for PG&E, SCE and SDG&E

A proposed decision filed October 16, 2026 addresses Phase 2 issues on residential disconnection caps and disconnection pilots, and identifies the remaining issue in the proceeding. The PD would conditionally lift the disconnection cap established for SoCalGas in D.20-06-003 and update the caps applicable to PG&E, SCE and SDG&E.

► Details
The caps limit the share of residential customers an energy utility may disconnect for non-payment in a given period. Lifting one — even conditionally — changes the operative constraint on collections practice rather than the underlying arrearage, so the conditions attached are the substantive part of the PD.
R.23-03-007 · PD Oct 19, 2026 · Proposed Decision · Comments Nov 9 · Earliest Dec 3

Proposed Decision Would Cut the 2027 Wildfire Fund Charge to $0.00545/kWh, Down 7.8%

A proposed decision filed October 19, 2026 would reduce the 2027 Wildfire Fund Non-Bypassable Charge to $0.00545/kWh from $0.00591/kWh in 2026, a decrease of about 7.8%. PG&E, SCE and SDG&E would collect the charge from eligible customers across calendar 2027. The PD adopts the Department of Water Resources’ updated calculation, which calls for collecting $860 million in 2027 against the fund’s $902.4 million annual revenue requirement, with a projected $42.4 million cumulative overcollection through 2026 covering the difference. The utilities must file Tier 1 advice letters implementing the charge by December 31. Comments are due November 9; the earliest the Commission may act is December 3.

► Details
The reduction is almost entirely a function of accumulated overcollection rather than a change in the underlying obligation — the annual revenue requirement is unchanged at $902.4 million. Forecast electricity sales also move the per-kWh figure. DWR recalculates and proposes the charge each year from prior collections and projected sales, subject to Commission approval, so the charge can fall in a year when the fund’s exposure has not.

The charge is non-bypassable: it applies regardless of who supplies a customer’s generation, so it reaches bundled, CCA and Direct Access customers alike. It backs the AB 1054 Wildfire Fund, which is the mechanism absorbing exactly the tail risk PG&E’s management has been pressing the Legislature to address.
A.26-02-005 · SB 884 · PD Oct 16, 2026 · Proposed Decision · Comments Nov 5 · Earliest Nov 19

Undergrounding Proposed Decision Would Tie SB 884 Cost Recovery to Project-Level Benefit-Cost Performance

A proposed decision from President John Reynolds, filed October 16, 2026, would add cost-recovery requirements for electric distribution undergrounding under Senate Bill 884, California’s expedited 10-year program. It adopts a standardised benefit-cost ratio methodology, audit requirements and five additional conditions governing how PG&E, SCE and SDG&E evaluate undergrounding against alternative wildfire mitigations and recover costs through one-way balancing accounts. BCRs must use unscaled, risk-neutral values and a common weighted-average-cost-of-capital discount methodology, and avoided O&M must be counted as a benefit rather than netted against project cost. An actual project BCR may not fall more than 30% below the final Energy Safety Screen 4 forecast, unit costs may not exceed that forecast by more than 30%, and a project must retain a forecast BCR of at least 1.0 after final scoping.

► Details
The design intent is to keep expedited recovery available only while a project’s economics hold up as it moves from preliminary forecast to completed construction — the balancing account stops being a guarantee and becomes conditional on realised performance.

The PD rejects the utilities’ request to weigh local factors outside their risk models where undergrounding’s forecast BCR falls below an alternative’s but remains at least 70% of it, finding that the exception would systematically favour undergrounding over competing mitigations. That is the same comparative question the Safety Policy Division raised against SCE’s RAMP workpapers, where operating-cost assumptions depressed covered conductor’s ratio relative to undergrounding — carded separately in this period.
R.21-06-017 · Decision Oct 29, 2026 · Adopted · DER Orchestration

Commission Orders PG&E, SCE and SDG&E to File a Joint DER Orchestration Application Within 12 Months

The adopted decision establishes a process for the three utilities to propose a common framework for coordinating distributed energy resources and folding load flexibility into distribution planning. They must hire an outside facilitator, run a stakeholder working group, and file a joint DER orchestration application within 12 months addressing grid services, cost-effectiveness, interoperability, dispatch, aggregator participation and CAISO coordination. Load flexibility becomes a fourth scenario in distribution planning. Memorandum-account funding for developing the application is capped at $500,000 across all three utilities. Commissioner Matthew Baker was recused.

► Details
The decision sets the process without adopting an operating framework. Utilities must prioritise existing technology investments and justify why further spending cannot come out of general rate case funding. Aggregators are not guaranteed a role and must demonstrate value without compromising cost-effectiveness.

Commissioner Houck acknowledged the concern that utilities may favour capital investment over DER alternatives but deferred it to the working group and the subsequent application. President John Reynolds said he would focus on affordability and competitive neutrality when the applications arrive; Commissioner Christine Harada called for measurable savings and straightforward customer participation. The savings figures cited from the dais are the utilities’ own studies, not Commission findings.
A.25-04-020 · Decision Oct 29, 2026 · Adopted · SoCalGas TIMP

SoCalGas Granted Partial TIMP Recovery; $20.2M Capital and $42.6M O&M Disallowed

The adopted decision grants SoCalGas partial recovery of its $173.8 million revenue requirement request for Transmission Integrity Management Program work performed 2019–2023. It disallows $20.2 million of capital costs and $42.6 million of O&M from $305.8 million of underlying expenditure, citing SoCalGas’s failure to show that straight-time labour and associated vacation and sick leave were incremental, unsupported vendor expenses, and missing workpapers for 8% of expenditures. The Commission allowed $40.7 million for Pipeline 235 West subject to refund and approved a 12-month recovery period. SoCalGas must file a Tier 2 advice letter within 30 days to calculate the final revenue requirement.

► Details
Commissioner Darcie Houck introduced a revised decision replacing an earlier proposal to disallow 40% of the remaining revenue requirement under the prudent-manager standard. The Commission therefore stepped back from questioning the prudence of the pipeline-safety spending while holding that the utility must still substantiate costs and show labour was not already funded through the general rate case. This supersedes the $81.3 million approval figure in the proposed decision, which CalReg carded in the prior period.

Commissioner Baker supported the revisions but pressed for clearer standards on incremental cost recovery; Douglas and Reynolds agreed; Harada noted the volume of filings did not substitute for missing evidence. Houck observed that the 2024 GRC decision (D.24-12-074) converted the TIMP balancing account from two-way to one-way, which should make proceedings of this kind rarer. Future applications must identify the federal pipeline-safety requirement and compliance deadline behind each project.
D.26-10-053 · Decision Oct 29, 2026 · Adopted · Demand Response

Commission Approves $608.3M of Demand-Response Bridge Funding for 2028–2029

The decision authorises two years of bridge funding for demand-response programs while the Commission considers reforms under R.25-09-004. Annual budgets are $110.5 million for PG&E, $178.4 million for SCE and $15.2 million for SDG&E — about $608.3 million over 2028 and 2029 combined. Emergency Load Reduction Program sub-groups for virtual power plant and EV aggregators continue at all three utilities with minimum annual dispatch hours cut from 20 and 30 respectively to 18; SDG&E’s non-residential sub-group also continues, and all other ELRP sub-groups close at the end of 2027. The bridge-year portfolios are exempt from the Societal Cost Test, which must be built into the cost-effectiveness tool by April 1, 2028. Applications for the 2030–2034 cycle are due November 1, 2028, and unspent bridge funding returns to ratepayers. Adopted as consent item 22.

► Details
TURN cited substantial underspending — PG&E and SDG&E spent just 19.7% and 17.8% of their 2024–2025 budgets — but the Commission held authorised funding at previous levels rather than delay the extension. That is a deliberate trade of budget discipline for program continuity, and the unspent-funds return provision is what limits the ratepayer exposure.

The decision also rejects calls to end the ELRP pilot, keeping the better-performing VPP and EV aggregation sub-groups while reducing guaranteed dispatch hours. The 18-hour floor splits the difference between the 10 hours PG&E and SDG&E proposed and aggregators’ concern that fewer dispatch opportunities would deter participation. A comprehensive ELRP cost-effectiveness review is deferred, leaving the program’s long-term role unresolved.
Climate Adaptation · Decision Oct 29, 2026 · Adopted · Mandatory Framework

Climate-Adaptation Framework Adopted as Mandatory, Over Staff’s Recommendation That It Be Guidance

The adopted decision establishes a climate-adaptation framework for PG&E, SoCalGas, SDG&E and SCE, and makes it mandatory despite the Safety Policy Division’s recommendation that it serve as optional guidance. Utilities must screen new infrastructure applications against yes/no questions in five policy areas: repetitive loss and failure, site selection, design and engineering, equipment tolerance, and climate risk modelling. From 2028 each utility files an annual report by May 1 documenting how climate risk was addressed, followed by a joint workshop by June 30. The decision declines to revise existing General Orders or create a standalone climate-adaptation order, and drops a staff-proposed requirement for written climate-risk analyses in individual applications, which the utilities argued duplicated their existing Climate Adaptation Vulnerability Assessments and RAMP filings.

► Details
The Commission went further than staff on whether the framework binds, and less far than staff on what it requires — mandatory in form, but limited to new infrastructure applications with the separate analytical step removed. The reporting that results gives regulators visibility into the hazards identified in CAVAs and RAMPs, the modelling assumptions behind them, and the adaptation actually built into proposals, which is the input the Commission would need before deciding whether to fold climate adaptation into the General Orders. Utilities may seek revisions after the first annual workshop.
SoCalGas Microgrids · Decision Oct 29, 2026 · Denied Without Prejudice · Tariff

SoCalGas Microgrid Tariff Denied; Commission Cites Cost-Shift Risk and PU Code § 218 Exposure

The Commission denied, without prejudice, SoCalGas’s application for an optional microgrid tariff for commercial and industrial customers. The proposal would have let SoCalGas design, build, own and operate behind-the-meter and off-grid microgrids serving facilities such as data centers, hospitals and EV charging stations, with costs recovered through individually negotiated customer agreements. The Commission found SoCalGas had not demonstrated sufficient public benefits or adequate protection against cost shifting and financial risk to ratepayers, had not established consistency with state decarbonisation policy, and had left the record insufficient to judge competitive effects. SoCalGas must file a Tier 2 advice letter within 60 days identifying project-development and litigation costs and crediting ratepayer-funded expenses back to customers without interest.

► Details
Two specific findings carry the denial. First, SoCalGas had not shown the tariff avoids the risk of making it an electrical corporation under PU Code § 218 — a jurisdictional line, not a policy preference. Second, it had not addressed the possibility that microgrid customers could avoid non-bypassable charges, shifting those costs to remaining electric utility customers.

The Commission also questioned whether new gas-fired microgrids would cut against pipeline retirement under the Long-Term Gas Planning proceeding (R.24-09-012). The denial being without prejudice leaves a revised application open, and the data-center use case is the one most likely to return.
A.26-05-002 · Decision Oct 29, 2026 · Adopted · Sempra SAP Migration

Sempra Utilities Authorised to Track Up to $13.7M of SAP Migration Costs in a Memorandum Account

The decision authorises SoCalGas and SDG&E to establish a memorandum account tracking up to $13.7 million of costs for their SAP enterprise software migration. Effective May 1, 2026, the account covers Phase 1B migration work and 2027 costs to solicit bids for Phase 2, ahead of SAP’s planned withdrawal of support for certain legacy applications at the end of 2027. The Commission rejected Cal Advocates’ objections, finding that its earlier reduction of SAP funding did not preclude a later request and that delay could create operational, compliance and cybersecurity risk. The decision does not authorise cost recovery or find the expenditures reasonable.

► Details
In the 2024 GRC (D.24-12-074) the Commission authorised $51.2 million of a $70.6 million capital request for a more extensive SAP transformation; the Sempra utilities now seek roughly $348 million of revenue requirement for the remaining phases of a scaled-back migration. This decision only preserves the possibility of recovering costs incurred since May 1.

The reasoning is worth noting for future memo-account requests: the Commission found SAP’s withdrawal of support was not an exceptional event beyond the utilities’ control, but concluded Phase 1B costs were unforeseeable because Sempra revised its migration plans after the last GRC. That distinction let the account qualify under three of five criteria while deferring any finding on ratepayer benefit. The $348 million request remains fully exposed.
A.26-05-018 · SPD Evaluation Oct 22, 2026 · Ruling · Comments Nov 18 / Replies Dec 14

Safety Policy Division Finds a $13 Billion Gap Between SCE’s RAMP Workpapers and Its Summary Wildfire Benefits

The CPUC’s Safety Policy Division issued an evaluation on October 22 finding that SCE generally complies with the risk-based decision-making requirements but identifying 35 findings on wildfire and PSPS risk and 49 findings across other risk categories. The central discrepancy is in benefits: staff calculate approximately $17.26 billion of mitigation benefit from SCE’s detailed benefit-cost workpapers, against an estimated upper bound of $4.30 billion from the utility’s own summary risk-reduction figures and documented assumptions. Covered conductor and undergrounding alone account for about $9.9 billion of the workpaper benefits. SPD also found inconsistent operating-cost assumptions, calculation errors affecting undergrounding, incomplete wildfire risk coverage and insufficient documentation of project prioritisation, and recommends SCE reconcile its calculations and validate its risk models before filing its 2029 GRC. An accompanying ALJ ruling invites comments by November 18, replies by December 14; the 2029 GRC application is due May 14, 2027.

► Details
A four-fold divergence between the workpapers and the summary is not a rounding problem — it means the benefit figure supporting the portfolio cannot be independently reproduced from what SCE documented, which is the precondition for any intervenor or the Commission testing the prioritisation.

SPD’s more consequential finding is comparative: SCE’s operating-cost assumptions depress covered conductor’s reported benefit-cost ratio relative to undergrounding, and differences in unit-cost inputs may distort the comparison further. A separate formula error double-counts undergrounding’s operating costs, which SPD treats as discrete arithmetic rather than a source of comparative bias. The same covered-conductor-versus-undergrounding question drives the SB 884 cost-recovery PD carded in this period.
A.24-06-001 · PD Oct 15, 2026 · Proposed Decision · Comments Nov 4 · Earliest Nov 19

Proposed Decision Would Let SDG&E Recover $3.02M of Stranded Green Tariff Costs From Former Participants Only

A proposed decision would authorise SDG&E to recover $3.02 million of stranded Green Tariff and Shared Renewables procurement costs from former program participants. It denies with prejudice recovery of a net $1.59 million of administrative and outreach costs, which shareholders must absorb, and rejects SDG&E’s proposal to spread the costs across all distribution customers through the Public Purpose Program surcharge, finding that state law prohibits shifting GTSR costs to non-participants. Former participants would pay in proportion to consumption while enrolled, with residential charges capped at one standard deviation above the mean usage-based charge and the excess reallocated to non-residential participants. Recovery runs five years by default, with a 10-year option on request.

► Details
The PD protects non-participants from costs stranded by a discontinued voluntary program, at the price of billing former participants years after they left it. It finds SDG&E neither managed the program imprudently nor unreasonably delayed seeking recovery; the denial of administrative and outreach costs rests on failure to show those specific expenditures were reasonable.

The residential cap limits household exposure but transfers the remainder to former commercial and industrial participants. Actual per-customer charges stay undetermined until SDG&E’s implementing advice letter is reviewed.
Microgrids / Storage · PD Oct 2026 · Proposed Decision · Earliest Dec 3

Proposed Decision Would Extend the 150% Solar-Paired Battery Sizing Waiver to 2030

A proposed decision would extend the temporary waiver of the 150% storage sizing limit for large solar-paired battery systems until January 1, 2030, partially granting a petition from the California Solar & Storage Association. The rule caps the power rating of storage devices larger than 10 kW AC at 150% of the paired solar generator’s capacity without restricting stored energy. CALSSA sought permanent removal; the Commission agrees with PG&E that more analysis is needed of distribution upgrade costs, whether larger batteries generate more export credits, and whether Rule 21 fees cover interconnection costs. The waiver continues pending the Net Billing Tariff evaluation, with PG&E, SCE and SDG&E filing tariff updates within 30 days of a final decision.

► Details
CALSSA reports that 39% of NBT-paired storage installations between February and April 2025 exceeded the 150% threshold, so the waiver is load-bearing for a substantial share of the market rather than an edge case.

One drafting problem worth watching: the PD’s discussion defers permanent removal and new grid-upgrade cost-responsibility requirements pending further analysis, but an ordering paragraph appears to impose those cost obligations on qualifying systems. The conflicting language leaves it unclear whether affected customers become responsible for distribution upgrades under the extended waiver — the kind of ambiguity that is far cheaper to fix in comments than in a petition for modification.
Res. E-5484 · Adopted Oct 29, 2026 · Resolution · Electric Rule 2 Exception

Commission Approves PG&E Rule 2 Exception for Redundant Service to an Unnamed Cupertino Customer

The resolution approves PG&E’s request for exceptions to Electric Rule 2 to provide two redundant electric services to an unnamed customer in Cupertino, involving upgrades to Stelling Substation and associated distribution facilities to supply backup service from a different substation than the customer’s existing feed from Wolfe Substation. PG&E designs and installs the facilities; the customer pays actual construction costs rather than estimates, billed as work progresses, plus ongoing ownership charges or an equivalent one-time payment, and is not eligible for refunds on the special facilities. PG&E sought expedited approval for a requested October 2027 in-service date. The resolution identifies no direct cost to existing ratepayers.

► Details
Actual-cost billing is the ratepayer protection here: it shields existing customers from construction overruns while preventing the customer from paying an estimate above actual expense. The Commission cited a prior exception allowing actual-cost billing to relocate PG&E facilities for a state levee project, but this one concerns a private customer seeking substation-level redundancy.

The customer’s identity, project cost and negotiated terms remain confidential and the advice letter drew no protests, so there is little public scrutiny of the terms. Substation-level redundancy in Cupertino at this scale is the profile of a large technology load, and the structure — actual costs, no refunds, ownership charges — is a useful comparison point against the terms being negotiated in the Google agreement under Res. E-5455.
Res. UEB-018 · Adopted Oct 29, 2026 · Resolution · Enforcement Settlement

SCE Settles COVID Deposit Violations for $7.77M; 65,773 Customers Improperly Billed

The resolution approves a $7.77 million settlement between SCE and the Commission’s Consumer Protection and Enforcement Division over alleged violations of COVID-19 restrictions on deposits to establish or re-establish electric service. Regulators alleged SCE improperly billed 65,773 residential customers about $10.48 million in deposits between April 2020 and August 2021, of which 19,667 customers paid roughly $2.96 million. The shareholder-funded settlement provides $3.12 million in customer credits — $100 for customers who paid and $25 for those billed who did not — plus $3.95 million to SCE’s Energy Assistance Fund and $700,000 to the state General Fund. SCE had previously credited customers who paid deposits and says the billing problems are corrected.

► Details
The problems arose during a billing-system transition that prevented SCE from promptly disabling deposit charges. Manual corrections followed: nearly 24,000 customers were billed deposits after February 2021, but only seven paid — which indicates the corrective measures substantially reduced actual collections even as the billing continued.

For comparison, the $7.77 million settlement exceeds the $2.7 million SoCalGas paid in a comparable 2023 enforcement settlement despite SCE billing fewer customers. The distinction regulators drew: SoCalGas stopped assessing residential deposits after a December 2020 enforcement resolution, while SCE continued billing them through August 2021. The agreement resolves the allegations without an admission of wrongdoing.
PG&E CPIM · Scoping Memo Oct 2026 · Scoping Memo · $26.63M Shareholder Award

Scoping Memo Issued on PG&E’s $26.63M Gas Procurement Incentive Award — the First Under the Post-Price-Spike Rules

Commissioner Christine Harada issued a scoping memo for reviewing PG&E’s request for a $26.63 million shareholder award under its Core Procurement Incentive Mechanism for November 2022 through October 2023. The CPIM rewards PG&E for buying and transporting gas for core customers at or below prevailing market prices. Two issues are scoped: whether the award was calculated in accordance with applicable decisions and tariffs, and whether it should be approved. Cal Advocates, which protested the application in August, files its monitoring and evaluation report by December 30; comments are due February 1, 2027, replies February 19, with a proposed decision expected in the first quarter of 2027.

► Details
This is the first CPIM award to run through the application process established by D.26-02-058, which the Commission adopted in February 2026 after examining the 2022–2023 winter gas price spike. That decision requires PG&E to seek CPIM awards by formal application rather than advice letter and adds annual reporting.

The award period covers the price spike itself, which is what makes it awkward: the mechanism pays shareholders for procuring below market during the window when market prices were the subject of a Commission investigation. Cal Advocates’ report will drive whether the calculation holds.
RNG Vehicles · Decision Oct 29, 2026 · Adopted · Gas Line Extension Allowances

Commission Approves $2.79M of Gas-Line Extension Allowances for Four SoCalGas RNG Refuelling Projects

The decision approves approximately $2.79 million in gas-line extension allowances for four SoCalGas renewable natural gas refuelling projects under the exception process created when the Commission eliminated gas line extension subsidies effective July 2023. The approved projects serve a bus fleet, refuse collection and commercial hauling. Three of the original nine dropped out, and two public fuelling stations were denied allowances for failing to show that alternatives to natural gas were infeasible, though they may reapply. The decision also approves a revised non-residential allowance multiplier of 3.1 and a new two-way balancing account. Customers pay extension costs upfront, with approved allowances applied after a three-year review of actual gas usage.

► Details
The Commission accepted specific operational evidence rather than a general decarbonisation argument: that electric refuse trucks could not meet certain operators’ range and payload requirements, that battery-electric trucks were impractical for a hauler running 280–550 mile routes, and that an existing RNG bus fleet needs continued fuelling while transitioning to zero-emission by 2040.

It rejected the arguments that every project needs a zero-emission transition plan and that stranded-asset risk alone justifies denial. The two public fuelling stations failed on evidence, not principle, and the Commission declined Sierra Club’s request to deny them with prejudice — so the test is demonstrated infeasibility of alternatives, project by project.
SDG&E EVIMA · Decision Oct 29, 2026 · Petition Denied · EV Charging

Petition to Lift SDG&E’s $7.58M EV Infrastructure Funding Cap Denied on Procedural Grounds

The Commission denied a petition by clean-transportation groups, charging companies, Tesla, Walmart and the City of San Diego seeking to eliminate the $7.58 million funding cap on SDG&E’s Electric Vehicle Infrastructure Memorandum Account. Petitioners argued the cap had led SDG&E to seek to close its Rule 45 EV infrastructure program to new applications and terminate contracts for projects without a Notice to Proceed. SDG&E supported the petition, but the Commission concluded petitioners had failed to show new or changed facts warranting modification of the 2024 general rate case decision and had improperly raised alleged legal errors after the rehearing deadline. The cap stays, and the decision points to SDG&E’s pending 2028 GRC as the venue.

► Details
The Center for Sustainable Energy told the Commission the cap was reached just eight months after adoption, and several San Diego-area governments said the Rule 45 closure threatened their ability to comply with California’s Advanced Clean Fleets requirements.

The Commission resolved the petition almost entirely on procedure without reaching whether the cap conflicts with state electrification policy. That leaves the substantive question open for the 2028 GRC but provides no interim relief — an outcome that turns on the difference between a petition for modification and a timely application for rehearing.
Prior Period
Oct 1 – Oct 15, 2026
21 items
D.26-10-036 · D.26-10-037 · D.26-10-038 · Voted Oct 8, 2026 · Rehearing Orders · 2026 ERRA

Rehearing Denied in All Three 2026 ERRA Cases Over Banked RECs and the RA Benchmark

The Commission denied rehearing of its 2026 Energy Resource Recovery Account decisions for all three large utilities. Each order turns on the same two contested questions: the revised Resource Adequacy Market Price Benchmark methodology adopted in D.25-06-049, and the valuation of pre-2019 banked Renewable Energy Credits — the issue that governs how portfolio costs are split between bundled and community choice aggregation customers. D.26-10-036 covers SCE (A.25-05-008), D.26-10-037 covers PG&E (A.25-05-011 and A.25-09-015), and D.26-10-038 covers SDG&E (A.25-05-012).

► Details
All three were voted October 8 and published October 9.

D.26-10-036 denies rehearing of D.25-12-028, which approved SCE’s amended 2026 ERRA revenue requirement and its 2025 year-end balance using the revised RA benchmark. The contested question was whether pre-2019 banked RECs should be valued at zero, as SCE proposed, or under the RPS-Adder approach CalCCA proposed.

D.26-10-037 denies rehearing of D.25-12-027 on the same two issues for PG&E.

D.26-10-038 corrects a formatting error and denies the San Diego community choice aggregators’ rehearing of D.25-12-008. SDG&E argued the application was an improper collateral attack on D.25-06-049 rather than a challenge to the ERRA decision itself.

The banked-REC valuation question is the same one addressed on the merits in D.26-09-047, carded in the prior period, which affirmed pre-2019 credits at zero and rejected CalCCA’s departed-customer claim as untimely. Because the rehearing orders leave that treatment undisturbed, the allocation between bundled and departed load stands as decided.
D.26-10-035 · Voted Oct 8, 2026 · Rehearing Order · A.23-10-009 · Intervenor Compensation

Limited Rehearing Granted on an Intervenor’s Financial-Hardship Showing

The Commission granted limited rehearing of D.25-09-024, directing the assigned ALJ to reconsider whether Community Legal Services demonstrated significant financial hardship under Public Utilities Code § 1802(h). The order arises in PG&E’s Diablo Canyon Employee Retention Program proceeding (A.23-10-009), which is now reopened for that purpose. Commissioner Matthew Baker was recused.

► Details
The significant-financial-hardship finding under § 1802(h) is a threshold eligibility requirement for intervenor compensation. Because customer-funded intervenor awards are how organizations without their own resources participate in rate proceedings, the standard applied to that showing affects which parties can appear at all.

The rehearing is limited in scope: the Commission did not disturb the balance of D.25-09-024, and the remedy is reconsideration by the ALJ rather than a new decision on the merits. Reopening A.23-10-009 is procedural, confined to the hardship question.
A.26-01-022 · Voted Oct 8, 2026 · Decision · Bear Valley Electric · Memorandum Account

Bear Valley Electric May Track the Gap Until Its 2027 Rate Case Is Decided

The Commission authorized Bear Valley Electric Service to establish a memorandum account tracking the difference between current rates and the final rates set in its 2027 General Rate Case, running from January 1, 2027 until the final decision — now expected in February 2027. The motion was unopposed. The underlying application seeks a test-year 2027 revenue requirement of $78.37 million, an increase of $9.77 million, or 14.25%, followed by increases of $4.11 million (5.24%) in 2028, $3.91 million (4.74%) in 2029 and $6.62 million (7.66%) in 2030.

► Details
The mechanism is the same device the Commission approved for PG&E in A.25-05-009 at the same meeting: the revenue difference accrues from the start of the test year and is trued up once the final revenue requirement is set, so neither side gains from a delayed decision. Authorizing the account does not approve any part of the requested increase.

For Bear Valley’s customers the practical consequence is that a decision issued after January 1, 2027 can still reach back to that date. The cumulative request across the four years is the figure to watch rather than the test-year number alone, and the Commission retains full discretion over the amount it ultimately authorizes.
A.25-04-020 · Issued Oct 12, 2026 · Order Extending Deadline · SoCalGas TIMP

SoCalGas Pipeline-Integrity Cost Case Gets a Deadline Extension

The Commission issued an order extending the statutory deadline in SoCalGas’s Transmission Integrity Management Program cost-recovery proceeding. The extension is consistent with the proposed decision in that case being held from the October 8 meeting to October 29. The pending proposed decision would approve $81.3 million of the recorded costs for 2019 through 2023 and disallow $92.5 million.

► Details
Statutory deadline extensions are routine where a proceeding cannot be completed within the period set by statute, and carry no implication about the outcome. What makes this one worth noting is the timing: the order issued four days after the proposed decision was held, which is the ordinary housekeeping step when an item moves to a later meeting.

The proposed disallowance is the larger of the two numbers in the case, so the October 29 disposition determines whether roughly $92.5 million of recorded pipeline-integrity cost is recovered from customers or absorbed by shareholders. The proposed decision is carded separately in an earlier period.
A.26-06-008 et al. · R.18-04-018 · Oct 1–2, 2026 · Scoping Rulings

Scoping Rulings Open Low-Income Program Review for Six Smaller Utilities

Two assigned-commissioner scoping rulings issued at the start of the period. On October 2, Commissioner Baker issued a scoping ruling across six consolidated applications — A.26-06-008 through A.26-06-013 — covering CARE and Energy Savings Assistance low-income program applications and budgets for program years 2028 through 2033 at Liberty Utilities (CalPeco) Electric, PacifiCorp, West Coast Gas, Bear Valley Electric, Southwest Gas and Alpine Natural Gas, all filed June 12, 2026. On October 1, Commissioner Douglas issued a scoping ruling in the reopened R.18-04-018, which evaluates the Mobilehome Park Pilot Program and considers programmatic modifications.

► Details
The six consolidated applications cover the small and multi-jurisdictional utilities rather than the three large investor-owned utilities, whose low-income programs are set in separate proceedings. CARE provides a bill discount and the Energy Savings Assistance program provides no-cost weatherization and appliance measures, so the 2028–2033 budgets determine the level of assistance available to low-income customers in these service territories for six years.

The Mobilehome Park Pilot Program addresses customers in parks served through master-meter arrangements, where residents have historically lacked direct utility accounts and the associated protections and program eligibility.

Both rulings are published as scanned documents whose text layer cannot be reliably extracted. The proceedings, dates and assigned commissioners above are confirmed from the Commission’s document index and proceeding records; the specific issues placed within scope, the proceeding categorizations and the schedules are not restated here because they could not be read from the filings. Consult the linked rulings directly for those details.
R.15-05-006 · Adopted Oct 8, 2026 · Decision · High Fire-Threat District · Vote 4–0

SCE Fire-Threat Map Gains 47 Areas; All 61 Proposed Removals Rejected

The Commission adopted a decision partially granting SCE’s petition to modify the High Fire-Threat District map. It approves the 47 areas SCE asked to add — about 208 square miles — and rejects all 61 areas it asked to remove, about 168 square miles. The Commission found the additions warranted stricter wildfire protections, and found SCE had not shown that risk in the removal areas had declined enough to drop existing requirements. SCE must apply the fire-safety rules adopted in D.17-12-024 — inspection frequency, vegetation clearance and correction timeframes — in the newly designated areas by January 1, 2027, must file a Tier 1 advice letter within 30 days to update the map, and must demonstrate the reasonableness of any incremental compliance costs.

► Details
The decision carried 4–0, with Commissioner Matthew Baker recused. The Commission also directed a workshop in 2027 on future map revisions. This is the adopted disposition of the proposed decision carded in the August archive.

Assigned Commissioner Karen Douglas said the record relied heavily on SCE’s own wildfire modeling. She noted that when SCE sought map changes in 2019, CAL FIRE took part in the technical review, and said she was advised the Commission now lacks the in-house fire-safety expertise for a comparable assessment. She asked that the workshop be held early in 2027 with CAL FIRE, the Office of Energy Infrastructure Safety, utilities and other wildfire experts.

President John Reynolds supported caution in removing existing protections, citing uncertainty about wildfire behavior while noting the substantial costs borne by ratepayers. Commissioner Darcie Houck questioned the rejection of the removals, citing SCE’s investment in wildfire science and an estimated $8 million to $11 million in potential ratepayer savings, and reserved the right to file a concurrence. Commissioner Christine Harada, who lives in the wildland-urban interface, said she was familiar with many of the areas proposed for removal and supported retaining the existing protections.

The Public Advocates Office had generally supported SCE’s proposed changes. The decision cites the tier-classification criteria from D.20-12-030 without specifying what evidence would justify removing an area. SCE had sought either a temporary Tier 2 advice-letter process or a 2026 workshop; the Commission kept the existing petition process and set the workshop for 2027, leaving unresolved how future removal requests will be evaluated independently and what evidence will suffice.
A.25-04-014 · Adopted Oct 8, 2026 · Decision · Energy Efficiency · Vote 4–1

SDG&E Must Keep Running Its Regional Energy Efficiency Programs

The Commission adopted a decision denying SDG&E’s request to stop administering its regional energy efficiency programs from 2027 through 2032, and rejecting the settlement SDG&E had reached with the Public Advocates Office. SDG&E estimated that ending the programs would cut bill collections by up to $300 million over six years, while its own testimony forecast at least $286 million in lost system benefits — leaving roughly $14 million in net savings on the Commission’s calculation. SDG&E must continue running its regional portfolio, including codes and standards programs, though the Commission encouraged it to revise or eliminate underperforming programs.

► Details
The vote was 4–1. SDG&E’s regional resource acquisition programs reached a cost-effectiveness ratio of 1.05 in 2025, above the required 1.0 threshold and up from 0.66 in 2022. This is the adopted disposition of the proposed decision carded in the prior period.

Assigned Commissioner Darcie Houck said no commissioner disputed the need for cost-effective programs, but that SDG&E’s application was not the right venue for evaluating program administration — those issues belong in the energy efficiency rulemaking and should be considered across all utilities. She added that nothing in the record showed the San Diego Regional Energy Network (SDREN) or community choice aggregators could take over SDG&E’s required programs. Commissioner Karen Douglas said SDREN’s programs were never designed to run independently of utility-administered programs, and that any transfer would require assessing the successor administrator’s readiness. Commissioner Christine Harada emphasized preserving access for small businesses and for customers struggling with energy costs who do not qualify for income-based assistance.

Commissioner Matthew Baker dissented. He said the regional programs have averaged a 0.87 total resource cost ratio since the Commission segmented portfolios in D.21-05-031, and read the same $14 million figure as a net loss — ratepayers contributing $300 million to receive about $286 million in benefits. Citing Cal Advocates’ testimony, he said SDG&E’s cost per kilowatt-hour saved rose 270% from 2021 to 2024. He also noted that about 0.5% of customers participate in regional programs annually while all customers pay for them, including CARE and FERA households, and that two CCAs now serve roughly 85% of retail load. He urged SDG&E to file an advice letter eliminating non-cost-effective programs, and asked staff to examine cost escalation and program overlap with SDREN.

President John Reynolds said the $300 million in potential bill reductions warranted scrutiny but was “just one side of the ledger,” and that the Commission must verify whether SDG&E’s recent cost-effectiveness improvements are sustainable or are the outlier SDG&E and Cal Advocates contend. He also acknowledged that under volumetric rates, program participants see savings sooner than non-participants, who may wait years.
R.24-10-005 · Adopted Oct 8, 2026 · Decision · General Order 95 · Effective Jan 1, 2028

Overhead Line Design Rules Convert to Load and Resistance Factor Design

The Commission adopted a decision replacing Working Stress Design with Load and Resistance Factor Design under General Order 95, which governs overhead electric and communications facilities. The new method applies separate factors to structural loads and to material strength, letting the Commission adjust for individual conditions such as wind. The initial conversion preserves existing safety requirements and takes effect January 1, 2028 — six months later than originally proposed.

► Details
The decision rejects a utility proposal to allow continued use of Working Stress Design calculations for existing lines when new calculations are required under GO 95, and keeps existing lines subject to future changes in load and strength factors. Utilities prevailed in removing language that would have expanded the maintenance rule, over objections from the Safety and Enforcement Division; the decision also rejects SED’s objections to revised material-strength language. This is the adopted disposition of the proposed decision carded in the earlier period.

A related attachment converts about 40 rules and the supporting engineering examples to the new terminology. A follow-up workshop within 24 months will consider additional changes.

Commissioner Matthew Baker described the proceeding as “a no drama way to update our general orders” and credited ALJ Joanna Perez-Green and the Safety and Policy Division for managing it. The conversion changes little in engineering terms on its own. The cost consequences arrive if and when the Commission revises the load and strength factors, as it previously did in response to wildfire risk in D.14-02-015. Because existing lines remain subject to those future changes, the eventual scope of work on in-place poles and lines — and the cost recovered from ratepayers — is unresolved.
Res. E-5476 · Adopted Oct 8, 2026 · Resolution · Avoided Cost Calculator

2026 Avoided Cost Calculator Adopted, With Higher Greenhouse Gas Values

The Commission adopted Resolution E-5476, putting the 2026 Avoided Cost Calculator into use for testing whether distributed energy resource programs are cost-effective. Against the 2024 version, avoided costs rise on average, driven partly by higher greenhouse gas values reflecting expiring federal renewable-energy tax credits and tariffs on imported solar and storage equipment. Energy avoided costs decline as renewable generation grows. The update applies a common GHG value to electricity and gas, removes GHG rebalancing, and revises generation capacity calculations using hybrid solar-plus-storage resources.

► Details
Because the calculator sets the benchmark for program cost-effectiveness, its inputs determine which programs ratepayers fund. This is the adopted disposition of the draft resolution carded in the earlier period.

After stakeholder comments, Energy Division added scarcity-price adjustments, corrected a formula that had reversed two societal carbon-cost scenarios, and raised PG&E’s marginal transmission capacity cost from $53.98 to $63.61/kW-year using a value proposed in PG&E’s pending General Rate Case Phase 2 proceeding (A.24-09-014). Energy Division declined requests to revise storage valuation, transmission project selection, low-load energy prices, and gas and allowance price forecasts.

The greenhouse gas value was contested. Higher GHG values improve the calculated economics of electrification and other distributed resources. In comments on the draft, the California Large Energy Consumers Association calculated that the adopted values exceed the high societal cost of carbon in 19 of 20 years and urged the Commission to consider a cap in the 2028 update. SoCalGas opposed a cap but questioned the underlying methodology. Energy Division said it may revisit these issues in future updates but made no commitment.
R.19-03-009 · Adopted Oct 8, 2026 · Decision · Direct Access · Rulemaking Closed

Direct Access Expansion Petition Denied and the Rulemaking Closed

The Commission denied a petition by six retail-energy and large-customer interests that sought to reverse its 2021 recommendation against expanding Direct Access and instead recommend that the Legislature lift the program’s cap. The decision denies the petition under Rules 16.4(b) and 16.4(d), finding inadequate evidentiary support for its factual claims and insufficient justification for filing nearly five years after the 2021 decision. It closes R.19-03-009. The Commission did not reach the merits of expansion, leaving unresolved statutory questions — including cost shifting between Direct Access and bundled customers — for a fuller record.

► Details
The petitioners argued that electric service providers have improved their resource adequacy and renewable-procurement performance, that RA scarcity has given way to surplus, and that growing data-center demand warrants expanded retail competition. They cited the Commission’s 2026 Integrated Resource Planning decision (D.26-02-057), which requires ESPs to procure a share of 6 GW of new renewable capacity for anticipated load growth, and argued the Direct Access cap prevents ESPs from serving much of that load. This is the adopted disposition of the proposed decision carded in the earlier period.

The decision concludes that limits on ESPs serving new load, and load-based procurement obligations, were known or should have been known within one year of the 2021 decision — agreeing with SDG&E that the 2021 mid-term reliability decision (D.21-06-035) already used load-based procurement allocations.

With R.19-03-009 closed, proponents seeking another Commission review would need a new procedural vehicle such as a petition for rulemaking, or could pursue legislation to lift the cap directly. Because the denial rests on evidentiary and timeliness grounds, the cost-shifting question between Direct Access and bundled customers remains undecided.

Separately, four of the petitioners filed a same-day application for rehearing challenging D.26-02-057’s allocation of procurement obligations to ESPs. This decision does not resolve that application.
Res. E-5483 · Adopted Oct 8, 2026 · Resolution · Diablo Canyon · PG&E AL 7860-E

PG&E’s $1.22B Diablo Canyon Costs Found Reasonable; TURN Protest Denied

The Commission adopted Resolution E-5483, approving $1.22 billion in PG&E Diablo Canyon extended operations costs for September 2023 through December 2025 and denying a protest by TURN. The resolution, which disposes of PG&E Advice Letter 7860-E, finds the costs fall below the statutory 115% threshold for further reasonableness review under both the original $1.33 billion forecast and a revised $1.19 billion forecast reflecting updated resource adequacy market benchmarks. Spending exceeded the revised projection by 2.6% but stayed $148 million below the review threshold. No additional rate increase is authorized.

► Details
TURN argued that a $132.2 million reduction in resource adequacy substitution costs — the result of a Commission methodology change rather than of PG&E’s own management — masked higher spending on O&M and on plant equipment and improvements. TURN asked the Commission to apply the 115% threshold separately to individual cost categories. The resolution rejects that request, finding that no category exceeded 115% during this period, and deems PG&E’s recorded costs reasonable. This is the adopted disposition of the draft resolution carded in the earlier period.

The reasoning and the formal findings diverge slightly. The resolution’s discussion treats TURN’s category-by-category test as unsupported by statute, while its findings deny the protest on the narrower ground that the test would not change the outcome here; the resolution cites past Commission practice in support of the aggregate approach.

Whether a different cost mix could warrant another approach is left open. TURN identified an extended unplanned outage as one such scenario, in which reductions in fixed management and performance fees could offset — and therefore shield from review — overspending on costs within PG&E’s control.
A.25-05-004 · Adopted Oct 8, 2026 · Decision · Customer Information System

SoCalGas Denied $24.9M in Extra Billing-System Funding

The Commission adopted a decision denying SoCalGas’s request for $24.9 million in additional operations and maintenance funding for its Customer Information System Replacement Program. It finds insufficient evidence that costs will exceed the $46.9 million already authorized for 2024–2027 in the 2024 SoCalGas/SDG&E General Rate Case decision (D.24-12-074). The existing authorization stays intact, and the Commission determined that denying the additional funding would not delay the project.

► Details
SoCalGas spent $8.463 million in 2024, below the $10 million authorized for that year and, according to the Public Advocates Office, about half its own forecast. The decision finds SoCalGas failed to substantiate its projected spending with finalized vendor contracts. This is the adopted disposition of the proposed decision carded in the earlier period.

The decision also rejects a settlement with Small Business Utility Advocates that would have cut the request to $21 million and established a two-way balancing account. The Commission concluded the settlement was unreasonable, was inconsistent with Public Utilities Code Section 451, and lacked the comparison exhibit required by Rule 12.1 of the Commission’s Rules of Practice and Procedure.

Cal Advocates and SBUA both opposed the full request, though SBUA had negotiated the settlement that would have allowed SoCalGas to seek up to $21 million. The outcome leaves customers paying only the previously authorized amount, with the absence of finalized contracts the decisive evidentiary gap.
A.25-05-009 · Adopted Oct 8, 2026 · Decision · Revenue Tracking · Uncontested Motion

PG&E May Track 2027 Rate Case Revenue Differences Back to January 1

The Commission adopted a decision granting an uncontested motion PG&E filed January 12, 2026, allowing it to capture the difference between revenues authorized under its 2023 General Rate Case and those ultimately approved for 2027, regardless of when the Commission finishes its review. The decision does not approve PG&E’s requested increase or commit the Commission to any amount; it preserves the Commission’s authority to set the final revenue requirement while letting the resulting adjustments apply back to January 1, 2027.

► Details
PG&E may use three existing memorandum accounts — covering gas distribution; electric distribution and generation; and gas transmission and storage — to track and recover overcollections or undercollections. Adjustments will carry interest at the Federal Reserve’s three-month commercial paper rate, as needed to keep ratepayers and shareholders financially indifferent to the timing of the final decision. PG&E must file a Tier 1 advice letter within 14 days of the decision’s effective date to update its Tariff Preliminary Statement. This is the adopted disposition of the proposed decision carded in the August archive.

For customers, the practical effect is that once the Commission adopts the 2027 GRC, bills may carry an adjustment covering several months of accumulated revenue differences, plus interest on amounts collected above or below the final authorized level. The mechanism cuts both ways and is designed to remove either side’s incentive to benefit from a delayed decision.

The size of any adjustment is unknown while the underlying rate case remains unresolved, and the Commission retains full discretion over how much PG&E can ultimately collect.
R.25-01-005 · Adopted Oct 8, 2026 · Decision · DAC-SASH

Low-Income Solar Program Modified; Battery Storage Declined

The Commission adopted a decision authorizing PG&E, SCE and SDG&E to cover up to $2.35 million in projected administrative and outreach expenses through 2030 using interest accrued in their Disadvantaged Communities – Single-Family Solar Homes balancing accounts, subject to annual budget approval. The decision also orders SDG&E to return $306,056 to its greenhouse gas revenue account — $280,000 in excess administrative funding plus $26,056 in interest — and limits future transfers to its authorized allocation. The Commission declined to expand the program to include battery storage.

► Details
The changes preserve the program’s $10 million annual budget and its $3-per-watt solar incentive. The utilities had accumulated $3.59 million in interest through 2025 — enough to cover projected remaining administrative expenses without drawing on the program’s administrative budget. This is the adopted disposition of the proposed decision carded in the earlier period.

The decision requires program administrator GRID Alternatives to report outside funding at the project level, with $50,000 available for reporting improvements, to submit an implementation plan within 90 days, and to begin reporting in its first-half 2027 report. The reporting will disclose aggregate outside funding for individual projects; GRID Alternatives need not identify donors.

The accompanying handbook removes workforce training and energy-efficiency education requirements, allows meter socket adapters as eligible equipment, and prohibits combined incentives from exceeding project costs. Declining battery storage keeps the program focused on rooftop solar until reservations close at the end of 2030.
Res. E-5472 · Adopted Oct 8, 2026 · Resolution · SCE AL 5709-E · SDG&E AL 4772-E

Meter Socket Adapter Fees Must Be Publicly Posted

The Commission adopted Resolution E-5472, approving SCE Advice Letter 5709-E and, with modifications, SDG&E Advice Letter 4772-E, and requiring greater transparency for the fees utilities charge when their personnel install or remove meter socket adapters. These devices let customers add EV chargers and batteries without a panel upgrade or a larger service line. PG&E currently charges $275 and SCE $279.22. SDG&E has 60 days to disclose its fee online, and all three utilities must keep their fees publicly posted.

► Details
The utilities have 60 days to add their fees to their tariffs and 90 days to jointly propose a fee calculation methodology. Future fee updates will require Tier 3 advice letters unless the Commission authorizes a simpler process. This is the adopted disposition of the draft resolution carded in the earlier period.

These installation charges currently lack an approved calculation methodology, so the amounts customers pay have not been tested against utility cost. PG&E and SCE sought lighter procedures for routine fee updates; the Commission is requiring an approved formula first. Its review of the joint methodology filing will determine whether future adjustments can proceed with less scrutiny.

The charges matter for electrification access: a meter socket adapter is the alternative to a full panel upgrade for customers adding an EV charger or battery, so the fee sits directly in the path of the lower-cost option.
Res. E-5469 · Adopted Oct 8, 2026 · Resolution · BioRAM · Price Above Benchmark

PG&E’s Burney Biomass Contract Extended Five Years at an Above-Benchmark Price

The Commission adopted Resolution E-5469, approving a five-year extension of PG&E’s Bioenergy Renewable Auction Mechanism (BioRAM) power purchase agreement with Burney Forest Products, a 29-MW biomass facility in Shasta County, through October 31, 2032. The amended price exceeds the existing contract price, which serves as the Commission’s per se reasonableness benchmark. The resolution finds it comparable to offers for other clean baseload resources and more favorable to customers than Burney’s earlier proposals. Bundled, CCA and direct access customers all pay through the Tree Mortality Non-Bypassable Charge.

► Details
The extension follows negotiations required under Assembly Bill 2750 and Resolution E-5376. AB 2750 required PG&E to negotiate an extension; it did not require accepting a price above the existing contract. Negotiations ran past the 180-day deadline, and the Commission approved an above-benchmark price to keep the agreement in place.

An independent evaluator rated the amended price very high relative to competing resources, but reasonable against comparable biomass and baseload generation. The evaluator rated project viability high and portfolio fit moderate, and found that continued operations support state bioenergy policy goals and economic activity in a low-income, high-unemployment community.

The contract price is confidential. Under the Commission’s confidentiality rules it should become public no later than April 2028, which means customers paying the Tree Mortality Non-Bypassable Charge will not see the price until the extension is more than a year under way.
2026 Market Price Benchmarks · Issued Oct 2026 · Energy Division · PCIA Inputs

2026 Market Price Benchmarks Set the 2027 PCIA — RPS Adder Falls to $30.88/MWh Against a $62.45 Forecast, and to $12.69 for 2027

The CPUC’s Energy Division issued the 2026 Market Price Benchmarks used to calculate the 2027 Power Charge Indifference Adjustment, and the renewable values fall sharply. The final 2026 RPS adder is $30.88/MWh, against a 2026 forecast of $62.45 and a 2025 final benchmark of $63.86; the 2027 forecast drops further to $12.69/MWh. The forecast 2027 Resource Adequacy adder declines to $10.02/kW-month from a 2026 forecast of $11.53. Energy benchmarks also fall, and for 2027 off-peak prices sit above on-peak at all three utilities — $46.59 vs $44.22/MWh for PG&E and $44.89 vs $34.41 for SCE and SDG&E. The benchmarks feed the utilities’ October updates to their 2027 ERRA forecast applications.

► Details
The PCIA is calculated as eligible portfolio costs less the market value credited to those portfolios, so a lower benchmark reduces the credit and tends to increase the indifference amount, all else equal. Pressure arrives from both directions this cycle: on the true-up side the 2026 final RPS benchmark came in at $30.88/MWh against a $62.45 forecast and the final RA benchmark fell to $10.11/kW-month from $11.53; on the forecast side the 2027 RPS value drops again to $12.69 and RA to $10.02.

Energy Division set the 2027 GHG-free benchmark at $0 because only 275 GWh qualified. That value is informational only, since the investor-owned utilities allocate the attributes directly rather than monetising them through the benchmark. Energy Division stated separately that it will examine whether the GHG-free adder accurately reflects incremental value, and will take that question up in the PCIA rulemaking.
A.26-09-019 · Oct 2026 · Trigger Filing · Scoping Ruling Oct 2 · PHC Oct 19

SCE Asks the CPUC to Leave ERRA Rates Unchanged Despite a $236.9M Overcollection That Crossed Both the 4% Trigger and the 5% Statutory Threshold

SCE is asking the Commission to make no interim ERRA rate change despite a $236.9 million overcollection that crossed both the 4% trigger point and the 5% statutory threshold, attributing the balance mainly to lower-than-forecast wholesale power and gas prices. SCE says its 2027 ERRA Forecast rates will bring the balance below both limits when they take effect January 1 — which is 123 days after the trigger, three days past the 120-day self-correction window. SCE asks that the trigger case be consolidated with its 2027 ERRA Forecast application (A.26-05-006) or dismissed as moot. A prehearing conference on October 19 will consider consolidation.

► Details
Assigned Commissioner Matthew Baker set an expedited schedule and directed SCE to file party positions on whether the case can be dismissed under Rule 2.8. Separately, ALJ Brandon Gerstle ordered SCE to fold the trigger analysis into its October Update in the forecast case, and told parties to raise trigger issues there. Both rulings therefore move the substance into the 2027 forecast proceeding ahead of any formal consolidation, and Baker’s ruling also invites dismissal of the standalone trigger case.

The rate effect SCE illustrates is modest: a 1.7% reduction to average bundled rates, with an average non-CARE residential customer using 500 kWh saving about $2.77 a month, or 1.5%. The January 1 date depends on a December 17 final decision in the forecast case; if that slips, the self-correction argument weakens.

For comparison, PG&E reported a $225 million ERRA overcollection in September that breached the 5.4% trigger without a requested rate change — carded separately in the prior period.
A.25-06-017 · Held to Oct 29, 2026 · Proposed Decision · Mountain View Fire · First AB 1054 Covered-Wildfire Case

Liberty Utilities — $58.05M of a $77.4M Mountain View Fire Request Allowed; 25% Assigned to Shareholders Over a Missed PSPS Protocol

A proposed decision would allow Liberty Utilities to recover about $58.05 million in costs tied to the 2020 Mountain View Fire, plus up to $3.375 million in additional financing costs and 75% of five unresolved claims, through a five-year customer surcharge. This is the first covered-wildfire case governed by Assembly Bill 1054. The PD finds Liberty prudently designed, maintained and operated its system and that its wildfire programs conformed to regulatory requirements, while also finding that the utility failed to follow its own tactical PSPS protocol as winds intensified. Because factors within Liberty’s control exacerbated the fire’s costs, the PD assigns 25% of claimed costs to shareholders rather than granting the full $77.4 million request.

► Details
The Commission did not act on this item at its October 8 meeting; it was held to the October 29 meeting, along with the PG&E–Google data-center resolution and the competing biomethane cost-allocation proposed decisions.

AB 1054 established the framework governing cost recovery for catastrophic wildfires involving investor-owned utilities, including the prudency standard against which a utility’s conduct is measured. Because this is the first covered-wildfire proceeding decided under that framework, the allocation methodology adopted here is likely to be cited in later cases regardless of the dollar amounts involved.

The structure of the finding is the notable part. The PD does not conclude that Liberty’s system design, maintenance or operation was imprudent, nor that its wildfire mitigation programs fell short of regulatory requirements. The disallowance rests instead on a narrower operational failure — departure from the utility’s own tactical Public Safety Power Shutoff protocol as wind conditions worsened — and translates that into a 25% shareholder share of claimed costs. A utility can therefore satisfy the programmatic requirements and still bear a material share of costs on execution grounds.
A.24-01-020 · Held to Oct 29, 2026 · Proposed Decision · SFPP Terminals · PU Code § 227

SFPP Destination Terminals Are Jurisdictional Pipeline Assets — PD Rejects “Non-Carrier” Treatment and Finds the 2021–2024 Rate Applications Incomplete

A proposed decision finds that SFPP’s connected destination terminals are jurisdictional pipeline assets under Public Utilities Code § 227 and have been dedicated to public use, rejecting SFPP’s treatment of the facilities as nonregulated “non-carrier” assets. The PD concludes the terminals are integral to the transportation, storage, distribution and delivery of refined petroleum products, and that shippers often cannot obtain pipeline service without using them. Because SFPP excluded the terminals’ costs and revenues from its consolidated 2021–2024 rate applications, those applications are incomplete, and SFPP is directed to supplement its cost-of-service showing and to file a tariff covering the terminals going forward.

► Details
The Commission did not act on this item at its October 8 meeting; it was held to the October 29 meeting (Agenda 3588, item 8).

The dispute turns on whether a facility physically connected to a regulated pipeline, and functionally necessary to the service that pipeline provides, can be carried outside the regulated rate base as a separate commercial business. The PD’s reasoning is functional rather than formal: it looks to whether the terminals are integral to the delivery of the product and whether shippers have a practical alternative, and finds on both counts that they are part of the jurisdictional service.

The remedial consequence matters as much as the jurisdictional holding. Excluding the terminals’ costs and revenues from the rate applications means the record does not show the full cost of service, so the pending 2021–2024 applications cannot be decided as filed. SFPP must supplement, and must file a tariff for the terminals prospectively — bringing a previously unregulated revenue stream inside the tariffed framework.
Res. E-5422 · Adopted Oct 8, 2026 · Resolution · Federal Service Contract

SDG&E–Navy 10-Year Service Contract Approved, Running to September 2035

The Commission adopted Resolution E-5422, approving a 10-year master utility services contract between SDG&E and the Navy’s Naval Facilities Engineering Command Southwest, replacing a 2014 agreement. The contract covers gas and electric service to Navy and Marine Corps installations in SDG&E territory. Rates remain under SDG&E tariffs, while certain contract terms differ under the rules governing service to government agencies. The agreement runs through September 17, 2035 and includes an estimated $10.5 million for authorizations beyond basic utility service, including connection charges and studies. Energy Division found the contract consistent with SDG&E’s obligation to serve and with federal and state law; SDG&E is expected to recover its costs through rates.

► Details
The agreement runs September 18, 2025 through September 17, 2035. Master utility services contracts with federal installations are a routine but low-visibility category of CPUC approval. The terms that differ from standard tariff service generally concern billing, liability, termination and dispute resolution, reflecting federal contracting rules rather than any rate advantage. Rates themselves stay tariffed, so the contract does not create a negotiated price.

The $10.5 million estimate covers authorizations beyond basic service — connection charges and studies — rather than the value of commodity service over the ten-year term. Cost recovery through rates means the general body of ratepayers backstops the utility’s performance, which is the standard treatment for obligation-to-serve customers.
Earlier Period
Sep 16 – Sep 30, 2026
6 items
A.23-06-008 · PD issued Sep 18, 2026 · Proposed Decision · WMPMA / FRMMA · Earliest vote Nov 19

PG&E Wildfire Mitigation Cost Recovery PD — $1.768B of $2.246B Authorized; $477M (21%) Disallowed as Not Incremental or Reasonable

ALJ Elaine Lau’s proposed decision would authorize PG&E to recover approximately $1,768.4 million of 2020–2022 costs recorded in the Wildfire Mitigation Plan Memorandum Account and Fire Risk Mitigation Memorandum Account. PG&E recorded about $2.495 billion over the three years — $969 million in expenses and $1.527 billion in capital — then removed $250 million in accounting adjustments to request $2.246 billion. The PD finds roughly $477 million of the recorded costs not incremental or not reasonable, a 21% reduction to the request. Earliest Commission vote: November 19, 2026.

► Details
Of the recorded total, the WMPMA holds $864 million in expenses and $1.480 billion in capital; the FRMMA holds $105 million in expenses and $47 million in capital. The accounting adjustments PG&E removed before filing were $246.296 million of expense and $3.402 million of capital, and include $233.6 million in revenue requirement removed to comply with the $1.823 billion disallowance ordered in the 2020 Wildfire OII decision (D.20-05-019).

Intervenor positions were far apart. TURN recommended disallowing $1.375 billion, about 55% of recorded costs, arguing PG&E failed to carry its burden on incrementality and reasonableness; counting the D.20-05-019 disallowance, TURN would have capped recovery at $870.5 million, or 39% of the request. Cal Advocates recommended disallowing $613 million of WMPMA capital and $280 million of WMPMA expenses, plus $5 million of FRMMA capital and $22 million of FRMMA expenses. The Energy Producers and Users Coalition and Indicated Shippers argued that spending pursuant to an approved wildfire mitigation plan does not by itself establish that the spending was prudent or affordable.

The PD adopts neither extreme. Its recurring test is whether a cost was genuinely incremental to the 2020 General Rate Case authorization and separately whether it was reasonably incurred — a cost can clear the first and fail the second. Overhead Patrols illustrate the point: the full $6.072 million recorded in MAT BFA is disallowed as unreasonable even though the PD finds the costs incremental, because PG&E performed 4,023,363 base units against 4,476,868 authorized in the GRC. The Overhead Electric Distribution Asset Inspections category recorded $207.332 million in total, of which TURN sought $184.092 million in disallowances.

PG&E has already been collecting against this request in interim rates: D.24-03-006 authorized 75% of the $688 million revenue requirement, or $516 million, and $428.9 million for Track One costs. The proceeding also covers electric modernization and gas safety work performed primarily in 2022, which this PD does not resolve.
R.26-09-009 · Opened Sep 17, 2026 · Rulemaking · Regional Markets / AB 825

CPUC Opens the AB 825 Regional-Market Rulemaking — Decision Targeted for Q3 2027, Markets No Earlier Than January 2028

The Commission opened R.26-09-009 on September 17 to implement Assembly Bill 825 and determine whether PG&E, SCE and SDG&E may participate in electricity markets governed by an independent regional organization. The statute permits CAISO to operate those markets no earlier than January 1, 2028, subject to statutory conditions, and utility participation requires a CPUC decision finding those requirements satisfied. All three utilities are respondents. The preliminary schedule calls for a decision in the third quarter of 2027.

► Details
The proceeding will examine protections for state authority over procurement, resource adequacy, environmental and reliability policies and utility oversight, along with independent market analysis and governance transparency. A threshold question is whether the Commission’s determination may rely on draft governance documents and tariffs or must await final CAISO resolutions and FERC-approved tariff changes; the rulemaking also asks whether an interim process is needed if CAISO’s transition advances before the Commission completes its review.

Other issues include procedures for directing utilities to withdraw, CAISO’s ability to provide separate market services after withdrawal, and authorization of additional regional-organization products including a potential resource adequacy program. The CPUC will coordinate with the California Energy Commission to prevent the transition from expanding which transactions qualify for RPS content categories, measured against a December 31, 2025 baseline.

The order does not resolve whether the Q3 2027 decision will itself authorize participation or instead establish the process for a later determination. Requiring final governance documents and FERC-approved tariffs would compress the interval before the earliest permitted January 2028 launch. The withdrawal questions bear directly on how readily the Commission can exercise retained authority, since utilities are separately required by statute to participate in CAISO.
D.26-09-047 · Adopted Sep 17, 2026 · Decision · PCIA / Banked RECs

PCIA Banked RECs — Pre-2019 Credits Affirmed at Zero; CalCCA’s Departed-Customer Claim Rejected as Untimely

A decision affirms zero-dollar valuation of renewable energy credits generated before January 1, 2019 and banked for later use in PG&E, SCE and SDG&E’s Power Charge Indifference Adjustment calculations. It rejects additional compensation for customers who helped fund those credits but left utility generation service before the credits were used for renewable compliance. The Commission found the credits’ costs and benefits fully allocated under the 2011 methodology adopted in D.11-12-018, which recognized renewable resources’ market value in the year of generation.

► Details
D.19-10-001 shifted REC valuation to the time credits are sold or used, but only for credits generated beginning in 2019. Because customer indifference was already satisfied for the older credits, the decision concludes that another payment would violate cost-shifting prohibitions.

CalCCA sought vintage-specific credits at the current RPS market price benchmark, or allocation of the credits to departed customers’ providers; Cal Advocates and direct-access representatives also supported non-zero valuation. The decision adopts the utilities’ position, rejects four staff alternatives and finds CalCCA’s challenges to the earlier decisions untimely. The final revision limits its separate laches finding to the failure to challenge the 2019 decision.

The decision resolves differing treatment across utilities: PG&E’s 2023–2025 ERRA forecast cases used RPS benchmark valuation, while SCE’s disputed cases used zero-dollar valuation. Uniform zero-dollar treatment applies through the October updates in the utilities’ 2027 ERRA forecast proceedings, affecting 2026 true-ups and 2027 forecast rates without otherwise reopening earlier outcomes. CalCCA executive director Beth Vaughan called the outcome “deeply disappointing,” saying the association had urged the Commission for six years to give CCA customers their share of the value of banked credits they helped pay for.

The reasoning treats the original allocation as complete even where the customers funding a resource and those benefiting from its eventual use differ, which forecloses a further PCIA credit without requiring the Commission to determine the banked credits’ present compliance value.
D.26-09-072 · Adopted Sep 17, 2026 · Decision · Tribal Land Transfer

Tribal Land Transfer Policy Extended to Surplus Utility Property; 60/30/15/90-Day Negotiation Clock Adopted, R.22-02-002 Closed

A decision expands the CPUC’s Tribal Land Transfer Policy to surplus utility property, giving tribes an opportunity to negotiate for ancestral lands before utilities seek other buyers. It covers property removed from rate base because it is no longer necessary or useful for utility service, but exempts land removed to benefit utility operations, such as mitigation for capital projects. Transactions outside Public Utilities Code Section 851 require no new CPUC approval but must comply with the policy. Telecommunications providers remain excluded.

► Details
For each covered transaction a utility must request the Office of the Tribal Advisor’s list of relevant tribes. Tribes receive 60 days to express interest, with a second notice and another 30 days for nonrespondents. A utility must establish a virtual data room within 15 business days after a tribe expresses interest, beginning a 90-day negotiation period; it may then seek other buyers if no agreement in principle exists and none appears reasonably imminent.

Data rooms must contain available property records and a current appraisal, with a broker’s opinion of value permitted temporarily. Confidential cultural information remains subject to legal disclosure restrictions. Electric and gas utilities must report quarterly on dispositions and tribal engagement; water utilities report annually. Competing tribal claims proceed first through discussions among tribes, then through alternative dispute resolution and, if unresolved, to a Commission decision.

The decision also revises tribal consultation responsibilities, establishes quarterly Tribal Information Forums open to all California Native American tribes, and provides for review of the consultation policy every three years. It closes R.22-02-002 while leaving taxation, jurisdiction and infrastructure delays for further engagement. The Commission acknowledged that the Tribal Advisor position is vacant and said it would coordinate with the governor’s office to fill it — a consideration given that implementation rests heavily on that office.
D.26-09-048 · Adopted Sep 17, 2026 · Decision · SGIP

SGIP Rulemaking R.20-05-012 Closed; SCE Medical-Baseline Waiver Preserves $1.7M in Reserved Incentives

A decision closes the Self-Generation Incentive Program rulemaking while implementation and wind-down of the Residential Solar and Storage Equity program continue through 2028; funding allocation ended in June 2026. The decision also waives demand-response enrollment requirements for certain SCE Medical Baseline Exemption customers whose SGIP projects faced expiration because they receive generation service from another provider and could not satisfy the requirement — protecting approximately $1.7 million in reserved incentives. No party opposed the waiver.

► Details
Medical Baseline Exemption customers must preserve stored energy for medical equipment and are excluded from qualifying demand-response programs, which is why the enrollment condition could not be met. The waiver removes that barrier while preserving the customers’ generation-provider choice and MB-E schedule.

The California Solar & Storage Association opposed closing the proceeding, citing payment delays, project deadlines and the absence of the cost-attestation process from the SGIP Handbook. It warned that administrators could reject baseline-supported incentive claims without an open proceeding to resolve disputes, and sought corrective action regarding LADWP’s administration. The decision finds that earlier rulings addressed baseline and payment issues and that existing program mechanisms can handle remaining concerns.

The proceeding therefore closes with program implementation still underway, and the attestation process is not codified in the Handbook; the decision relies instead on existing rules, working groups and staff coordination to address future disputes.
EE Portfolio PD · Issued Sep 2026 · Proposed Decision · Energy Efficiency

PD Would Deny SDG&E’s Exit From Regional Energy-Efficiency Administration — Claimed $300M Saving Reduced to About $14M

A proposed decision would deny SDG&E’s request to stop administering regional energy-efficiency programs from 2027 through 2032, finding the request premature and unsupported by the record. SDG&E estimated that ending the portfolio would avoid $300 million in customer collections over six years, or $1.36 per month for an average residential gas and electric customer. The PD finds that calculation omits SDG&E’s own forecast of at least $286 million in foregone Total System Benefits, leaving roughly $14 million in net savings before longer-term energy, grid and equity benefits. Earliest CPUC vote: October 8.

► Details
Under the PD, SDG&E would remain responsible for its regional portfolio and codes-and-standards programs but could eliminate underperforming programs and rebalance spending. Public Purpose Program charges, which fund energy efficiency and other programs, represent about 1.4% of SDG&E bills.

The PD rejects the argument that regional efficiency has become structurally uneconomic. SDG&E’s resource-acquisition segment achieved a 1.19 Total Resource Cost ratio in 2025, or 1.05 excluding statewide programs; six of seven regional programs had ratios at or near 1.0 in 2024, while the Federal Customer Services Program recorded a 0.03 ratio. Reforming or eliminating weak programs could improve performance without ending the portfolio.

The CPUC has legal authority to select administrators other than utilities, but the PD finds SDG&E did not show that its efficiency targets were infeasible, uneconomic or harmful to public health, nor that the San Diego Regional Energy Network could replace its portfolio — SDREN was designed to supplement SDG&E’s programs, and approximately 8% of SDG&E’s electric customers live outside its coverage. The PD also rejects an SDG&E–Cal Advocates settlement that would have ended SDG&E’s administration of regional programs and codes-and-standards activities.

SDG&E prevailed on the legal question that utilities need not administer regional programs indefinitely, but the improving cost-effectiveness results undercut the factual case for withdrawal. The PD leaves a path for a future exit conditioned on a willing replacement, an orderly transition and a plan to preserve customer and grid benefits.
No matches for selected IOU.

Miscellaneous

Voting-meeting results, agenda previews, advice letters, CAISO and FERC filings, litigation, and other items that are not a formal Application or Rulemaking/Decision.

Current Period
Oct 16 – Oct 31, 2026
6 items
Voting Meeting · Agenda 3589 · Held Oct 29, 2026 · Results · DER Orchestration, $608M DR Bridge

October 29 Voting Meeting Results — IOUs Ordered to Build a Joint DER Plan; Google Data-Center Resolution Held a Sixth Time

The Commission adopted a decision directing PG&E, SCE and SDG&E to hire an outside facilitator, run a stakeholder working group and file a joint distributed-energy-resource orchestration application within 12 months, and to add load flexibility as a fourth scenario in distribution planning. Commissioner Darcie Houck cited utility studies estimating distribution savings through 2040 of $1.8 billion for PG&E, $320 million to $1.38 billion for SCE and $697 million for SDG&E. The Commission also approved D.26-10-053, roughly $608.3 million of demand-response bridge funding for 2028–2029, and granted SoCalGas partial recovery on its Transmission Integrity Management Program. Draft Res. E-5455 — PG&E’s agreement to energize a 250 MW Google data center in San Jose — was postponed again, to November 19.

► Details
Adopted, each carded separately in Proposed Decisions & Rulings: the DER orchestration decision (R.21-06-017, Commissioner Baker recused); the demand-response bridge (D.26-10-053, consent item 22); SoCalGas’s TIMP cost recovery (A.25-04-020); the mandatory climate-adaptation framework; the denial without prejudice of SoCalGas’s microgrid tariff; the Sempra utilities’ SAP memorandum account; approximately $2.79 million of RNG gas-line extension allowances; the denial of the SDG&E EVIMA petition; Res. E-5484 (PG&E Rule 2 exception, Cupertino); and Res. UEB-018 (SCE’s $7.77 million COVID deposit settlement).

Held to November 19: Draft Res. E-5455 (Google, now deferred at six consecutive meetings); the competing biomethane cost-allocation proposed decisions; Draft Res. E-5474 on the Database for Energy Efficient Resources; Draft Res. G-3622, $44.6 million of California Energy Commission natural-gas research funding; Liberty Utilities’ request to recover about $58.05 million tied to the 2020 Mountain View Fire; a PD approving a settlement on SDG&E’s remaining Track 3 wildfire costs and partial Pipeline Safety Enhancement Program recovery for SDG&E and SoCalGas; and the PD on PG&E’s interim revenue requirement of up to $456 million from January 1, 2027. From the dais, Commissioner Matthew Baker separately held the PD on the jurisdictional status of SFPP’s connected destination terminals under PU Code § 227.

Two corrections to CalReg’s prior-period coverage. First, the Draft Res. G-3622 figure is $44.6 million in total, not $24 million for each of two fiscal years. Second, the SoCalGas TIMP outcome is not the proposed decision’s $81.3 million approval: Commissioner Houck introduced a revised decision replacing an earlier proposal to disallow 40% of the remaining revenue requirement under the prudent-manager standard. The adopted disallowance is $20.2 million of capital and $42.6 million of O&M. The earlier figure is superseded.
CAISO · Meeting Oct 26, 2026 · Transmission Planning · FERC Order No. 1920

CAISO Proposes Pushing the Start of Long-Term Regional Transmission Planning From 2027 to 2029

CAISO held a stakeholder meeting on October 26 on its compliance with FERC Order No. 1920, including a proposal to extend the start of Long-Term Regional Transmission Planning from February 1, 2027 to February 1, 2029. Separately, CAISO and the Southwest Power Pool held a joint market seams workshop on October 22, alongside Day-Ahead Market Enhancements training.

Clean Miles Standard · Announced Oct 19, 2026 · Program Launch · Rideshare ZEVs

CPUC to Launch RIDE Incentives for Rideshare Drivers; Applications Open November 2

The CPUC announced the Rideshare Incentives for Driving Electric (RIDE) program, offering up to $20,300 toward a new zero-emission vehicle, up to $14,200 toward a used one, and up to $1,170 a year in charging support for up to four years. Eligibility is limited to low- and moderate-income high-volume drivers at or below 400% of the federal poverty level with at least 4,500 passenger trips in the prior twelve months. The program is funded by per-trip regulatory fees collected from transportation network companies under the Clean Miles Standard and administered by the Center for Sustainable Energy. Applications open November 2, 2026.

PG&E · ERRA · Oct 2026 · Procurement · $306M Overcollection

PG&E Projects a $306 Million ERRA Overcollection and Asks to Return It Through 2027 Rates

PG&E projects a $306 million overcollection in its Energy Resource Recovery Account and has asked the Commission to return it through 2027 rates rather than by an immediate rate adjustment. The timing choice determines whether customers see the credit as a discrete adjustment or absorbed into the consolidated January 2027 rate change, and it affects the balancing account’s carrying cost in the interim.

CPUC Workshops · Held Oct 22, 2026 · Workshops · EPIC 5 · RES-BCT

CPUC Holds EPIC 5 Investment Plan and RES-BCT Program Workshops

The Commission held two energy workshops on October 22: one on the EPIC 5 investment plan under the Electric Program Investment Charge, and one on the Renewable Energy Self-Generation Bill Credit Transfer (RES-BCT) program, which allows a local government or other eligible customer to transfer bill credits from an onsite renewable generator to its other accounts.

2027 Procurement · Updated Oct 15–16, 2026 · Rate Forecasts · All Three IOUs

All Three IOUs Update 2027 Procurement Forecasts — Bundled Rates Fall, Departing-Load Rates Rise

Lower resource adequacy and renewable portfolio standard market price benchmarks drove mid-October updates at all three electric IOUs, producing divergent outcomes for bundled and departing-load customers. SCE revised its 2027 ERRA revenue requirement to $4.510 billion, up $159.9 million from May but $200.8 million below current rates, forecasting a 7.36% cut in bundled generation rates from 10.15 to 9.40 cents/kWh. PG&E updated its forecast to $4.674 billion and projects a 2.5% decrease in average bundled rates from 33.6 to 32.7 cents/kWh, while CCA and Direct Access rates rise 0.6%. SDG&E increased its proposed revenue requirement to $1.441 billion, up $547.7 million from May, projecting a 2.3% decrease in average bundled rates but a 17.7% increase for unbundled customers.

► Details
The bundled-versus-departing-load split is the whole story, and it is mechanical. Lower RA and RPS benchmarks increase the Portfolio Allocation Balancing Account undercollection, which bundled and departing-load customers share, while increasing the ERRA overcollection, which is credited exclusively to bundled customers. SCE’s forecast 2027 indifference amount has risen roughly 687% since May, almost entirely from the lower benchmarks.

Average rates also mislead at the bill level. SDG&E projects a 2.3% decrease in average bundled rates, yet a typical bundled non-CARE residential customer using 400 kWh a month would see a $4 increase, from $183 to $187; the equivalent unbundled customer faces $27, from $123 to $150.

Other figures worth holding: PG&E cut forecast 2027 system sales by about 2.1% on revised data center demand, EV adoption and behind-the-meter generation, and nets an $882 million year-end ERRA overcollection to a $306 million trigger balance. Greenhouse gas allowance returns: $551.5 million (SCE, Climate Credit $47, down from $54), $535 million (PG&E, Climate Credit $42.11) and $106.7 million (SDG&E, down from $140.6 million). SCE also calculates a $427.6 million overcollection on final September balances.
Prior Period
Oct 1 – Oct 15, 2026
9 items
OEIS Annual Performance Reports · Issued Oct 1, 2026 · Wildfire Mitigation · 2024 Performance Period

SCE Met 41 of 47 2024 Wildfire Mitigation Targets; Four Misses Repeat From 2023

The Office of Energy Infrastructure Safety issued its annual performance report on SCE’s 2024 Wildfire Mitigation Plan, finding SCE completed 41 of 47 initiative-activity targets (87%). Four of the six missed targets were also missed in 2023: covered conductor, rapid earth fault current limiters and ground fault neutralizers, inspection and maintenance tools, and open work orders. OEIS also flagged data-reporting accuracy and completeness, QA/QC shortcomings, spending-estimate and expenditure management, and transmission inspection quality — including misclassified survey types and inadequate follow-up. A companion report covers PacifiCorp.

► Details
The four repeat misses are the ones worth tracking, because each maps to a mitigation whose cost is recovered from customers. Covered conductor is SCE’s largest single wildfire hardening program by expenditure; open work orders measure the backlog of identified-but-uncorrected conditions found during inspection.

The report covers the 2024 performance period and states no dollar figures. OEIS’s findings on data-reporting accuracy and QA/QC bear on the reliability of the self-reported figures used to measure the rest of the program, which is why those findings matter beyond the individual initiatives.

The report notes that Los Angeles County Fire determined SCE equipment caused the Eaton Fire in January 2025 — the month after this performance period closed, and therefore outside the conduct this report assesses.
SCA-Guidelines · Issued Oct 2, 2026 · Draft Guidelines · Comments Due ~Nov 1

OEIS Proposes Biennial Safety Culture Assessments for Nine Utilities

The Office of Energy Infrastructure Safety released draft Safety Culture Assessment guidelines for public comment, covering biennial wildfire-focused assessments at nine California investor-owned utilities. Each assessment would comprise a workforce survey, a management self-assessment, lessons learned and progress on prior OEIS recommendations, interviews and observational visits, and a deep-dive analysis. Implementing assessment results is one of seven eligibility requirements for a utility’s annual Safety Certificate. The comment period runs about 30 days, closing on or about November 1, 2026.

► Details
The Safety Certificate is the mechanism that connects safety-culture findings to financial consequence. Under the AB 1054 framework, holding a valid certificate affects a utility’s access to the Wildfire Fund and the prudency presumption available to it in cost-recovery proceedings. Making implementation of assessment results a certificate requirement therefore gives the assessments weight they would not carry as advisory findings.

Moving to a biennial cadence across nine utilities standardises what has been a less regular process. The assessment components are qualitative — surveys, interviews, observational visits — so the guidelines’ treatment of methodology and of how “implementation” is judged will determine how consistently the requirement can be applied.
PSPS Event · Oct 9–12, 2026 · Public Safety Power Shutoff · 17 Counties

PG&E Shuts Off About 12,200 Customers Across 17 Counties

PG&E carried out a Public Safety Power Shutoff from October 9 to October 12 in response to westerly wind gusts of 30 to 45 mph, peaking near 55 mph in the Northern Sierra. The event affected roughly 12,200 customers across 17 counties — Alameda, Butte, Colusa, Fresno, Glenn, Kern, Kings, Lake, Merced, Napa, San Benito, San Joaquin, San Luis Obispo, Shasta, Solano, Tehama and Yolo — plus three tribal areas. All customers were restored by 8:00 p.m. on October 12.

► Details
At about 12,200 customers this is a small event by historical standards, and the roughly three-day restoration window closed without extension.

PSPS scope and duration are reportable to the Commission and feed the post-event reporting requirements that apply to each shutoff, where the relevant measures are whether de-energisation was proportionate to observed conditions and how long customers waited for restoration after winds subsided.

PG&E separately issued two-day-ahead notifications to about 30,000 customers across 22 counties for possible shutoffs from late October 14 through October 17. That window falls outside this period and the notifications are advance warnings rather than a completed event.
CAISO · Oct 1–2, 2026 · Market Expansion · FERC AD26-10-000

Portland General Joins the Extended Day-Ahead Market; CAISO and SPP File a Seams Plan

Portland General Electric began participating in the Extended Day-Ahead Market on October 1, joining CAISO and PacifiCorp’s two balancing authority areas. EDAM produced about $11 million in benefits across its first two months of operation in May and June 2026, of which PacifiCorp reported $5.42 million gross. Separately, CAISO and the Southwest Power Pool filed a joint seams report at FERC in Docket AD26-10-000, responding to the Commission’s July 2026 directive and setting six near-term objectives for coordination between the two markets.

► Details
Portland General had accrued about $377 million in Western Energy Imbalance Market benefits since 2017 before joining the day-ahead market. The remaining EDAM entry schedule is LADWP, BANC, PNM and Turlock Irrigation District in 2027, and Imperial Irrigation District, BHE Montana and NV Energy in 2028.

The joint CAISO–SPP seams report sets six near-term objectives: improved data exchange, model alignment, expanded education and training, support for the Western Interconnection Loading Relief and Enhanced Curtailment Calculator initiatives, processes for transmission constraints affected by more than one market area, and a commitment to publish a longer-term seams plan. A 30-day comment period applies, with a stakeholder workshop set for October 22, 2026.

Day-ahead market benefits accrue to participating utilities and flow to customers through procurement costs rather than as a separate line item, so the reported figures are gross market benefits and not a direct bill effect.
California Climate Credit · Announced Oct 12, 2026 · Residential Bill Credit · November 2026

November Climate Credit Set for the Smaller Electric Utilities

The Commission announced the November 2026 California Climate Credit for customers of the smaller electric utilities: $17.52 for Bear Valley Electric, $71.98 for Liberty Utilities and $111.83 for Pacific Power. The credit is applied automatically to residential electric bills, with no application required, and is funded through the Cap-and-Invest Program administered by the California Air Resources Board rather than by other ratepayers.

► Details
The credit returns to residential customers the proceeds their utility receives from selling greenhouse gas allowances under Cap-and-Invest. Because allowance proceeds scale with a utility’s emissions-related obligation and are divided across its residential base, the per-customer amount varies widely between utilities — here by more than a factor of six — without reflecting anything about an individual household’s usage.

No proceeding number was cited in the announcement. The credit for the three large investor-owned utilities is set separately and on a different schedule.
Voting Meeting · Held Oct 8, 2026 · Results · Wildfire Maps, Energy Efficiency, Diablo Canyon

October 8 Voting Meeting Results — 12 Energy Items Adopted, Several Held to October 29

The Commission adopted decisions and resolutions on wildfire threat maps, energy efficiency, overhead line design, distributed energy resources, Direct Access and utility cost recovery. The largest dollar item was approval of $1.22 billion in PG&E Diablo Canyon extended operations costs. The Commission also denied SDG&E’s request to stop administering its regional energy efficiency programs, denied SoCalGas’s $24.9 million billing-system funding request, and rejected the petition to lift California’s Direct Access cap. Several agenda items were held to the October 29 meeting, including the repeatedly deferred PG&E–Google data-center resolution.

► Details
Adopted, each carded separately in Proposed Decisions & Rulings: the SCE fire-map decision (R.15-05-006, 4–0 with Commissioner Baker recused); the SDG&E energy-efficiency withdrawal denial (A.25-04-014, 4–1 with Commissioner Baker dissenting); the General Order 95 conversion to Load and Resistance Factor Design (R.24-10-005); Res. E-5476 adopting the 2026 Avoided Cost Calculator; the Direct Access petition denial closing R.19-03-009; Res. E-5483 on the Diablo Canyon true-up; the SoCalGas Customer Information System denial (A.25-05-004); the PG&E 2027 revenue-tracking decision (A.25-05-009); the DAC-SASH modifications (R.25-01-005); Res. E-5472 on meter socket adapter fee transparency; Res. E-5469 extending the Burney Forest Products BioRAM contract; and Res. E-5422 approving the SDG&E–Navy master utility services contract.

Held to October 29, per the final hold list for Agenda 3588: PG&E’s proposed Google data-center agreement (Draft Res. E-5455, item 2, now deferred at five consecutive meetings); SoCalGas’s Transmission Integrity Management Program cost recovery (A.25-04-020, item 13), carrying a proposed $81.3 million approval and $92.5 million disallowance; Liberty Utilities’ Mountain View Fire cost-recovery request (A.25-06-017, item 47) — the first covered-wildfire case under AB 1054; the competing biomethane cost-allocation proposed decisions (R.22-12-011, items 48 and 48A); the SFPP terminals jurisdictional finding (A.24-01-020, item 8); and Draft Res. G-3622 on California Energy Commission gas research (item 6). One item was withdrawn (item 29), two were taken up with the regular agenda (items 4 and 11), and two further staff holds (items 3 and 19) are not publicly mapped to dockets.

Note that the $92.5 million SoCalGas disallowance and the SFPP finding were not decided on October 8, though both appeared on the agenda.

Two threads from the dais are worth noting for later proceedings. On the fire map, Commissioner Karen Douglas said the Commission lacked the independent technical review it had used in 2019, when CAL FIRE participated, and lacked the in-house fire-safety expertise for a comparable assessment — the reason she asked for a 2027 workshop. On energy efficiency, Commissioner Matthew Baker’s dissent and President John Reynolds’s remarks both engaged the question of how to read SDG&E’s improving cost-effectiveness figures against its rising cost per kilowatt-hour saved, an issue the Commission deferred to the energy efficiency rulemaking rather than resolving here.
Voting Meeting · Scheduled Oct 8, 2026 · Preview · Large Loads, Gas Costs, Direct Access

October 8 Voting Meeting Preview — The Repeatedly Held Google Data-Center Resolution, a $92.5M SoCalGas Disallowance, and the Direct Access Cap

A heavily loaded agenda. The headline item is Draft Resolution E-5455, held at four consecutive meetings, which would approve PG&E’s agreement to energize a 250-MW Google data center in San Jose while requiring an additional refundable capital advance of $600,000/MW — as much as $150 million. Also before the Commission: competing biomethane cost-allocation proposed decisions, a proposed $92.5 million disallowance of SoCalGas pipeline-integrity costs, a proposed decision rejecting the effort to lift California’s Direct Access cap, and the first AB 1054 covered-wildfire framework for Liberty Utilities. Diablo Canyon costs, energy efficiency, wildfire mapping and distributed energy resources round out the agenda.

► Details
This card is the pre-meeting preview and is preserved as filed. For what the Commission actually did — including which items were adopted and which were held to October 29 — see the October 8 results card above.

On E-5455, the draft adopts the fixed $600,000/MW charge after developers, business groups and Cal Advocates opposed the uncertainty created by an earlier proposal to defer network-cost treatment to the pending Rule 30 proceeding. Google’s facility would use approximately 25% of the new Newark-NRS line’s capacity and depends on more than 10 other South Bay transmission upgrades.

Other items already carded in Proposed Decisions & Rulings and appearing on this agenda: the competing Houck and Reynolds biomethane proposed decisions; the SoCalGas TIMP disallowance; the SoCalGas Customer Information System denial; the Direct Access petition denial; Draft Res. E-5476 adopting the 2026 Avoided Cost Calculator; the DAC-SASH modifications; the SDG&E energy-efficiency exit denial; Draft Res. E-5483 on the Diablo Canyon true-up; the SCE fire-map proposed decision; the GO 95 Load and Resistance Factor Design proposed decision; Draft Res. G-3622 on CEC gas research; the PG&E 2027 GRC effective-date decision; the SFPP terminals jurisdictional finding; and Draft Res. E-5422 on the SDG&E–Navy contract.

On G-3622, the draft approves $44.6 million of the California Energy Commission’s two proposed $24 million research plans for fiscal years 2024–2025 and 2025–2026, while requiring the agency to draw down $31.1 million in previously authorized, unspent funds first — limiting new ratepayer funding to $13.5 million.
R.24-01-018 · Filed Oct 2026 · Compliance Reports · Data Through Jun 30

Energization Reports Through June 30 — PG&E Clears 94–99% of Timelines While Upstream Upgrades Run 942 and 1,285 Days; SDG&E Still Cannot Separate Customer From Utility Time

PG&E, SCE and SDG&E filed updated energization reports under R.24-01-018 covering projects through June 30. PG&E reports that 98% of Rule 16 projects, 99% of Rule 29, 94% of combined Rule 15/16 and 95% of main-panel upgrades completed from July 2025 through June 2026 stayed within the Commission’s maximum timelines. SCE’s results vary sharply by project type — Rule 16 averaged 79 business days with 2% exceeding the maximum, while 41% of Rule 15 projects and 63% of main-panel upgrades exceeded theirs. SDG&E still cannot reliably separate customer time from utility-controlled time, so it cannot report compliance on the same basis as the other two.

► Details
PG&E. Average utility-controlled times are drawn from the cumulative population of applications since January 2023: 113 calendar days for Rule 16, 81 for Rule 29 and 124 for combined Rule 15/16. Upstream upgrades averaged 942 days for circuit work and 1,285 days for substation work, both above the applicable targets; PG&E states that customers waited an average of 433 days from identification of the upgrade need to energization.

SCE. For 2025, Rule 16 averaged 79 business days with 2% exceeding the 230-day maximum. Rule 15 averaged 239 days with 41% exceeding its maximum, though only 44 projects fell in that category. Main-panel upgrades averaged 71 business days against a 30-day average target, with 63% exceeding the 45-day maximum. Comparing the first half of 2026 with the same period in 2025, Rule 15 rose from 304 to 317 days while main-panel upgrades improved from 83 to 70 days and their maximum-target exceedance rate fell from 65% to 53%. SCE notes that some customer-controlled time remains embedded in its reported utility timelines.

SDG&E. End-to-end data show shorter post-decision timelines for completed projects: Rule 15 fell from 277 to 179 business days, combined Rule 15/16 from 328 to 226, and Rule 16 from 115 to 86. Those figures include customer time and cover only projects already completed, so longer jobs still in progress are excluded from the averages.

The reports do not support a clean utility-to-utility ranking. PG&E uses a July-to-June measurement window and calendar days; SCE reports calendar-year compliance in business days; SDG&E cannot isolate utility-controlled time at all. The Commission has statewide targets, but the three utilities are not yet measuring performance on a consistent basis.
D.26-09-003 · Filed Oct 2026 · Biennial Progress Reports · Grid Modernization

First Biennial Grid-Modernization Reports — PG&E Moves Outage Management Into ADMS, SCE Reaches 128 FLISR Substations, SDG&E Islands Borrego Springs on 100% Renewables

PG&E, SCE and SDG&E filed their first biennial grid-modernization progress reports under D.26-09-003, detailing distribution-management systems, communications infrastructure, planning tools and technologies for managing distributed energy resource adoption and electrification. PG&E plans to move outage-management functions into its ADMS in November and began an AMI 2.0 pilot in September. SCE reports ADMS has replaced legacy distribution-management functions at all 13 switching centers, with closed-loop fault location, isolation and service restoration added at 128 substations so far in 2026. SDG&E reports more than 94% of distribution substations SCADA-enabled and highlights its November 2025 demonstration of the entire Borrego Springs community operating as an island supplied 100% by renewable energy.

► Details
PG&E. Its DERMS already supports flexible connections, customer-owned telemetry and demand-response visibility. Flex Connect has served seven locations, with customers energized about 12 months earlier on average, and PG&E projects the program will unlock more than 3.5 GWh of additional energy use by the end of 2026. The AMI 2.0 pilot began in September with about 9,500 meters planned by year-end and roughly 297,000 more proposed for 2027 through 2030.

SCE. Replacement of its outage-management system is planned for 2027. Closed-loop FLISR reached 128 substations in 2026 on top of eight at the end of 2025, with a target of 150 by year-end and deployment to all currently eligible substations expected in 2028. The communications buildout is expected to reach 114 radio-access sites and more than 2,300 edge radios this year. SCE states that the first two phases of its Grid Management System now span seven years instead of five, citing COVID, supply-chain problems, the war in Ukraine — where one ADMS module was developed — and cybersecurity concerns with the vendor’s product.

SDG&E. Reports more than 3,000 wireless fault indicators, 380 SCADA-controlled capacitors and 73 private-LTE base stations as of the first quarter of 2026. Its enterprise DERMS remains in procurement with vendor selection beginning in 2027, and its Smart Meter 2.0 proposal is pending before the Commission with a proposed decision expected in the third quarter of 2027.

Comparability is limited. PG&E provides detailed cost tables, SDG&E incorporates most costs from its General Rate Case, and SCE reports no costs at all. Energy Division’s joint review of the reporting template with the utilities before the 2028 reports will have to address that gap.
Earlier Period
Sep 16 – Sep 30, 2026
1 item
Voting Meeting · Held Sep 17, 2026 · Results · San Marcos, Agenda 3587

September 17 Voting Meeting Results — PCIA Banked RECs Affirmed at Zero, AB 825 Rulemaking Opened, Four Marquee Items Pushed to October 8

At its September 17 voting meeting the Commission affirmed zero-dollar treatment of pre-2019 banked renewable energy credits in the PCIA (D.26-09-047) and opened the AB 825 regional-markets rulemaking (R.26-09-009). It also adopted distribution-planning equity metrics (Res. E-5480), the revised tribal land-transfer and consultation policies (D.26-09-072), Ava’s Sonrisa incremental-resource determination (Res. E-5475), PG&E’s gas RD&D budgets (Res. G-3623) and closure of the SGIP rulemaking (D.26-09-048). Four items were held to October 8.

► Details
Held to October 8: Draft Resolution E-5455, approving PG&E’s agreement to energize a 250-MW Google data center in San Jose while requiring an additional refundable capital advance of $600,000/MW; the proposed decision approving SCE’s request to add 47 areas totalling about 208 square miles to the High Fire-Threat District; the proposed decision replacing Working Stress Design in General Order 95 with Load and Resistance Factor Design for overhead electric and communications facilities; and Draft Resolution G-3622, approving in part the California Energy Commission’s research plans for fiscal years 2024–2025 and 2025–2026.

The Google resolution has now been held at four consecutive meetings — July 2, July 16, August 13 and September 3 — and the SCE fire-map item was held from September 3. Each adopted item has its own card in Proposed Decisions & Rulings. The meeting was held at the San Marcos City Council Chambers under agenda 3587.
No matches for selected IOU.

Sources: CPUC News · CPUC Docket Search · Document Portal · CalRegulatory · Utility Dive Updated October 8, 2026