Current Period
Jun 16 – Jun 30, 2026
5 new entries
CA AG · CEC · Litigation
Notice filed Jun 23, 2026
Litigation · Offshore Wind
California — Notice of Intent to Sue Trump Administration Over Offshore Wind Lease Buyouts; $2.6B Federal Pullback Threatens 25 GW Target
California AG Rob Bonta and CEC Chair David Hochschild filed a Notice of Intent to sue the U.S. Department of the Interior under the Outer Continental Shelf Lands Act, challenging a $120 million federal buyout of Golden State Wind's 2 GW Morro Bay lease that would also force the lessee to invest $120 million in out-of-state fossil-fuel projects. Total Trump-administration offshore wind buyouts across eight lease areas now total $2.6 billion; California has invested more than $100 million in offshore wind port and transmission readiness.
► Details
The Notice frames the federal buyout structure as ultra vires under OCSLA on three grounds: the leases were competitively awarded under a federal statute that requires development; the cash buyout plus mandated out-of-state fossil reinvestment is itself a substantive policy reversal not authorized by the statute; and the cumulative effect across eight lease areas ($2.6 billion) materially impairs California's ability to meet the 25 GW by 2045 offshore wind target adopted under AB 525. Golden State Wind's 2 GW Morro Bay lease (OCS-P 0564) and Invenergy's adjacent 1.5 GW lease (OCS-P 0565) are the two largest single buyouts. If the suit succeeds, the federal Interior Department would be enjoined from finalizing the buyout structure pending judicial review; if it fails, the practical effect is that the California port and transmission investments already underway (Humboldt Bay, Long Beach, Port of San Luis) absorb the stranded-asset risk while the offshore generation pipeline collapses. The case will be watched as a test of state standing to challenge federal lease modifications affecting state energy planning.
FERC · Maryland OPC Complaint
Comment deadline Jul 27, 2026
FERC · Cost Allocation
FERC — Maryland Data-Center Transmission Cost Allocation Complaint: 80 Legislators Back $1.6B Cross-State Cost Challenge
Eighty Maryland legislators filed in support of the Maryland Office of People's Counsel's FERC complaint alleging that PJM's cost-allocation framework forces Maryland ratepayers to pay approximately $1.6 billion over a decade for transmission projects driven by data centers located in other PJM states. PJM projects more than 80,000 MW of new data-center load over the next 20 years. FERC comment deadline extended to July 27, 2026; the complaint tests the "roughly commensurate benefits" doctrine under FPA Section 205/206. Precedent-setting for CAISO and CPUC large-load cost allocation as California prepares for 7-9 GW of hyperscaler load.
► Details
The "roughly commensurate benefits" doctrine was articulated in Illinois Commerce Commission v. FERC (7th Cir. 2009) and codified in Order 1000: transmission cost allocation must trace cost causation to beneficiaries with reasonable proportionality. The Maryland OPC argues that PJM's regional Order-1000 allocation lumps Maryland ratepayers into a generalized beneficiary pool for transmission upgrades whose actual cost driver is hyperscaler load growth in Virginia, Pennsylvania, and Ohio. The complaint, if granted, would either remand PJM's allocation methodology or direct PJM to develop a participant-funded sub-regional surcharge for data-center-driven upgrades. The decision is precedent-setting for California in three ways: (1) it tests whether large-load cost causation can be statistically separated from generalized regional reliability needs at scale; (2) it informs CAISO's pending revisions to Rule 30 network-upgrade allocation; and (3) it establishes a record for CPUC arguments in future PG&E, SCE, and SDG&E exceptional-case AL filings that customer-specific cost-causation refunds (BARC) should be paired with non-detriment tests for non-participating bundled customers. Watch for whether FERC opens a Section 206 investigation, which would dramatically expand the proceeding's scope.
R.25-10-003
Opening Comments Closed Jun 22, 2026
RA Reform · Reply Window Open
CPUC — RA Reform PD Opening Comments Closed Jun 22; Reply Window Open Ahead of Jul 2 Vote
Opening comments on the Resource Adequacy Reform Proposed Decision in R.25-10-003 closed on Jun 22, 2026. The PD adopts the UCAP framework for 2028, sets 2027-2029 LCRs (23,618 / 24,545 / 25,480 MW), modifies storage penalty structures, and ends paper capacity. Six Track 2 implementation questions remain open. Earliest Commission consideration: July 2, 2026.
► Details
Reply window is the last opportunity to shape the Jul 2 voting outcome on California's structural overhaul of Resource Adequacy. Storage operators have the most to lose from the PD's penalty structure (charging-sufficiency shortfalls convert to a flat 24-hour MW adder, with the largest hourly deficiency setting the penalty) and from the UCAP derating that will move 2028 RA accreditation off nameplate capacity. LSEs have the most to gain from real-time deliverability tightening as paper capacity is formally ended. LDES developers get a formal RA accreditation pathway for the first time via the Forward Charge Period multiplier (2x for 8-hour resources, scaling to 8x for 72-hour-plus). The six Track 2 deferrals — hybrid resource methodology, Must-Offer Obligation basis, EFORd for the energy component of storage, fifth-hour foldback, Flexible RA interaction, and Slice-of-Day template integration — do not delay the 2028 effective date but remain unsettled 15 months before the first UCAP compliance year opens.
FERC · Data Centers
Order issued Jun 22, 2026
FERC Order · Large Load
FERC — Data Center Interconnection Order: Federal Backstop Reshaping RTO Large-Load Process; Implications for CAISO and CA Tariff Design
FERC issued a major data-center interconnection decision laying out federal standards for how RTOs must handle large-load interconnection. Commissioner David LaCerte: "If RTOs fail to address large-load concerns identified by FERC, the agency will dictate the solutions. I say this not as a threat, but as a statement of duty." The order's framework will influence how CAISO updates its Rule 30 network-upgrade cost-allocation framework and how the CPUC structures future utility-data-center supply agreements (Res. E-5455 PG&E + Google 250 MW is the most recent template).
► Details
FERC's six-takeaway order signals that flexible-load tools (Grid-Enhancing Technologies, demand response) and Co-located Load Behind the Meter arrangements may have to satisfy federal cost-causation tests before being allowed to bypass RTO interconnection processes. Berkeley Lab's parallel analysis projects data centers could use up to 15% of all U.S. electricity by 2030, up from 5% in 2024. For California, the order matters in three ways: (1) it sets a federal floor for the kind of refund-cap and BARC-mechanism protections the CPUC is layering onto exceptional-case agreements like PG&E + Google; (2) it tightens the legal basis for arguments that hyperscale loads bear cost causation for upstream transmission; (3) it pressures CAISO's 2025-2026 Transmission Plan ($6.7B / 38 projects) toward more rigorous large-load attribution as the Tesla-Trimble-Metcalf 230 kV corridor and other South Bay reliability projects move forward. The Imperial County, CA 950,000-square-foot data center reversal reported by CalMatters (Jun 23) underscores that the federal backstop is colliding with local opposition at the same moment.
Prior Period
Jun 1 – Jun 16, 2026
14 entries
R.24-01-018
ALJ Ruling Jun 1, 2026
ALJ Ruling · Energization
CPUC — Energization Reports Found Insufficient: Guidehouse Roadmap Tightens Future Reporting
An ALJ ruling in R.24-01-018 directs PG&E, SCE, and SDG&E to respond to questions arising from Guidehouse's review of the utilities' September 2025 Biannual Energization Reports. Guidehouse found the data insufficient to assess utility compliance with the targets set in D.24-09-020; approximately one-third of required data fields were missing for more than 75% of projects across all three IOUs.
► Details
Why the data failed. D.24-09-020 established enforceable energization targets, an eight-step framework, and a twice-yearly reporting obligation covering tariff projects under Rules 15, 16, 29, and 45, plus main panel upgrades. The September 2025 reports cover projects with complete applications from January 31, 2023 through June 30, 2025 — a window that straddles the decision's September 2024 issuance date.
Each utility's tracking systems failed in a distinct way:
PG&E is still integrating systems and cannot reliably track Step 6 (IOU Site Readiness) or Step 8 (Energization); only 6.3% and 47% of completed tariff projects have start or end dates for those steps. SCE provided complete step-date data across all eight steps (the only utility to do so) but cannot separate IOU-controlled time from customer or third-party time. SDG&E struggled with multiple steps and could not track utility-controlled time separately.
Guidehouse's sufficiency thresholds: 95% availability for compliance data points; 75% for contextual data points. None met those thresholds. The ruling asks parties whether utilities that fail the proposed sufficiency thresholds should be required to file additional reporting on their energization backlogs — effectively converting bad data into its own regulatory problem. Whichever parties shape the definitions of utility-controlled time, customer delay, upstream capacity triggers, actual project costs, and outliers will shape how future energization performance is judged.
R.25-10-003
PD issued Jun 2, 2026
Proposed Decision · RA Reform
CPUC — Resource Adequacy Reform PD: UCAP Framework, 2027-2029 LCRs, 2027 Flex RA
A Proposed Decision adopts the Unforced Capacity (UCAP) framework for the 2028 RA year, sets 2027-2029 Local Capacity Requirements, adopts 2027 Flexible Capacity requirements, modifies storage penalty structures, sets Effective Output limits, and formally ends paper capacity. Comments due June 22, 2026. Earliest Commission consideration: July 2, 2026.
► Details
The PD adopts CAISO's recommended Local Capacity Requirements: 23,618 MW for 2027; 24,545 MW for 2028; and 25,480 MW for 2029. The LA Basin climbs from 6,823 MW to 7,721 MW over the three years; seven of 10 local areas carry the CAISO's resource-deficiency notation. Effective for the 2028 RA compliance year, dispatchable thermal, nuclear, geothermal, and non-hybrid storage resources will have accreditation reduced by their Equivalent Forced Outage Rate during RA Measurement Hours: UCAP = (1 - EFORd) x Pmax, applied separately for summer and non-summer seasons using the best three of the prior four calendar years of CAISO outage data. New resources receive class-average EFORd values until unit-specific history accumulates; thermal generators get NOAA 30-year typical weather-year derates. Preliminary UCAP values publish early 2027; final values September 2027.
Long-Duration Energy Storage is defined as any storage capable of discharging at maximum capacity for at least 8 continuous hours. For 2027, LSEs may count LDES capacity across the full 24-hour Slice-of-Day period using a Forward Charge Period multiplier ranging from 2x (eight-hour resources) to 8x (72-hour-plus resources). Closed-loop pumped storage hydropower receives LDES treatment; open-loop PSH deferred.
Storage charging sufficiency penalty: beginning 2027, an LSE with a MWh charging sufficiency shortfall has that shortfall converted to a flat 24-hour MW adder, applied to each hourly position, with the largest resulting hourly deficiency determining the RA penalty. Energy-only resources may not count toward RA capacity requirements; same-Point of Interconnection rule from 2027 allows EO excess to count toward charging sufficiency at deliverable storage co-located at the same POI, after subtracting the paired storage's own energy sufficiency need.
Rejections: hourly load obligation trading rejected (Energy Division's Transactability Report found no demonstrated inability for LSEs to meet Slice-of-Day obligations under existing mechanisms). The Commission ends paper capacity. Six implementation questions deferred to Track 2: hybrid resource methodology; Must-Offer Obligation basis; EFORd for storage energy component; fifth-hour foldback; Flexible RA interaction; Slice-of-Day template integration. None of those open items will delay the 2028 effective date. Comments due Jun 22; earliest vote Jul 2.
I.19-06-014
Decision Adopted Jun 11, 2026
Decision · Shareholder-Funded
SoCalGas — Safety Culture Plan Adopted; Shareholders (Not Ratepayers) Pay
The CPUC adopted SoCalGas's revised Safety Culture Improvement Plan in I.19-06-014, with the explicit ordering that SoCalGas shareholders, not ratepayers, fund the safety culture fixes. The decision closes the safety culture phase of the long-running Aliso Canyon investigation and establishes a no-ratepayer-cost-recovery rule for plan compliance work.
► Details
I.19-06-014 is the OII opened after the 2015 Aliso Canyon leak and the cascading findings on SoCalGas's institutional safety practices. The decision approves the revised plan as a foundation for implementation, while expressly declining to find that any specific intervention is adequate or effective. SoCalGas must, in its next quarterly compliance report: integrate security into its definition of comprehensive safety; strengthen contractor integration with metrics and oversight comparable to employee-focused efforts; expand its corrective-action program to capture public and non-occupational safety concerns; and demonstrate that "Learning Team" sessions on resource allocation continue until no new insights emerge. The decision also creates a Tier 2 Advice Letter pathway delegating Safety Policy Division authority to approve Safety Culture Improvement Plan revisions when interventions fall short, bypassing a full Commission vote. The decision finds Sempra's participation minimal; SoCalGas must maintain a consolidated plan tracking Sempra contributions and demonstrate through quarterly reporting how parent-level governance responds to assessment findings originally directed at Sempra. CPUC staff retains authority to engage SoCalGas's board directly.
Dais discussion (Jun 11): Commissioner Houck framed approval as a starting point, not an endpoint, with quarterly compliance reports until the next safety culture assessment (no later than August 2029). Commissioner Douglas said safety culture improvement must be demonstrated through measurable outcomes. Commissioner Harada drew on her aerospace background, distinguishing real safety from polished reports and dashboards. President Reynolds emphasized implementation must show measurable outcomes over time.
Cost recovery is the decision's most consequential outcome. SoCalGas has already incurred more than $5 million in unrecoverable Safety Culture Improvement Plan costs; the CPUC again rejects ratepayer recovery for safety culture remediation through the next assessment cycle. Expect Sempra investor disclosures to flag the decision as a 2026 charge against equity.
Res. E-5455 · AL 7785-E
Draft · Vote ≥ Jul 2, 2026
Draft Resolution · Large Load
PG&E — 250 MW Google San Jose Data Center: BARC Refund Cap, Extended Refund Window, Rule 30 Conformance
Draft Resolution E-5455 would let PG&E energize Google's 250 MW San Jose data center while capping annual refunds at actual net revenues (not projected future revenues) and extending the refund window from 10 to 15 years. The agreement must conform to the Rule 30 network-upgrade cost framework within 60 days of that decision. Earliest CPUC vote: July 2, 2026.
► Details
Google's load depends directly on the Newark-NRS 230 kV line (a $1 billion-plus project whose FERC-approved revenue requirement reaches ratepayers at roughly $100 million per year) plus more than ten other South Bay transmission upgrades. The CPUC previously capped refunds at 75% of net revenues for the STACK Infrastructure and Microsoft data centers (Resolutions E-5420 and E-5439); here it allows 100%, but only because the Rule 30 proceeding handles network-upgrade cost exposure separately. Energy Division notes that the Base Annual Revenue Calculation (BARC) process — built for distribution-scale energization where many similar customers statistically absorb stranded-cost risk — can, unadjusted, refund a large-load customer up to nine times first-year net revenues. The draft therefore caps refunds at actual net revenues and ties final terms to Rule 30. This is the first major California utility–data center supply agreement to clear CPUC staff review under the post-2024 large-load framework and will be cited in every subsequent large-load AL from PG&E, SCE, and SDG&E.
Res. E-5467 · AL 4736-E
Adopted Jun 11, 2026 (5-0)
Resolution · UOG Storage
SDG&E — $267.9M Utility-Owned 119 MW Westside Canal 2A Battery Approved Despite 2034 Deliverability Gap
The CPUC approved SDG&E's acquisition of the 119 MW Westside Canal Phase 2a lithium-ion battery (Imperial Valley) from an RWE subsidiary for $267.9 million, plus a 10-year operations-and-maintenance agreement, recoverable through the Cost Allocation Mechanism (CAM). Commissioners approved 5–0 over protests from IEP, CalCCA, and Cal Advocates.
► Details
The project came online in December 2024 and already dispatches in CAISO markets, where RWE sells short-term resource adequacy on a merchant basis, so SDG&E's purchase adds no new physical capacity. Resolution E-5467 finds the project incremental on a technicality (it is not on the baseline resource list) and authorizes full CAM cost recovery. Energy Division reads the 120–220 MW Effective Planning Reserve Margin range as a floor utilities may exceed, rejecting CalCCA's argument that only ~11.4 MW should flow to CAM. The core ratepayer risk is deliverability: the project has interim status for 2025–2026 but will not reach Full Capacity Deliverability Status until transmission upgrades complete, potentially in 2034.
Dais discussion (Jun 11): Commissioner Baker called it the weakest of three utility-owned battery projects before the Commission, citing four reservations — SDG&E's incremental EPRM need may be only about 11 MW; SDG&E is long on Resource Adequacy; the battery likely would remain in service under RWE; and full deliverability remains unresolved until 2034 absent operational changes such as an eight-hour configuration. He nevertheless supported it, saying he would be nervous letting the opportunity pass. President Reynolds emphasized the multi-year review process, independent evaluator oversight, and Energy Division's cost review against comparable projects, framing planning reserve margins as an insurance policy. Mitigation rests on price concessions, RWE penalty provisions, continued CAISO participation, and quarterly CAM Procurement Review Group reporting rather than a firm RA-value guarantee.
PG&E AL · GIC San Jose
Filed Jun 6, 2026
Advice Letter · Large Load
PG&E — GIC San Jose 97.3 MW Data Center: Non-Standard 115 kV Package, Customer-Funded Redundancy
PG&E filed a non-standard interconnection package for GIC San Jose's 97.3 MW data center at 350 W. Trimble Road. The project requires a new 115 kV switching station for regular service plus a customer-funded redundant 115 kV line. Refunds run on actual costs with progress billing, calculated through PG&E's BARC process over 10 years.
► Details
The ratepayer-protection structure runs on actual costs with progress billing rather than estimates. Refunds on the regular-service facilities are tied to actual revenues after service begins, calculated through PG&E's BARC process over 10 years: if load underperforms, refunds shrink or disappear. The customer-funded redundant 115 kV line carries no refund rights — the customer eats every dollar of optional redundancy. PG&E's template across recent large-load advice letters: actual-cost payment; BARC-based refunds; minimum demand protections; no refund rights for customer-requested redundancy; and a CPUC/FERC jurisdictional split on cost recovery. PG&E is normalizing bespoke large-load agreements ahead of the Rule 30 outcome, using each filing to reinforce the same basic bargain: accelerated transmission service in exchange for upfront risk absorption.
Res. E-5457
Adopted Jun 11, 2026
Resolution · ReMAT Prices
CPUC — ReMAT 2026 Price Update: Baseload Jumps 21% to $92.33/MWh
Resolution E-5457 updates fixed avoided-cost prices for the Renewable Market Adjusting Tariff (the feed-in tariff for renewable generators of 3 MW or less). The 2026 prices are $58.38/MWh non-peaking, $67.40/MWh peaking, and $92.33/MWh baseload. PG&E, SCE, and SDG&E must file Tier 1 advice letters within 30 days; existing contracts are unaffected.
► Details
Prices reflect weighted-average Renewable Portfolio Standard contract prices from utility, CCA, and ESP contracts executed 2020–2025 for projects of 20 MW or less. The baseload rate jumps 21% from $75.96/MWh, driven by geothermal contracts dominating the baseload reference set; non-peaking rises from $52.85/MWh; peaking is essentially unchanged from $67.99/MWh. The ReMAT program has produced 65 contracts totaling roughly 112 MW since inception, mostly small hydro and solar PV, with only two contracts executed in 2025. The resolution changes nothing about program design — it is the administratively set avoided-cost rate catching up to a higher-cost environment for small baseload renewables.
Res. G-3621
Adopted Jun 11, 2026
Resolution · CTA Fees
CPUC — 2026 Core Transport Agent Fees Reaffirmed; Complaints Up 75%
Resolution G-3621 keeps the $5,000 base fee for all 39 registered Core Transport Agents (non-utility gas suppliers) while assigning variable fees only to CTAs that generated consumer-protection costs in 2025. Consumer Affairs Branch CTA complaints rose 75% to 2,942 in 2025. The largest assessments fall on Wave Energy (~$206,000), SFE Energy (>$118,000), Big Tree Energy, and United Energy Trading/Callective.
► Details
The methodology from Resolution G-3597 remains intact: fixed administrative costs ($212,491, or $5,449 per CTA, within the 20% tolerance band) are spread across all 39 registered agents, while variable costs are assigned by complaint and unauthorized-enrollment activity. The 2026 charges are $5.94 per phone contact and $189.52 per informal written complaint, with $680.43 per unauthorized-enrollment complaint and $739.17 per enforcement action. Unauthorized-enrollment complaints rose nearly 88%, even as total enforcement actions fell 83% (393 in 2024 to 65 in 2025). Four suppliers generated 52% of all complaints, so the cost-causation design leaves high-complaint CTAs paying substantially more than clean-record operators such as BP Energy, Shell, and Calpine, which pay only the $5,000 floor.
R.25-10-003 · LOLE Ruling
Ruling Jun 11, 2026
Ruling · RA Modeling
CPUC — 2028 LOLE Study Inputs & Assumptions Set (Resource Adequacy)
An Energy Division ruling attaches the Revised Inputs & Assumptions for the 2028 Loss-of-Load-Expectation (LOLE) study. It deploys SERVM 10.28, expands the weather and hydro record to 2000–2024, and moves California demand to the CEC 2025 IEPR forecast. The 2028 CAISO baseline grows nearly 17 GW to 114,813 MW (batteries +9,891 MW, solar +5,555 MW). The LOLE study is expected by August 2026.
► Details
SERVM tests whether CAISO meets the 0.1 days/year LOLE standard. The baseline expansion makes over-reliability a plausible starting point, raising the stakes of staff's stress-test choices (adding perfect demand, reducing capacity pro rata, or lowering the import limit). The load assumptions remain contested: SERVM's modeled 2028 managed peak of 49,388 MW sits 1,032 MW above the IEPR projection because staff calibrate to consumption rather than managed demand. Diablo Canyon is counted in the 2028 RA baseline but excluded from IRP modeling, a mismatch that any RA determination premised on its presence will need to revisit. This ruling sets the assumptions that will produce the first major reliability determination in the proceeding.
R.26-04-016
Opening comments Jun 8, 2026
Rulemaking · Risk Framework
CPUC — Risk-Based Decision-Making Framework: Should Affordability Define Risk Tolerance?
Parties filed opening comments in the successor to R.20-07-013 (final decision D.25-08-032). The framework governs how utilities quantify and propose safety spending in General Rate Cases. The central dispute: whether the definition of risk tolerance should incorporate affordability. SoCalGas/SDG&E say no; Cal Advocates, TURN, Mussey Grade Road Alliance, and EPUC/Indicated Shippers support incorporating ratepayer cost.
► Details
The proceeding picks up unfinished tasks from D.25-08-032: adopting a formal risk tolerance standard, formalizing added RAMP review time for the Safety Policy Division, and standardizing Benefit-Cost Ratio methodology. TURN is the most skeptical that an abstract standard can be built at all, warning that utilities will drive stated tolerance toward zero because capital grows rate base and profit; it invokes Arrow's Impossibility Theorem against any representative-consensus working group and favors building on D.25-08-032's budget-constrained portfolios anchored in ESJ affordability. PG&E wants the standard built through evidentiary hearings; SCE wants Benefit-Cost Ratio methodology stabilized first. The key test across parties is unscaled, risk-neutral Benefit-Cost Ratio reporting: a mitigation that clears 1.0 only after risk-aversion adjustments is not the same as one that clears 1.0 before utility scaling.
2026 ACC · Staff Proposal
Ruling issued Jun 6, 2026
Staff Proposal · Avoided Cost
CPUC — Revised 2026 Avoided Cost Calculator: Single Electric-Sector GHG Value, Excel-Based Integrated Calculation
The CPUC filed a revised 2026 Avoided Cost Calculator staff proposal with opening comments due Jun 19. The revision rebuilds the Integrated Calculation for generation capacity and GHG avoided costs and changes the transmission avoided-cost methodology for SCE, dropping Locational Net Benefits Analysis in favor of Discounted Total Investment Method only.
► Details
On GHG issues, staff propose to (a) collapse separate electric and gas values into a single electric-sector figure derived from Integrated Resource Planning modeling; (b) eliminate the GHG Rebalancing component; and (c) cap total GHG value at the high societal cost of carbon. The Integrated Calculation moves from a Python optimization criticized by stakeholders as a black box to an Excel-based framework using RESOLVE GHG shadow prices; marginal capacity value would be derived from a hybrid solar-plus-storage resource rather than solved through the optimization. Hourly allocation changes are also substantive: staff would swap expected unserved energy for loss-of-load hours as the basis for capacity value allocation, on the theory that each avoided LOLH carries equal marginal reliability value regardless of shortfall magnitude. Temperature would give way to SERVM energy prices as the trigger for identifying high-capacity-value days, reflecting IRP modeling showing California's reliability risk migrating from hot summer peaks toward winter periods driven by electrification load and low renewable output. Staff also propose weekday/weekend differentiation consistent with reliability modeling and with downstream uses such as Net Billing Tariff export rates. The proposal is a reweighting of the economic signals that flow through DER cost-effectiveness tests, electrification incentives, gas-substitution economics, and Net Billing Tariff export rates across CPUC programs.
DR Draft Resolutions
Earliest vote Jul 2, 2026
Draft Resolutions · Demand Response
CPUC — Four Demand Response Draft Resolutions: SCE Direct Enrollment Approved, SDG&E Residential CBP Denied
Four CPUC draft resolutions impose stricter standards on Demand-Response program changes. E-5456 approves SCE direct customer enrollment in Capacity Bidding Program Elect (with SCE as aggregator). E-5444 denies SDG&E's proposed residential CBP for weakening penalties and lacking RA / load-impact filings. E-5450 gives PG&E partial approval for Automated Response Technology program changes but rejects a 30% capacity-payment hike. E-5453 approves, with modifications, a joint PG&E + SCE update to the Automated Demand Response Technology Incentive Program.
► Details
E-5456 (SCE): closes a participation shortfall that was leaving Self-Generation Incentive Program customers without a qualifying DR option when third-party aggregators withdrew. E-5444 (SDG&E): the proposal weakened penalties too far from the existing model and lacked the Resource Adequacy compliance and load-impact filings required of supply-side resources. E-5450 (PG&E ART): 30-day performance evaluation timeline, Day-of Adjustment standardization, CAISO tariff alignment, and minor formatting updates approved; the 30% capacity-payment rate increase rejected. E-5453 (Joint PG&E + SCE AutoDR): expands eligible customer segments and measures and adds PG&E's ART program as a qualified residential AutoDR program. The Commission will fix program-access problems and approve narrow implementation changes; it will not approve residential DR expansion or DER-based supply-side programs without the documentation that real capacity products require. Earliest vote July 2.
CAISO 2025-26 TPP
Approved Jun 2026
Transmission Plan · CAISO
CAISO — 2025-26 Transmission Plan Approved: $6.7B Across 38 Projects; Serrano-Del Amo-Mesa Cancelled
CAISO approved its 2025-2026 Transmission Plan, authorizing 38 projects totaling $6.7 billion over the next decade driven by reliability, policy, and congestion needs. Reliability is most of the package: 33 projects, $4.2B, led by the $1.424B Tesla-Trimble-Metcalf 230 kV corridor expansion in PG&E territory. Four policy-driven projects total $2.4B, including the $1.685B Trout Canyon-Lugo 500 kV line. The plan cancels the previously approved Serrano-Del Amo-Mesa 500 kV project, originally $1.125B, now re-priced by SCE at $5B.
► Details
CAISO is planning around load growth from electrification, data centers, manufacturing, and transportation. PG&E's Greater Bay Area dominates the reliability picture — Tesla-Trimble-Metcalf and related Bay Area upgrades indicate that South Bay load growth is now a system-planning driver, not a one-off interconnection issue. Path 15 congestion forecasts have moved from 244 hours on the most-limiting circuit in 2030 (per the 2021-2022 plan) to 3,256 hours forecast for 2035, supporting the Gates-Los Banos project now and pointing toward a larger backbone decision next cycle. The Serrano-Del Amo-Mesa cancellation shows the ISO will kill projects when costs outrun the original planning case; its reliability function is replaced with the Mesa-Laguna Bell 230 kV #2 Upgrade and the policy need dropped after updated resource portfolios. Transmission planning is becoming bigger, more iterative, and more politically exposed to large-load cost allocation.
R.23-12-008
VGI Joint Report filed Jun 6, 2026
Report · Transportation Electrification
CPUC — IOU Joint Vehicle-Grid Integration Report: Commercial Bidirectional Pilots Strong, Residential V2X Lags
A joint SCE, SDG&E, and PG&E report filed in R.23-12-008 records the CPUC's third annual Vehicle-Grid Integration Forum (March 25, 2026). Managed and bidirectional charging can reduce long-term distribution costs only through grid-aware coordination across bulk and distribution needs. Passive TOU-driven charging just moves load into new system peaks.
► Details
Vehicle-to-Grid commercial track record has promising data: Tellus Green Power's school-bus deployment ran 74 bidirectional chargers at 98%+ uptime over two years. Residential is a different story: PG&E's Vehicle-to-Everything pilots are behind enrollment targets, held back by equipment costs, customer-side integration complexity, and rate-design constraints. The record now shows the familiar California sequence: large theoretical avoided-cost value, thin customer uptake, rate design that can't target distribution-level constraints, uncertain export compensation, and pilots expiring before they generate scalable rules. The unresolved question is whether VGI can convert from pilot to scaled program before transportation electrification adds incremental peak load that the distribution system cannot absorb without bidirectional flexibility.
Prior Period
Apr 14 – May 31, 2026
4 items
R.26-04-009
Opened Apr 9, 2026
Rulemaking
Advanced Electric Rate Design OIR
CPUC opens rulemaking to redesign advanced electric rates for residential and non-residential customers, succeeding R.22-07-005. ALJ Joanna Perez-Green and Commissioner John Reynolds assigned April 22, 2026.
► Details
R.26-04-009 is the CPUC's successor rulemaking to R.22-07-005, which established the current advanced residential rate framework including default time-of-use rates and income-graduated fixed charges. The new OIR expands scope to non-residential customers and addresses rate design for high-electrification scenarios -- how rates should be structured as buildings and transportation shift to electricity. ALJ Joanna Perez-Green and Commissioner John Reynolds were assigned April 22, signaling Commission prioritization. The proceeding will shape how millions of California ratepayers are billed for electricity as the grid transitions and fixed-cost recovery shifts away from volumetric charges.
R.24-01-018
ALJ Ruling Apr 17, 2026
ALJ Ruling
CPUC — Energization Timelines ALJ Ruling: Bridge-Year Enforcement Framework
ALJ Dugowson issues a ruling in R.24-01-018 establishing the procedural framework for CPUC enforcement of electric service energization timelines — addressing how PG&E, SCE, and SDG&E must meet Rule 21 and new service connection deadlines as the Commission develops enforcement tools.
► Details
R.24-01-018 is the CPUC's rulemaking on energization timelines — the time it takes utilities to connect new customers, rooftop solar, and battery storage systems to the grid. Data shows PG&E and SCE meet Rule 21 interconnection timelines as little as 18% of the time, prompting the JLAC to authorize a state audit (JLAC 2026-126) and the CPUC to develop formal enforcement mechanisms.
This April 17 ALJ ruling by ALJ Dugowson sets out the procedural schedule and framework for how the Commission will enforce compliance going forward, including potential penalty mechanisms. The ruling is significant because it marks the CPUC's first formal procedural step toward creating binding enforcement tools for energization delays — a longstanding pain point for solar installers, EV charging developers, and customers awaiting new service connections.
A.24-12-011
Decision Apr 30, 2026
Application Denied
SoCalGas Angeles Link Hydrogen Pipeline — Cost Recovery DENIED
SoCalGas request to charge ratepayers for Phase 2 of the Angeles Link hydrogen transmission pipeline denied. CPUC found SoCalGas failed to identify specific ratepayer benefits, protecting customers from $266 million in escalated project costs.
► Details
Angeles Link is SoCalGas's proposed 36-inch hydrogen transmission pipeline spanning roughly 215 miles across Los Angeles County. The Phase 2 cost estimate ballooned from $92 million (2022) to $266 million (2024) -- a 189% increase before a single pipe was laid. SoCalGas applied to recover this cost from ratepayers under A.24-12-011. The CPUC rejected the request, holding that SoCalGas had not demonstrated specific, quantified ratepayer benefits sufficient to justify ratepayer funding. The decision effectively forces SoCalGas either to abandon Phase 2 or fund it with shareholder capital. Environmental and consumer groups including Sierra Club and EDF supported the denial, arguing the project would lock ratepayers into a hydrogen infrastructure bet that may not materialize as green hydrogen costs remain far above natural gas.
R.13-02-008
Decision Apr 30, 2026
Decision Adopted
Renewable Gas Standard — Biomethane Procurement Target Cut 50%
CPUC adopts decision reducing the 2030 biomethane procurement target from 72.8 to 36.4 billion cubic feet/year (50% reduction), extending targets and adding a cost containment mechanism to protect ratepayers from rate impacts.
► Details
R.13-02-008 is the CPUC's Renewable Gas Standard rulemaking, which sets mandatory procurement targets for biomethane (renewable natural gas from organic waste) that gas utilities must meet. The April 30 decision reflects a significant policy retreat: the 2030 annual procurement target was halved from 72.8 to 36.4 billion cubic feet, and both the Diverted Organic Waste and overall targets were extended from 2030 to 2035. A new Cost Containment Mechanism limits ratepayer exposure to above-market biomethane prices. All feedstocks remain eligible to bid into future utility solicitations, and all procurement contracts must go through Tier 3 Advice Letters regardless of price. Gas utilities must also submit revised Renewable Gas Procurement Plans. The decision reflects growing CPUC caution about the cost trajectory of renewable gas mandates as biomethane prices remain high relative to conventional gas.
R.25-07-013
Decision Apr 30, 2026
Decision Adopted
California Climate Credit — Distribution Shifted to Summer Months
CPUC adopts decision moving the PG&E residential electricity Climate Credit from April to August-September distribution to align the credit with peak summer billing. Total credit amount per household unchanged; timing only.
► Details
The California Climate Credit is a twice-yearly credit on utility bills funded by cap-and-trade auction revenue, providing meaningful bill relief for residential customers. For 2026, the April credit for PG&E residential electric customers was paused and redistributed to August and September -- when air conditioning demand drives bills to annual highs. For smaller utilities (Bear Valley, Liberty, Pacific Power), the credit shifts to April and November for 2026, then October and November in future years. The total annual credit per household remains the same; only the delivery timing changes. The policy rationale is straightforward: delivering bill relief when bills are highest has greater affordability impact than spreading it to lower-use spring months. The decision applies to the electric Climate Credit; gas credits follow a separate schedule.
A.24-03-019
Decision Apr 30, 2026
Decision Adopted
SCE 2024 General Rate Case Phase 2 — Rate Design Adopted
CPUC adopts rate design settlements in SCE's 2024 GRC Phase 2, finalizing how revenue authorized in Phase 1 is allocated across rate schedules and customer classes effective with the next rate cycle.
► Details
GRC Phase 2 proceedings set rate design -- the allocation of revenue requirement authorized in Phase 1 across SCE's various customer rate schedules (residential, commercial, industrial, agricultural, EV, etc.). The April 30 decision adopts the negotiated rate design settlements, locking in how SCE will recover its authorized revenue from different customer groups through at least the next general rate case cycle. Rate design outcomes directly affect the distribution of costs between high- and low-usage customers, the structure of tiered vs. flat rates, and the incentive signals embedded in time-of-use and demand charge schedules. The decision follows separate Phase 1 revenue requirement proceedings already concluded.
Res. E-5436
Adopted Apr 30, 2026
Resolution Adopted
California DGStats Platform — Funding Tripled to $2.6M
CPUC adopts Resolution E-5436, tripling the budget for the California Distributed Generation Statistics platform to $2.6 million per 3-year contract with annual inflation adjustment authority. DGStats is the statewide hub for rooftop solar, battery storage, and DER interconnection tracking.
► Details
The California DGStats platform (californiadgstats.ca.gov) aggregates interconnection data from all California IOUs and publishes monthly reports on distributed energy resource deployments -- rooftop solar capacity, battery storage installations, EV chargers, and interconnection queue status by utility and zip code. It is the authoritative public data source used by CPUC staff, researchers, local governments, and industry to track California's DER buildout.
Resolution E-5436 increases the contract budget from approximately $875,000 to $2.6 million per 3-year cycle -- roughly tripling current funding -- and authorizes the Energy Division to adjust annually for inflation. The funding increase reflects the platform's growing role as the backbone for CPUC interconnection planning, enforcement, and ICA (Integration Capacity Analysis) compliance tracking. All three large electric IOUs (PG&E, SCE, SDG&E) contribute data to the platform and fund it through their rates.
Prior Period
Apr 1 – Apr 13, 2026
7 items
►
R.26-04-001
Opened April 9, 2026
New Rulemaking
Large Load / Data Center Rate Design — New OIR Opened
CPUC opens a new Order Instituting Rulemaking to determine how system upgrade costs driven by surging data center and large-load demand are allocated across ratepayers — a decision that will shape grid expansion costs for millions of California customers.
► Details
With California data center electricity demand projected to grow 40–60% by 2030, the CPUC opened this rulemaking to establish durable rules for large-load cost allocation. The central policy question: when a new data center or industrial facility requires expensive grid upgrades, should that customer bear the full incremental cost, or should the costs be spread across all ratepayers?
Large-load customers argue that general ratepayer sharing is appropriate because all customers benefit from a more robust grid. Consumer advocates and ratepayer groups counter that socializing costs driven by a narrow class of high-demand customers amounts to an unjust subsidy. The proceeding follows the April 9, 2026 vote and will involve workshops, data requests, and potentially a phase for proposed decisions. A final decision is expected in 2027.
A.24-03-009
Adopted April 9, 2026
Adopted
PG&E — Citizens Energy $1B Transmission Lease Approved (§851)
The CPUC adopted the proposed decision authorizing PG&E to lease transmission entitlements to Citizens Energy Corporation under up to five 30-year leases worth up to $1 billion. After-tax profits — estimated at over $450 million over 35 years — will fund bill-payment assistance for low- and moderate-income PG&E customers.
► Details
The Commission adopted the decision authorizing PG&E to lease entitlements on new high-voltage transmission projects to Citizens Energy Corporation — a nonprofit — through up to five 30-year leases. Citizens Energy funds grid upgrades (safety, reliability, capacity) in exchange for the entitlements. The arrangement satisfies Public Utilities Code §851 public interest requirements, per the adopted decision by ALJ Jack Chang.
Total investment up to $1 billion. Citizens Energy commits to directing 50% of net after-tax profits to clean energy for low-income communities in Central and Northern California, rising to 90% over time. Over 35 years, the CPUC estimated after-tax profit flows to low-income customers at over $450 million.
Res. E-5440
Adopted April 9, 2026
Resolution Adopted
ICA Remediation Plans Adopted — PG&E, SCE, SDG&E Ordered to Fix Interconnection Capacity Data
The CPUC adopted Resolution E-5440, directing PG&E, SCE, and SDG&E to correct Integration Capacity Analysis data deficiencies within a specified compliance timeline. Accurate ICA data governs distributed energy resource interconnection across all three service territories.
► Details
The Integration Capacity Analysis (ICA) is a map-based tool showing how much distributed energy resource capacity each grid segment can accommodate without costly upgrades. CPUC staff found that all three large IOUs had methodology errors and data gaps that could mislead rooftop solar, battery storage, and EV charger applicants about available interconnection headroom.
Resolution E-5440, adopted at the April 9, 2026 voting meeting after being held from March 19, requires each utility to submit corrected ICA data and a remediation plan to CPUC staff within a specified timeline. Failure to provide accurate ICA data can cause developers to incur pre-development costs for projects that will ultimately face prohibitive grid upgrade requirements — a longstanding complaint from the California solar and storage industry.
A.24-06-001
Adopted April 9, 2026
Adopted
SDG&E — 2023 ERRA Compliance: $214.6M Net Undercollection Approved for Recovery
The CPUC adopted the proposed decision in A.24-06-001, approving SDG&E's recovery of a net $214.6 million 2023 energy procurement undercollection with modifications to RA portfolio valuation, RPS accounting, and battery storage revenue allocation. Commissioner Christine Harada presided after a March 19 holdover.
► Details
The Energy Resource Recovery Account (ERRA) mechanism allows SDG&E to track and recover reasonable energy procurement costs that differ from the forecast embedded in rates. The 2023 compliance filing reviewed whether procurement was prudent and consistent with the Commission-approved plan. The net $214.580 million undercollection flows back to customers through future rate adjustments.
The adopted decision includes modifications: SDG&E must update its resource adequacy portfolio valuation methodology, correct RPS compliance accounting, allocate battery storage revenues across a broader customer base, and recover Stranded Green Tariff Shared Renewables costs via the Public Purpose Programs charge. The item was held from the March 19 voting meeting to April 9 following reassignment to Commissioner Christine Harada.
A.22-05-022
PD Issued Apr 7, 2026
Proposed Decision
PG&E — Green Tariff Shared Renewables & DA Community Solar Programs PD
ALJ Kao issues a proposed decision implementing PG&E's Green Tariff Shared Renewables, Disadvantaged Communities Green Tariff, and Community Solar Green Tariff programs — establishing program rules, customer enrollment procedures, and cost-recovery mechanisms for this shared clean energy portfolio.
► Details
California's Green Tariff Shared Renewables program allows customers — including renters and others who cannot install rooftop solar — to subscribe to a share of a utility-owned or utility-contracted renewable energy project and receive a credit on their bill. The Disadvantaged Communities Green Tariff extends this model specifically to low-income customers in disadvantaged communities with additional subsidy. The Community Solar Green Tariff involves smaller, community-scale projects with local siting requirements.
This consolidated PD (covering A.22-05-022, A.22-05-023, and A.22-05-024) implements the regulatory framework for all three programs — setting subscription sizes, credit calculation methods, program caps, and cost allocation to non-participating ratepayers. The decision will affect how hundreds of thousands of California customers who want renewable energy access clean power without installing their own systems. Comments are expected in late April 2026.
A.24-03-018
PD Issued Apr 10, 2026
Proposed Decision
PG&E — Diablo Canyon Extended Operations Cost Recovery (Sep 2023 – Dec 2025)
ALJ Atamturk issues a proposed decision granting in part PG&E's petition to modify D.24-12-033, authorizing recovery of extended operation costs incurred at Diablo Canyon from September 2023 through December 2025 and addressing 2025 volumetric performance fees.
► Details
Diablo Canyon Power Plant — California's last operating nuclear facility, with 2,200 MW of carbon-free generation — was extended beyond its original 2025 closure date through state legislation (SB 846, 2022) and a Department of Energy loan to PG&E. The facility's continued operation required significant incremental costs: maintenance, licensing fees, and regulatory compliance from September 2023 onward that were not included in prior rate cases.
This PD addresses PG&E's request to modify D.24-12-033 to authorize recovery of those incremental costs from ratepayers. The Commission previously approved a framework for Diablo Canyon cost recovery; this proceeding resolves the specific amounts for the September 2023 through December 2025 period and sets 2025 performance fee volumes. The decision is significant for California's nuclear policy and for the broader question of how ratepayers bear the cost of facility life extensions driven by state policy decisions. An alternate PD was also filed concurrently, indicating commissioner-level disagreement on scope or methodology.
A.26-01-007
PD Issued Apr 10, 2026
Proposed Decision
SCE — Woolsey Fire Recovery Bond Securitization: Financing Order PD
ALJ DeAngelis issues a proposed decision authorizing SCE to issue rate reduction bonds to securitize its Woolsey Fire wildfire costs under AB 1054 — converting higher-cost traditional rate base recovery into lower-cost bond financing to reduce the total burden on ratepayers.
► Details
AB 1054 (2019) established a wildfire fund and authorized utilities to securitize approved wildfire costs through rate reduction bonds (also called catastrophe bonds or securitization bonds). Securitization replaces traditional utility financing — where the utility borrows at its weighted average cost of capital — with lower-cost bond financing backed by a non-bypassable charge on customer bills. Because bonds carry lower interest rates than utility debt, securitization reduces the total cost of recovery for ratepayers over the repayment period, typically 15–25 years.
SCE's application (A.26-01-007) seeks a financing order authorizing approximately $1.84 billion in rate reduction bonds for approved Woolsey Fire costs. This PD, if adopted, would issue the financing order allowing SCE to go to market with the bonds. The non-bypassable charge on bills provides bondholders security equivalent to a senior utility obligation — enabling the lower financing cost. Comments on the PD are due in late April 2026, with a decision expected at the May or June 2026 voting meeting.
Prior Period
Mar 14 – Mar 31, 2026
3 items
►
A.24-05-014
Adopted Mar 19, 2026
Adopted (Consent)
LS Power — "Power the South Bay" 230-kV Transmission CPCN Approved — $813M
ALJ Nilgun Atamturk recommends approval; Commission adopts on consent. LS Power is granted a CPCN to construct a 12-mile 230-kV transmission line connecting PG&E's Newark substation to Silicon Valley Power's Northern Receiving Station, with an LS Power cost cap of $813.2 million. In-service target: June 1, 2028.
► Details
A CPUC CPCN is required before a developer can construct new electric transmission facilities in California. The CPCN process reviews need, site suitability, environmental impacts, and consistency with CAISO transmission planning requirements.
The Power the South Bay Project is a 12-mile 230-kV double-circuit transmission line running from PG&E's Newark substation (Alameda County) to Silicon Valley Power's Northern Receiving Station in San Jose. The project addresses transmission constraints in the South Bay load pocket and supports load growth from data centers and electrification. LS Power's cost cap is $813,240,000; the broader project including related PG&E substation work totals approximately $1.59 billion. Construction was authorized to begin March 2026 with a June 1, 2028 in-service deadline. Commissioner Karen Douglas presided; the item passed on the consent agenda.
A.09-09-022
Adopted Mar 19, 2026
Adopted (Consent)
SCE — Alberhill System Project CPCN Approved: $481.7M Transmission
Commission adopts the Alberhill System Project CPCN on consent. SCE is authorized to construct transmission lines and substations in western Riverside County, with a capital cost cap of $481.7 million (2023 dollars, including 15% contingency). In-service target consistent with Inland Empire load growth timeline.
► Details
Originally filed September 2009, the Alberhill System Project is one of the longest-running CPUC transmission proceedings in recent history. The project addresses transmission constraints in the western Riverside County load pocket driven by Inland Empire population growth and electrification load. Years of route modifications, environmental review, and community opposition delayed final CPCN authorization.
The Commission granted the CPCN on the consent agenda at the March 19, 2026 voting meeting — reflecting unanimous staff and ALJ recommendation. Capital cost cap: $481,700,000 (2023 constant dollars), including a 15% contingency of $53.8 million. Costs are recovered through SCE's FERC-regulated transmission rate base — borne by all SCE ratepayers through transmission charges on monthly bills. The proceeding closes upon adoption.
A.24-04-017
Adopted Mar 19, 2026
Adopted (Consent)
LS Power — Santa Clara Valley Transmission CPCN Approved: $1.593B
LS Power Grid California granted a CPCN to construct a high-voltage transmission line serving the Santa Clara Valley at a capital cost cap of $1,593 million — primarily to meet surging data center load in the San José area. Adopted on the consent agenda at the March 19, 2026 voting meeting.
► Details
LS Power Grid California proposed a new high-voltage transmission line to deliver power to the Santa Clara Valley in response to surging data center electricity demand in the San José metro area. PG&E's Ringwood Substation interconnection queue had grown to over 15,000 MW of pending requests — far exceeding available capacity under the existing grid.
The CPCN approved at the March 19, 2026 voting meeting authorizes construction with a capital cost cap of $1,593,000,000. As a merchant transmission project, LS Power will recover costs through bilateral contracts with data center customers and LSEs — not through PG&E's regulated rate base. This approach shields ratepayers from direct cost recovery risk while enabling faster permitting than CAISO-driven transmission planning processes.
Prior Period
Mar 2 – Mar 13, 2026
4 items
►
A.24-04-001
PD Released Mar 6, 2026
Proposed Decision
SCE — 2023 Energy Resource Recovery Account (ERRA) Compliance
SCE's 2023 ERRA compliance — PD identifies a $63.2 million decrease in revenue requirement, flowing to customers as a net rate reduction. Comments due March 26, 2026.
► Details
SCE's annual ERRA compliance filing for 2023 — the Commission reviews whether procurement was reasonable and consistent with its approved plan. The ERRA mechanism ensures customers pay only for prudent energy costs; overcollections flow back as rate reductions. Proposed Decision issued by ALJ Jeffrey Lee.
The PD addresses a $63.195 million decrease in revenue requirement across seven accounts — customers receive a net rate reduction reflecting an overcollection in 2023. Comments due March 26, 2026.
A.21-06-021
Phase III Closed Mar 5, 2026
Phase III Closed
PG&E — 2023 General Rate Case Phase III Closed (D.26-02-035)
The Commission issued D.26-02-035 closing Phase III of PG&E's 2023 General Rate Case, completing the ratesetting proceeding for PG&E's electric and gas service effective January 1, 2023.
► Details
PG&E's 2023 GRC was split into three phases: Phase I set the revenue requirement (adopted in D.23-12-037); Phase II addressed nuclear operations and wildfire-related capital; Phase III resolved remaining contested issues including vegetation management cost recovery and outstanding intervenor claims.
D.26-02-035 formally closes Phase III after resolving all remaining issues, allowing the proceeding record to be finalized. Closure of Phase III does not reset or alter currently effective rates — all rate changes from this GRC were set at Phase I adoption effective January 1, 2023. The next GRC cycle (2027 GRC, A.25-06-016) will set rates effective January 1, 2027.
R.20-08-020
Court Ruling Mar 9, 2026
Court Upheld
NEM 3.0 — Court of Appeal Upholds D.23-02-015; Challenge Closed
California Court of Appeal upholds NEM 3.0 (D.23-02-015), which reduced solar export compensation for new residential solar customers to ~$0.05–$0.08/kWh — down from ~$0.30/kWh under prior NEM 2.0. Proceeding closed.
► Details
NEM 3.0 (D.23-02-015), adopted April 2023, replaced California's highly compensatory NEM 2.0 tariff for new rooftop solar customers. Under NEM 2.0, utilities credited solar exports at the full retail rate (~$0.30/kWh). Under NEM 3.0's Net Billing Tariff, new customers receive Avoided Cost Calculator-based rates averaging $0.05–$0.08/kWh — an ~80% reduction. Existing NEM 2.0 customers are grandfathered for 20 years.
Solar industry groups and several municipalities challenged the decision in court, arguing the CPUC failed to meet public notice requirements and violated the renewable energy mandate. California's First District Court of Appeal upheld the CPUC's decision on March 9, 2026 — rejecting all procedural and substantive challenges. NEM 3.0 remains binding law; the rooftop solar compensation question is now definitively resolved for the foreseeable future.
Prior Period
Feb 16 – Feb 27, 2026
2 items
►
I.23-03-008
Adopted Feb 26, 2026
Adopted 4–0 · Closed
Winter 2022–23 Natural Gas Price Spike Investigation — No Misconduct Found
No misconduct found in the winter 2022–23 gas spike; PG&E, SoCalGas, and storage providers exonerated. Core Procurement Charge cap adopted prospectively — triggered when monthly core price exceeds 150% of the 10-year average.
► Details
Opened March 2023 following the winter 2022–23 gas spike — some SoCalGas customers received bills exceeding $400 in January 2023. The Commission investigated whether PG&E, SoCalGas, SDG&E, and independent storage operators engaged in market manipulation, withholding, or imprudent procurement. After nearly three years, the Commission closed the investigation with no finding of misconduct, attributing the spike to coincident demand peaks and pipeline constraints outside California.
No penalties, fines, or refund orders against any utility. Prospective remedy: Core Procurement Charge (CPC) cap triggered when monthly core procurement price exceeds 150% of the 10-year average (November–March window). Undercollections amortized — not borne by shareholders.
R.25-06-019
Adopted Feb 26, 2026
Adopted — Unanimous
IRP — 6,000 MW Clean Energy & Storage Procurement Order
Orders all California LSEs to procure 6,000 MW of non-GHG-emitting capacity by 2030–2032. SCE: 2,088 MW · PG&E: 1,077 MW · CCAs: remainder. At least 25% must be long-duration or clean firm. Adopted 5–0.
► Details
President Alice Reynolds' final act. Requires all California load-serving entities — IOUs, CCAs, and ESPs — to procure 6,000 MW of new non-GHG-emitting capacity across three equal tranches. Each tranche: no more than 50% battery storage; at least 25% must be long-duration (≥8 hours) or clean firm. Adopted unanimously 5–0.
No revenue requirement set in this decision — it is a procurement mandate, not a ratesetting order. LSE obligations: SCE 2,088 MW · PG&E 1,077 MW · CCAs allocated the remainder. Costs flow into future GRC proceedings as contracts execute. Tranche 1 NQC deadline: December 31, 2030.
Prior Period
Feb 2 – Feb 13, 2026
3 items
►
A.25-06-012
PD Issued Feb 13, 2026
Proposed Decision
SoCalGas — Gas Cost Incentive Mechanism (GCIM) Year 31 Shareholder Award
SoCalGas earns a $8.374 million shareholder award under GCIM Year 31 — procurement came in $42.1 million below benchmark. $33.77 million flows to ratepayers as lower gas costs.
► Details
The Gas Cost Incentive Mechanism (GCIM) is SoCalGas's procurement performance incentive, in place since the mid-1990s. Each year the CPUC reviews whether SoCalGas beat or missed its benchmark procurement cost. A positive result triggers a shareholder reward; a negative result triggers a shareholder penalty. The mechanism aligns utility incentives with ratepayer interests in keeping gas costs low.
Shareholder reward: $8,374,056 for GCIM Year 31 (2024–2025 gas year). SoCalGas's recorded procurement costs were $42,142,370 below benchmark, of which $33,768,315 flows to ratepayers as lower gas costs and $8,374,056 goes to shareholders. Customers save roughly $4 for every $1 awarded to shareholders.
A.25-06-007
PD Issued Feb 12, 2026
Proposed Decision
SCE — $9.85B Debt & $1.155B Preferred Equity Authorization
SCE authorized up to $9.85 billion in long-term debt and $1.155 billion in preferred equity for capital programs — $525 million below SCE's original $10.375B request.
► Details
Utilities seek CPUC authority to issue debt and equity in advance of actual issuances, allowing them to move quickly when capital market conditions are favorable. This authorization covers SCE's anticipated capital needs driven by its wildfire mitigation capital program (WMCE), infrastructure replacement, and clean energy integration.
Authorized: $9,850,000,000 in long-term debt (SCE requested $10,125,000,000 — reduced by $275,000,000) and $1,155,000,000 in preferred equity (reduced by $250,000,000). Actual issuances within this cap do not require additional CPUC approval. Cost recovery occurs as capital is deployed and included in future GRC proceedings.
A.25-08-008
Adopted Feb 5, 2026
Interim Auth. Adopted
SoCalGas — Distribution Integrity Management Program $35.5M Interim Rate Recovery
D.26-02-006 grants SoCalGas a $35.5 million interim authorization (60% of $59.1M requested) for DIMP costs 2019–2023. 12-month authority; overage refunded with interest if final amount differs.
► Details
The Distribution Integrity Management Program (DIMP) is a federally-mandated natural gas pipeline safety program requiring operators to assess and remediate risks across their distribution systems. SoCalGas operates one of the largest gas distribution networks in North America — approximately 100,000 miles of pipeline serving 21 million customers.
Interim rate authority allows SoCalGas to recover $35,500,000 of the $59,100,000 claimed for DIMP costs incurred 2019–2023 while the full rate case proceeds. The interim amount represents a 60% grant — a common Commission approach to balance utility cash flow needs against unresolved prudency questions. Any amount recovered under the interim authorization that exceeds the final approved amount must be refunded to ratepayers with interest. The 12-month authorization expires in early 2027.
Prior Period
Jan 2 – Jan 16, 2026
7 items
►
A.22-05-015/016
Voted Jan 15, 2026
Decision
SDG&E / SoCalGas — Wildfire Mitigation Cost Recovery GRC (2019–2022)
SDG&E wildfire mitigation cost recovery: Commission disallows $434.9 million — approving $90.6M of $284M O&M and $945.2M of $1,188M capital requested.
► Details
The Commission rules on SDG&E's wildfire mitigation cost recovery within its consolidated General Rate Case (A.22-05-015/016 with SoCalGas). SDG&E sought recovery of $284 million in wildfire-related operations and maintenance costs and $1,188 million in capital expenditures incurred from May 2019 through December 2022. The Commission approved $90.6 million in O&M (disallowing $192.6M) and $945.2 million in capital (disallowing $242.4M) — a combined disallowance of approximately $434.9 million, signaling heightened scrutiny of wildfire mitigation spending and cost controls. The decision reinforces the Commission's use of cost reasonableness review to protect ratepayers from imprudent utility capital investments.
A.23-04-003
PD Voted Jan 15, 2026
Decision
SCE — ERRA Compliance Review 2022
SCE found compliant with its adopted procurement plan for 2022; $51.4 million in recorded energy procurement costs authorized for recovery.
► Details
The Commission reviews SCE's Energy Resource Recovery Account (ERRA) compliance for the record period January 1 through December 31, 2022. The PD finds that SCE's procurement-related operations — including power purchases, generation dispatch, and greenhouse gas compliance instrument procurement — complied with its adopted procurement plan. SCE's request to recover $51.442 million in costs recorded across five regulatory accounts is authorized. ERRA compliance proceedings are annual filings required of each electric IOU to verify that procurement spending was prudent and consistent with Commission-approved plans before costs are passed through to ratepayers.
Res. E-5437
Adopted Jan 15, 2026
Resolution
PG&E — Dirac 225 MW Battery Storage (Balsam/Aypa Power)
PG&E approved to contract with Balsam Project (Aypa Power) for a 225 MW lithium-ion battery energy storage system, 15-year contract, commercial operation May 2028.
► Details
The Commission approves PG&E's contract with Balsam Project LLC (developed by Aypa Power) for the Dirac Battery Energy Storage System, a 225 MW lithium-ion facility with a commercial operation date of May 20, 2028. The 15-year contract begins August 1, 2028. The procurement supports California's grid reliability and clean energy integration goals — battery storage is critical for absorbing excess solar generation during midday and discharging during evening peak demand periods. Contract costs flow through PG&E's procurement cost recovery mechanisms and are ultimately borne by ratepayers.
Res. E-5396
Adopted Jan 15, 2026
Resolution
PacifiCorp — Income-Graduated Fixed Charge (BSC) Approved
PacifiCorp income-graduated fixed charge (basic service charge) for residential customers approved with modifications per D.24-05-028 AB 205 rate reform framework.
► Details
The Commission approves, with modifications, PacifiCorp's Advice Letters implementing an income-graduated fixed charge (basic service charge) for residential customers, as directed by Decision 24-05-028. The income-graduated fixed charge is part of California's AB 205 rate reform, which restructures electric rates to include a fixed monthly charge scaled to household income — reducing the per-kWh volumetric rate in exchange. PacifiCorp serves a small portion of northeastern California; this approval extends the fixed charge framework beyond the three large IOUs and establishes precedent for the broader statewide rollout.
R.21-03-011
Decision Jan 15, 2026
Decision
Provider of Last Resort (POLR) Guidelines — SB 520
Commission adopts streamlined POLR eligibility guidelines for non-IOU entities under SB 520, opening CCA and other entities to seek full POLR designation.
► Details
The Commission adopts a decision establishing streamlined eligibility guidelines for non-IOU entities seeking Provider of Last Resort (POLR) designation under Senate Bill 520. POLR is the obligation to serve customers who lose their electricity provider — historically this responsibility has fallen to IOUs as default. SB 520 opened the door for community choice aggregators (CCAs) and other entities to apply for POLR status. The adopted guidelines specify application requirements and evidentiary standards. As of this decision, no non-IOU entity has formally sought comprehensive POLR designation, but the framework is now in place for future applicants.
R.18-07-003
Decision Jan 15, 2026
Petition Denied
BioMAT Tariff End-Date Extension — Petition Denied
Petition to extend the Bioenergy Market Adjusting Tariff (BioMAT) beyond its December 2025 end date denied; program closes as scheduled per Governor Newsom's Executive Order N-5-24.
► Details
The Commission denies a petition by the Bioenergy Association of California (BAC) to modify Decision 20-08-043 and extend the Bioenergy Market Adjusting Tariff (BioMAT) program beyond its scheduled end date of December 31, 2025. BioMAT provided feed-in tariff contracts for small bioenergy facilities — including dairy biogas, forest biomass, and landfill gas projects — interconnected to IOU distribution systems at above-market rates. The denial is consistent with Governor Newsom's Executive Order N-5-24, which maintained the BioMAT sunset date. The program's closure shifts bioenergy procurement to other pathways, including the Renewable Gas Standard and bilateral power purchase agreements.
Prior Period
Jan 19 – Jan 30, 2026
3 items
►
A.24-05-008
PD Released Jan 30, 2026
Proposed Decision
PG&E — Risk Assessment Mitigation Phase (RAMP) Proceeding Close
Proposed Decision to close PG&E's RAMP proceeding — confirms the RAMP record is accepted as informational and incorporated into its General Rate Case.
► Details
The Risk Assessment Mitigation Phase (RAMP) is a CPUC-mandated pre-GRC safety proceeding. Before filing a GRC, each large IOU must conduct a structured safety risk assessment across its assets — using a defined risk model — and file the RAMP report for Commission review. The RAMP record informs the Commission's evaluation of GRC safety spending requests but does not itself set rates.
Closing the RAMP proceeding formally incorporates the RAMP record into the GRC proceeding record and ends the standalone RAMP docket. The adopted RAMP report for PG&E's 2027 GRC cycle was already submitted; this closure is procedural. No direct rate impact — RAMP outcomes influence but do not directly determine approved GRC safety spending levels.
R.19-10-005
PD Released Jan 23, 2026
Proposed Decision
EPIC Phase 4 — Strategic Objectives & Triennial Investment Plan PD
Proposes the Electric Program Investment Charge (EPIC) Phase 4 triennial plan, updating strategic objectives for clean energy technology R&D investment by PG&E, SCE, and SDG&E.
► Details
The Electric Program Investment Charge (EPIC) is a customer-funded clean energy R&D program managed by the California Energy Commission (CEC) and the three large electric IOUs — PG&E, SCE, and SDG&E. Customers pay the EPIC charge (~$130–$170 million per year statewide) to fund applied research, technology demonstrations, and market facilitation for renewable energy, grid integration, and demand response.
Phase 4 covers 2026–2028. The PD updates investment priorities to align with California's evolving clean energy goals — including offshore wind integration, long-duration storage, building electrification, and grid modernization. IOU-administered funds focus on projects with near-term deployment potential in IOU territories; CEC-administered funds cover longer-horizon R&D. The EPIC charge is a small surcharge on all electric bills — ratepayers fund this program indirectly through their electricity rates.
R.10-05-004
PD Released Jan 21, 2026
Proposed Decision
CSI/SGIP — Petition for Modification Denied
Denies a petition to modify the Self-Generation Incentive Program (SGIP) and California Solar Initiative (CSI) incentive structures.
► Details
The Self-Generation Incentive Program (SGIP) provides rebates to customers who install behind-the-meter energy storage, fuel cells, or other clean generation resources. The California Solar Initiative (CSI) funded incentives for rooftop solar installations — its funding is largely exhausted, but the program framework remains in CPUC rulemaking. Petitions for modification (PFMs) allow stakeholders to formally request changes to prior Commission decisions.
This PD denies the petition, maintaining the existing SGIP incentive tiers and CSI framework without modification. The petitioner's proposed changes — not specified in the card — were found insufficient to warrant reopening the rulemaking. SGIP is funded by a surcharge on electric bills for PG&E, SCE, and SDG&E customers; denial of this PFM preserves current incentive structures and budget allocations.
No matches for selected IOU.