Bundled Average Retail Rate

¢/kWh, January 1 each year · bundled utility customers

CPUC Distribution Rate Base

$B · CPUC-jurisdictional distribution · dashed = pending proceedings

Source: CPUC Historical Electric Cost Data, pursuant to SB 695. Projected = cumulative Distribution RRQ from pending CPUC applications.


Applications Filed

Current Period
Sep 16 – Sep 30, 2026
0 filings
No new energy applications were docketed at the CPUC in this period. The Commission’s new-filings list for the week of September 14–18 shows one application, A.26-09-005 — a telephone-corporation registration filed September 14, outside both this period and CalReg’s scope.
Prior Period
Sep 1 – Sep 15, 2026
3 filings
EPIC 5 · Filed Sep 2026 · Investment Plans · 2026–2030

EPIC 5 Investment Plans — ~$1.07 Billion Across Four Administrators; SCE Alone Declines an Inflation Adjustment

California’s four Electric Program Investment Charge administrators filed 2026–2030 EPIC 5 plans totalling about $1.07 billion. The CEC, which administers roughly 80% of EPIC funding, requests $879 million including an 18.79% inflation adjustment. PG&E seeks $101.027 million (a 9% increase), SDG&E $17.094 million (5%), and SCE $76.035 million with no inflation adjustment, citing affordability. The CEC estimates its adjustment would add ~$27.8 million annually, raising average electric rates 0.045%.

► Details
The CEC plan runs nine initiatives led by $143.9 million for DER and load flexibility, $126.1 million for building and community-scale decarbonization, $109.155 million for transportation electrification, $105.4 million for industrial decarbonization and $89.2 million for connecting clean resources and new loads, plus $131.85 million for administration. PG&E proposes six initiatives and 14 research topics, weighted toward advanced planning and operating capabilities and community resilience; its $8.342 million inflation request is about half what its CPI-W calculation would permit. SCE proposes 17 topics around grid efficiency and flexibility, digital grid planning, field sensing and advanced field operations — grid-enhancing technologies, DC networks, next-generation conductors, digital substations, drones, robotics and asset sensors. SDG&E proposes seven topics across four initiatives, including evaluation of sodium-ion batteries as a lithium-ion alternative.

The filings push EPIC toward near-term operating problems: interconnection, load growth, DER orchestration, flexible demand, wildfire resilience and advanced sensing. They differ mainly on funding posture. SCE also seeks Tier 3 advice-letter authority to add future research topics; SDG&E asks that all IOUs receive that flexibility.
CRC v. Pacific Pipeline · Filed Sep 2026 · Complaint · Crude Transportation

California Resources Corp. Complaint — Line 63 Shipments Cut ~54% by Line 2000 Priority on the Shared Tehachapi Segment

California Resources Corporation asks the CPUC to stop Pacific Pipeline System from giving Line 2000 crude shipments priority over Line 63 when the shared segment crossing the Tehachapi Mountains is capacity-constrained. CRC relies on Line 63 to move crude from Kern County to Los Angeles-area refineries. It says its Line 63-dependent volumes have fallen about 54% from normal levels — roughly 14,500 barrels per day, and as much as 62% in a single month — with losses of approximately $3.8 million through May 31 and damages still accruing. CRC wants curtailments allocated pro rata among Line 63 shippers.

► Details
In 2017 Pacific asked the CPUC to idle the Line 63 trunkline across the Tehachapis and route those shipments over a shared Line 2000 segment. The Commission approved the change after Pacific said Line 63 shippers would not be adversely affected. CRC now argues that the resulting configuration leaves Line 63 shippers bearing the capacity risk whenever the shared route is constrained, violating the Line 63 tariff and the Public Utilities Code by giving Line 2000 shippers preferential treatment. Pacific rejected the claim in June as without merit.

The dispute places the CPUC in the middle of a significant constraint between Kern County production and Los Angeles refineries. It also arrives as CRC expands its own midstream footprint: CRC closed a $63 million acquisition of Crimson Midstream on September 1, adding approximately 2,000 miles of pipeline. The proceedings are separate, but the Line 63 dispute illustrates the transportation exposure CRC is seeking to reduce as it gains control over infrastructure connecting California crude production to downstream markets.
SoCalGas SPM 2025 · Amended Aug 31, 2026 · Safety Report · RAMP Spending

SoCalGas Amends Its 2025 Safety Performance Metrics Report — Capital Ran 15% Above Imputed Authorization, O&M 2% Below

SoCalGas amended its 2025 Safety Performance Metrics Report on August 31 to add risk-mitigation spending data unavailable when it filed in April, incorporating finalized figures from its July 31 Risk Spending Accountability Report. RAMP-related O&M came in at about $602.4 million, roughly $12.1 million (2%) below the $614.5 million imputed authorized amount. Capital spending totalled about $1.05 billion, $137.8 million (15%) above the $907.6 million imputed level. The main safety metrics are otherwise unchanged.

► Details
On the O&M side, high-pressure-system spending ran $38.4 million above the imputed level while medium-pressure was $45.8 million below; cybersecurity and physical security were 60% and 128% above imputed levels respectively, though both are small in absolute dollars. The largest capital overruns were storage-system work ($65 million) and medium-pressure-system work ($46.6 million); employee-safety capital ran 139% above imputed.

The report also carries SoCalGas’s 20 applicable CPUC safety metrics for 2025: 2.01 third-party dig-ins per 1,000 USA tickets, average emergency response of 23.38 minutes (19-minute median), 100% of scheduled storage baseline inspections completed, and 2,344 miles (about 70%) of transmission pipeline capable of internal inspection. SoCalGas reported nine serious public injuries and no fatalities, no missed in-line inspections, no overdue gas-operation corrective-action work orders, and one distribution and one transmission overpressure event.

The comparison has an important limitation: the 2024 GRC did not separately identify RAMP funding, so SoCalGas had to impute authorized amounts for some mitigation activities, and its accounting systems do not track costs by individual RAMP risk. The figures are a directional comparison, not a clean authorized-versus-recorded test.
Earlier Period
Aug 16 – Aug 31, 2026
0 filings
No new applications were docketed at the CPUC in this period.
No matches for selected IOU.

Advice Letters

Utility advice-letter filings — rate and revenue updates, tariff changes, compliance filings and non-standard interconnection packages. Commission resolutions disposing of these filings are carded under Proposed Decisions & Rulings.

Current Period
Sep 16 – Sep 30, 2026
1 filing
AL 6693-G · Filed Sep 16, 2026 · Advice Letter · Biomethane Procurement

SoCalGas Seeks Approval of Biomethane Contracts With United Energy Trading and Rialto Bioenergy — First Test of the Reduced 36.4 Bcf RGS Target

SoCalGas filed Advice Letter 6693-G asking the CPUC to approve biomethane procurement agreements with United Energy Trading and Rialto Bioenergy Solutions, negotiated with projects carried over from its 2025 solicitation. The contracts would help SoCalGas and SDG&E meet combined annual targets of about 9.9 Bcf of biomethane from diverted organic waste and 21.7 Bcf under the overall Renewable Gas Standard by 2035. One selected project would use pyrolysis to convert landfill-diverted walnut shells into biomethane. SoCalGas says the agreements pass the program’s 3% annual increase cap and 1% annual average program cost cap. Protests are due October 1.

► Details
Prices, volumes, contract terms, project milestones and cost calculations are confidential. SoCalGas proposes recovering net above-market costs from all gas end-use customers through a non-bypassable, equal-cents-per-therm transportation charge, subject to the outcome of the pending biomethane cost-allocation proceeding — see the competing Houck and Reynolds proposed decisions carded under Proposed Decisions & Rulings.

The agreements are an early test of the revised Renewable Gas Standard. In D.26-04-044 the CPUC reduced the overall RGS target from 72.8 to 36.4 Bcf annually, extended the compliance deadline from 2030 to 2035 and added cost-containment limits. SoCalGas states both agreements pass those limits, but confidentiality prevents independent assessment of the prices and calculations.

The bilateral negotiations illustrate the difficulty of converting eligible projects into completed contracts: both projects qualified during the 2025 solicitation but needed additional time to conclude negotiations. Approval would advance the utilities’ procurement targets while spreading the resulting above-market costs across all gas customers.
Prior Period
Sep 1 – Sep 15, 2026
5 filings
AL ELEC 7972-E · Filed Sep 2026 · Advice Letter · Protests Sep 17

PG&E Reports a $225 Million ERRA Overcollection — 5.4% Trigger Breached, But No Rate Change Requested

PG&E notified the CPUC that its ERRA trigger balance reached a $225 million overcollection in July — 5.4% of prior-year generation revenues, exceeding the 5% threshold. PG&E anticipates the overcollection will peak at about $247 million in September before declining to roughly $120 million by year-end. The utility is not requesting a rate change, saying the overcollection should self-correct within 120 days under existing rates. Protests are due September 17.

► Details
The balance represents amounts collected from bundled customers above recorded power costs. PG&E’s forecast remains sensitive to market prices, customer demand and the final 2026 market price benchmarks — which Energy Division has not yet issued. That dependency is the main open question: PG&E expects the overcollection to unwind without an interim rate adjustment, but the projection rests partly on benchmarks that do not yet exist.
AL ELEC 7970-E · Filed Sep 2026 · Joint Advice Letter · Protests Sep 14

Joint IOU Advice Letter Opposes a Single Statewide Reverse-Power-Flow Method in Integration Capacity Analysis

California’s three large electric IOUs are asking the CPUC to preserve their differing approaches to reverse power flow in Integration Capacity Analysis, arguing that alignment on a single statewide methodology is not warranted at this time. The utilities separate two questions — where reverse flow should be evaluated, and whether it should appear as a standalone ICA criterion — and oppose standardization on both. SCE evaluates reverse-flow limits at the substation level within its thermal-study framework, PG&E uses a separate “Safety Bank” criterion, and SDG&E evaluates reverse flow primarily at the feeder level. Protests are due September 14.

► Details
The utilities say changing those approaches could take approximately 12–18 months, with PG&E estimating about $500,000 in implementation costs. They frame the issue as a tradeoff between statewide consistency and utility-specific engineering practice, arguing that standardization could increase confidentiality redactions and reduce the usefulness of ICA and Limited Generation Profile data.

Use of LGP remains extremely limited: PG&E reports one active application statewide, with none at SCE or SDG&E. PG&E says no headline ICA-Static Grid values are currently redacted, although about 12.9% of line sections have at least one redacted hourly value.

For DER developers, the Commission’s eventual disposition could affect how much interconnection capacity shows up as usable on ICA maps and LGP profiles without upgrades.
AL 6687-G · Filed Sep 2026 · Advice Letter · SB 1221 Map Update

SoCalGas Reports Completed SB 1221 Map Updates — Priority Decarbonization Zones Incorporated, Two Tribes Responded

SoCalGas told the CPUC it has completed required updates to its SB 1221 maps, including incorporating the Priority Neighborhood Decarbonization Zones designated by the Commission in December 2025. The filing responds to a June 25 Assigned Commissioner’s Ruling requiring gas utilities to update their maps and conduct additional outreach to California tribes that do not have a federally recognized land base. SoCalGas said it contacted affected tribes in early July and offered to add their locations to the maps upon request, receiving responses from two tribes with which it is now working.

► Details
At this stage the maps remain planning tools rather than project-selection documents. The parallel SDG&E filing (AL 3549-G) reports the same compliance step with no tribal requests received as of August 31.

The map updates feed the next phase of the SB 1221 neighborhood decarbonization program, where an Energy Division staff proposal would expand the priority zones from 151 to 304 full census tracts plus nine partial tribal tracts across 26 counties — see the SB 1221 Phase 2 ruling in Proposed Decisions & Rulings.
AL 3549-G · Filed Sep 2026 · Advice Letter · SB 1221 Map Update

SDG&E Completes SB 1221 Map Updates — No Tribal Location Requests Received as of August 31

SDG&E told the CPUC it has completed required updates to its SB 1221 maps, incorporating the Priority Neighborhood Decarbonization Zones designated in December 2025. Like SoCalGas, the filing responds to the June 25 Assigned Commissioner’s Ruling directing gas utilities to update their maps and conduct additional outreach to California tribes without a federally recognized land base. SDG&E said it contacted affected tribes in early July and offered to add their locations upon request, but had received no such requests as of August 31.

► Details
The maps remain planning tools at this stage rather than project-selection documents. SDG&E’s filing is the companion to SoCalGas AL 6687-G, which reported responses from two tribes.
AL 5249-G / 5253-G / 5255-G · Filed Sep 2026 · Advice Letters · Gas System Reliability

PG&E Backbone Capacity Fell Below the 2,538 MMcf/d Standard on Three September Dates — 384 MMcf/d Short by September 15

PG&E reported that available backbone gas transmission capacity fell below the CPUC’s average-day standard for a 1-in-10 cold and dry year, which requires 2,538 MMcf/d. In AL 5249-G it reported 2,530 MMcf/d for September 1, an 8-MMcf/d shortfall tied to maintenance at Burney, Topock and Kettleman stations and unplanned maintenance at Hinkley. AL 5253-G reported 2,484 MMcf/d on September 8, 55 MMcf/d below the standard. AL 5255-G reported 2,154 MMcf/d on September 15 — 384 MMcf/d, or about 15%, below the standard.

► Details
The September 8 reduction coincided with maintenance at Shingletown PLS and at Gerber, Topock and Kettleman stations; Shingletown work was scheduled through September 30, while the other work was scheduled to end between September 10 and September 20. By September 15 work continued at Shingletown, Topock and Kettleman and began at Delevan Station and on the L300A and L300B pipelines. The entire 330 MMcf/d decline from September 8 occurred on the Redwood Path, where capacity fell from 1,860 to 1,530 MMcf/d; Baja remained at 600 MMcf/d and scheduled California production at 24 MMcf/d.

The filings document an increasingly large maintenance-related reduction in PG&E’s ability to receive gas, but they do not establish that customer demand exceeded available supply or that service was interrupted. The CPUC standard is a minimum system-design requirement based on an average day in a 1-in-10 cold and dry year, so crossing it requires notice even when actual September demand is considerably lower. The September 15 filing is the most significant of the three — available capacity roughly 15% below the standard, against less than 1% on September 1 and about 2% on September 8 — and concurrent maintenance on both paths leaves less flexibility if another facility becomes unavailable before the scheduled work ends.
Earlier Period
Aug 16 – Aug 31, 2026
1 filing
AL 6682-G · Submitted Aug 2026 · Advice Letter · Rates Effective Sep 1

SoCalGas — −$66.3M (−1.3%) Systemwide Transportation Revenue Update; Most Classes Decrease, BTS Up 1.1%

SoCalGas submitted Advice Letter 6682-G reducing systemwide gas transportation revenue by $66.3 million (−1.3%) effective September 1: completed 12-month recoveries for the DIMP balancing account, Catastrophic Event and COVID-19 memo accounts roll off, replaced by a 12-month $59.4 million Storage Integrity Management Program recovery plus $7.8 million allocated from SDG&E’s transmission-integrity account. Residential and core C&I rates fall 1.5%; backbone transportation rises 1.1%. Protests are due September 6.

► Details
The decrease reflects turnover in temporary balancing-account collections, not a decline in underlying service costs. Class impacts: noncore commercial-industrial −2.4%, electric generation −3.5%, wholesale −4.7%. The consolidated update reduces core revenue by $55.1 million and noncore by $19 million, partly offset by the $7.8 million backbone increase — backbone rates rise because SDG&E’s transmission-integrity costs are allocated entirely to that service. Both integrity-program figures include franchise fees and uncollectibles.
No matches for selected IOU.

Proposed Decisions & Rulings

Current Period
Sep 16 – Sep 30, 2026
6 items
A.23-06-008 · PD issued Sep 18, 2026 · Proposed Decision · WMPMA / FRMMA · Earliest vote Nov 19

PG&E Wildfire Mitigation Cost Recovery PD — $1.768B of $2.246B Authorized; $477M (21%) Disallowed as Not Incremental or Reasonable

ALJ Elaine Lau’s proposed decision would authorize PG&E to recover approximately $1,768.4 million of 2020–2022 costs recorded in the Wildfire Mitigation Plan Memorandum Account and Fire Risk Mitigation Memorandum Account. PG&E recorded about $2.495 billion over the three years — $969 million in expenses and $1.527 billion in capital — then removed $250 million in accounting adjustments to request $2.246 billion. The PD finds roughly $477 million of the recorded costs not incremental or not reasonable, a 21% reduction to the request. Earliest Commission vote: November 19, 2026.

► Details
Of the recorded total, the WMPMA holds $864 million in expenses and $1.480 billion in capital; the FRMMA holds $105 million in expenses and $47 million in capital. The accounting adjustments PG&E removed before filing were $246.296 million of expense and $3.402 million of capital, and include $233.6 million in revenue requirement removed to comply with the $1.823 billion disallowance ordered in the 2020 Wildfire OII decision (D.20-05-019).

Intervenor positions were far apart. TURN recommended disallowing $1.375 billion, about 55% of recorded costs, arguing PG&E failed to carry its burden on incrementality and reasonableness; counting the D.20-05-019 disallowance, TURN would have capped recovery at $870.5 million, or 39% of the request. Cal Advocates recommended disallowing $613 million of WMPMA capital and $280 million of WMPMA expenses, plus $5 million of FRMMA capital and $22 million of FRMMA expenses. The Energy Producers and Users Coalition and Indicated Shippers argued that spending pursuant to an approved wildfire mitigation plan does not by itself establish that the spending was prudent or affordable.

The PD adopts neither extreme. Its recurring test is whether a cost was genuinely incremental to the 2020 General Rate Case authorization and separately whether it was reasonably incurred — a cost can clear the first and fail the second. Overhead Patrols illustrate the point: the full $6.072 million recorded in MAT BFA is disallowed as unreasonable even though the PD finds the costs incremental, because PG&E performed 4,023,363 base units against 4,476,868 authorized in the GRC. The Overhead Electric Distribution Asset Inspections category recorded $207.332 million in total, of which TURN sought $184.092 million in disallowances.

PG&E has already been collecting against this request in interim rates: D.24-03-006 authorized 75% of the $688 million revenue requirement, or $516 million, and $428.9 million for Track One costs. The proceeding also covers electric modernization and gas safety work performed primarily in 2022, which this PD does not resolve.
R.26-09-009 · Opened Sep 17, 2026 · Rulemaking · Regional Markets / AB 825

CPUC Opens the AB 825 Regional-Market Rulemaking — Decision Targeted for Q3 2027, Markets No Earlier Than January 2028

The Commission opened R.26-09-009 on September 17 to implement Assembly Bill 825 and determine whether PG&E, SCE and SDG&E may participate in electricity markets governed by an independent regional organization. The statute permits CAISO to operate those markets no earlier than January 1, 2028, subject to statutory conditions, and utility participation requires a CPUC decision finding those requirements satisfied. All three utilities are respondents. The preliminary schedule calls for a decision in the third quarter of 2027.

► Details
The proceeding will examine protections for state authority over procurement, resource adequacy, environmental and reliability policies and utility oversight, along with independent market analysis and governance transparency. A threshold question is whether the Commission’s determination may rely on draft governance documents and tariffs or must await final CAISO resolutions and FERC-approved tariff changes; the rulemaking also asks whether an interim process is needed if CAISO’s transition advances before the Commission completes its review.

Other issues include procedures for directing utilities to withdraw, CAISO’s ability to provide separate market services after withdrawal, and authorization of additional regional-organization products including a potential resource adequacy program. The CPUC will coordinate with the California Energy Commission to prevent the transition from expanding which transactions qualify for RPS content categories, measured against a December 31, 2025 baseline.

The order does not resolve whether the Q3 2027 decision will itself authorize participation or instead establish the process for a later determination. Requiring final governance documents and FERC-approved tariffs would compress the interval before the earliest permitted January 2028 launch. The withdrawal questions bear directly on how readily the Commission can exercise retained authority, since utilities are separately required by statute to participate in CAISO.
D.26-09-047 · Adopted Sep 17, 2026 · Decision · PCIA / Banked RECs

PCIA Banked RECs — Pre-2019 Credits Affirmed at Zero; CalCCA’s Departed-Customer Claim Rejected as Untimely

A decision affirms zero-dollar valuation of renewable energy credits generated before January 1, 2019 and banked for later use in PG&E, SCE and SDG&E’s Power Charge Indifference Adjustment calculations. It rejects additional compensation for customers who helped fund those credits but left utility generation service before the credits were used for renewable compliance. The Commission found the credits’ costs and benefits fully allocated under the 2011 methodology adopted in D.11-12-018, which recognized renewable resources’ market value in the year of generation.

► Details
D.19-10-001 shifted REC valuation to the time credits are sold or used, but only for credits generated beginning in 2019. Because customer indifference was already satisfied for the older credits, the decision concludes that another payment would violate cost-shifting prohibitions.

CalCCA sought vintage-specific credits at the current RPS market price benchmark, or allocation of the credits to departed customers’ providers; Cal Advocates and direct-access representatives also supported non-zero valuation. The decision adopts the utilities’ position, rejects four staff alternatives and finds CalCCA’s challenges to the earlier decisions untimely. The final revision limits its separate laches finding to the failure to challenge the 2019 decision.

The decision resolves differing treatment across utilities: PG&E’s 2023–2025 ERRA forecast cases used RPS benchmark valuation, while SCE’s disputed cases used zero-dollar valuation. Uniform zero-dollar treatment applies through the October updates in the utilities’ 2027 ERRA forecast proceedings, affecting 2026 true-ups and 2027 forecast rates without otherwise reopening earlier outcomes. CalCCA executive director Beth Vaughan called the outcome “deeply disappointing,” saying the association had urged the Commission for six years to give CCA customers their share of the value of banked credits they helped pay for.

The reasoning treats the original allocation as complete even where the customers funding a resource and those benefiting from its eventual use differ, which forecloses a further PCIA credit without requiring the Commission to determine the banked credits’ present compliance value.
D.26-09-072 · Adopted Sep 17, 2026 · Decision · Tribal Land Transfer

Tribal Land Transfer Policy Extended to Surplus Utility Property; 60/30/15/90-Day Negotiation Clock Adopted, R.22-02-002 Closed

A decision expands the CPUC’s Tribal Land Transfer Policy to surplus utility property, giving tribes an opportunity to negotiate for ancestral lands before utilities seek other buyers. It covers property removed from rate base because it is no longer necessary or useful for utility service, but exempts land removed to benefit utility operations, such as mitigation for capital projects. Transactions outside Public Utilities Code Section 851 require no new CPUC approval but must comply with the policy. Telecommunications providers remain excluded.

► Details
For each covered transaction a utility must request the Office of the Tribal Advisor’s list of relevant tribes. Tribes receive 60 days to express interest, with a second notice and another 30 days for nonrespondents. A utility must establish a virtual data room within 15 business days after a tribe expresses interest, beginning a 90-day negotiation period; it may then seek other buyers if no agreement in principle exists and none appears reasonably imminent.

Data rooms must contain available property records and a current appraisal, with a broker’s opinion of value permitted temporarily. Confidential cultural information remains subject to legal disclosure restrictions. Electric and gas utilities must report quarterly on dispositions and tribal engagement; water utilities report annually. Competing tribal claims proceed first through discussions among tribes, then through alternative dispute resolution and, if unresolved, to a Commission decision.

The decision also revises tribal consultation responsibilities, establishes quarterly Tribal Information Forums open to all California Native American tribes, and provides for review of the consultation policy every three years. It closes R.22-02-002 while leaving taxation, jurisdiction and infrastructure delays for further engagement. The Commission acknowledged that the Tribal Advisor position is vacant and said it would coordinate with the governor’s office to fill it — a consideration given that implementation rests heavily on that office.
D.26-09-048 · Adopted Sep 17, 2026 · Decision · SGIP

SGIP Rulemaking R.20-05-012 Closed; SCE Medical-Baseline Waiver Preserves $1.7M in Reserved Incentives

A decision closes the Self-Generation Incentive Program rulemaking while implementation and wind-down of the Residential Solar and Storage Equity program continue through 2028; funding allocation ended in June 2026. The decision also waives demand-response enrollment requirements for certain SCE Medical Baseline Exemption customers whose SGIP projects faced expiration because they receive generation service from another provider and could not satisfy the requirement — protecting approximately $1.7 million in reserved incentives. No party opposed the waiver.

► Details
Medical Baseline Exemption customers must preserve stored energy for medical equipment and are excluded from qualifying demand-response programs, which is why the enrollment condition could not be met. The waiver removes that barrier while preserving the customers’ generation-provider choice and MB-E schedule.

The California Solar & Storage Association opposed closing the proceeding, citing payment delays, project deadlines and the absence of the cost-attestation process from the SGIP Handbook. It warned that administrators could reject baseline-supported incentive claims without an open proceeding to resolve disputes, and sought corrective action regarding LADWP’s administration. The decision finds that earlier rulings addressed baseline and payment issues and that existing program mechanisms can handle remaining concerns.

The proceeding therefore closes with program implementation still underway, and the attestation process is not codified in the Handbook; the decision relies instead on existing rules, working groups and staff coordination to address future disputes.
EE Portfolio PD · Issued Sep 2026 · Proposed Decision · Energy Efficiency

PD Would Deny SDG&E’s Exit From Regional Energy-Efficiency Administration — Claimed $300M Saving Reduced to About $14M

A proposed decision would deny SDG&E’s request to stop administering regional energy-efficiency programs from 2027 through 2032, finding the request premature and unsupported by the record. SDG&E estimated that ending the portfolio would avoid $300 million in customer collections over six years, or $1.36 per month for an average residential gas and electric customer. The PD finds that calculation omits SDG&E’s own forecast of at least $286 million in foregone Total System Benefits, leaving roughly $14 million in net savings before longer-term energy, grid and equity benefits. Earliest CPUC vote: October 8.

► Details
Under the PD, SDG&E would remain responsible for its regional portfolio and codes-and-standards programs but could eliminate underperforming programs and rebalance spending. Public Purpose Program charges, which fund energy efficiency and other programs, represent about 1.4% of SDG&E bills.

The PD rejects the argument that regional efficiency has become structurally uneconomic. SDG&E’s resource-acquisition segment achieved a 1.19 Total Resource Cost ratio in 2025, or 1.05 excluding statewide programs; six of seven regional programs had ratios at or near 1.0 in 2024, while the Federal Customer Services Program recorded a 0.03 ratio. Reforming or eliminating weak programs could improve performance without ending the portfolio.

The CPUC has legal authority to select administrators other than utilities, but the PD finds SDG&E did not show that its efficiency targets were infeasible, uneconomic or harmful to public health, nor that the San Diego Regional Energy Network could replace its portfolio — SDREN was designed to supplement SDG&E’s programs, and approximately 8% of SDG&E’s electric customers live outside its coverage. The PD also rejects an SDG&E–Cal Advocates settlement that would have ended SDG&E’s administration of regional programs and codes-and-standards activities.

SDG&E prevailed on the legal question that utilities need not administer regional programs indefinitely, but the improving cost-effectiveness results undercut the factual case for withdrawal. The PD leaves a path for a future exit conditioned on a willing replacement, an orderly transition and a plan to preserve customer and grid benefits.
Prior Period
Sep 1 – Sep 15, 2026
16 items
GRC Plan OIR · Opened Sep 3, 2026 · New Rulemaking · Rate Case Framework

CPUC Opens a Rulemaking to Overhaul the General Rate Case Plan — First Comprehensive Revision Since 2007

A new rulemaking would rewrite the General Rate Case Plan governing California energy utilities. It would update filing requirements not comprehensively revised since 2007, standardize utility evidence and workpapers, implement recent legislation, and revive unresolved proposals from the CPUC’s 2020–2021 GRC and RAMP workshops. The OIR follows the Commission’s goal of reducing electric-service costs by bringing more spending and rate impacts into the GRC for consolidated review, and asks whether thresholds should be set for major cost-recovery or infrastructure requests filed outside a GRC.

► Details
The OIR asks whether utilities should provide more standardized units, unit costs and other metrics for capital, O&M and indirect costs; formal requirements for electronic workpapers with functioning cells and searchable PDFs; consistent bill-impact calculations; more standardized Results of Operations models and depreciation studies; better support for post-test-year forecasts; and information on distributed-energy load growth, locations and costs.

The rulemaking would use the GRC process to show whether utility spending actually matches what ratepayers were asked to fund, what major capital investments will cost over time, and how wildfire spending is reflected in rates — implementing statutory requirements for comparing actual costs and returns with prior forecasts, showing multi-year rate impacts of capital projects, and tying Wildfire Mitigation Plans more directly to GRC revenue requirements. For wildfire costs recorded outside base rates, it asks what utilities should have to prove before recovery, including whether costs were reasonable, incremental and foreseeable.

Attachment A preserves the four-year cadence: RAMP begins three years before the test year; the Phase 1 GRC is filed May 15 two years before the test year; hearings follow that February and March; a final decision is targeted for December 1 before rates take effect January 1. Attachment B brings the 2020–2021 workshop disputes over standardized filings, rebuttable presumptions, attrition ratemaking and Results of Operations modeling back into consideration.
R.22-12-011 · PD + APD issued Sep 2026 · Comments Sep 24 · Earliest Vote Oct 8

Competing Biomethane PDs — Houck Would Hold RGS Above-Market Costs With Core Customers; Reynolds’ Alternate Charges Noncore Immediately

Competing proposed decisions in the biomethane cost-allocation rulemaking adopt the same method for calculating Renewable Gas Standard above-market costs but split on who pays them first. Commissioner Houck’s PD allocates costs to all core customers, including those served by Core Transport Agents, while deferring charges for noncore customers. President Reynolds’ alternate PD charges all core and noncore customers immediately. Approximately 1,020 noncore customers consume about 60% of utility-delivered gas, so an equal-cents-per-therm allocation could shift most above-market costs to industrial facilities and electric generators — even though the program’s eventual costs remain unknown.

► Details
Both proposals define above-market costs as all authorized program costs exceeding the monthly average citygate price of natural gas, less avoided greenhouse-gas compliance costs and other quantifiable benefits. Utilities would recover the resulting amount through transportation rates on an equal-cents-per-therm basis. CARE discounts are preserved; no other immediate exemptions are created. Both PDs require workshops on possible exemptions for emissions-intensive, trade-exposed industries, followed by a joint utility application within 18 months of the first workshop.

Both also carry apparent drafting errors that parties can raise before a vote. Reynolds’ APD orders immediate noncore allocation while directing the later application to ask whether it should be implemented. Houck’s PD substitutes “core” for “non-core” in its discussion and in one conclusion of law.
SoCalGas TIMP · PD issued Sep 2026 · Comments Sep 22 · Earliest Vote Oct 8

SoCalGas TIMP PD — $81.3M of a $173.8M Request Authorized; $92.5M Disallowed Over an Unjustified Accelerated Schedule

A proposed decision would authorize SoCalGas to recover $81.3048 million of its $173.8 million request for Transmission Integrity Management Program costs incurred 2019–2023, disallowing $92.4952 million. The PD concludes that expanded pipeline-safety requirements justified some additional work but that SoCalGas failed to justify its accelerated schedule — spreading the work across the longer federal compliance period and forecasting it in a GRC would have allowed greater scrutiny and reduced rate shock. On that basis it disallows $54.2032 million, 40% of the amount remaining after specific adjustments.

► Details
The PD separately disallows $34.328 million in straight-time labor, $3.271 million in related leave costs and $693,000 associated with an inadequately documented vendor. It states that $40.72 million in Line 235 costs is recoverable subject to refund pending a separate advice letter. The approved balance would be allocated under the 2024 Cost Allocation Proceeding decision (D.24-07-009) and recovered over 12 months.

The PD treats the timing of mandatory safety work as a question of prudence: because federal rules gave SoCalGas more time to complete some of the work, the utility had to justify both accelerating it and recovering the costs outside the GRC. Even required work may be found unreasonable if the utility cannot support its timing, cost or documentation.

Three internal problems are available for parties to raise. First, the PD references the $173.8 million request when describing the 40% reduction, although the resulting $54.2032 million is 40% of the $135.508 million remaining after the specific disallowances. Second, it does not explain whether the full $40.72 million authorized for Line 235 survives that aggregate reduction. Third, the Line 235 refund condition appears in the findings of fact and conclusions of law but not in an ordering paragraph, leaving the operative order silent on the condition.
SoCalGas CIS · PD issued Sep 2026 · Comments Sep 23 · Earliest Vote Oct 8

SoCalGas Customer Information System PD — $24.9M in Additional O&M Denied; SBUA Settlement Rejected

A proposed decision would deny SoCalGas’s request for up to $24.9 million in additional O&M funding for its Customer Information System Replacement Program. The CPUC authorized $46.9 million in the 2024 GRC and allowed the utility to seek more if projected costs exceeded that amount; SoCalGas now forecasts total O&M of roughly $71 million. The PD finds the utility has not shown the existing authorization will be insufficient — it spent $8.463 million in 2024 against a $16.87 million forecast, and $5.821 million through September 2025 against an $11.183 million full-year projection — and provided no finalized contracts supporting the higher forecast.

► Details
The PD concludes that denial will not delay the system’s planned third-quarter 2026 launch or its stabilization through 2027. It rejects a settlement between SoCalGas and Small Business Utility Advocates that would have reduced the additional funding to $21 million, established a two-way balancing account and provided up to $150,000 for small-business outreach — the settlement did not address contrary evidence from Cal Advocates and omitted the required comparison exhibit showing its ratepayer effects.

The PD separately grants Cal Advocates’ late request to admit a SoCalGas data response into evidence but admonishes parties against relying on new exhibits in reply briefs. Any further funding request would be considered in SoCalGas’s next GRC based on actual spending.

The disposition turns on burden: SoCalGas was permitted to seek additional funding, but still had to prove the original authorization would be insufficient. Recorded spending stayed below earlier projections and no binding commitments supported the anticipated increase. The rejection of the settlement also establishes that negotiating a smaller request does not by itself show the remaining amount is reasonable.
Direct Access PD · PD issued Sep 2026 · Comments Sep 24 · Earliest Vote Oct 8

Direct Access Cap — Reynolds PD Would Deny the Petition to Reopen, Resting on Timeliness Rather Than the Merits

President Reynolds issued a proposed decision rejecting an effort by retail-energy suppliers and large customers to eliminate California’s cap on Direct Access. The petitioners — the Alliance for Retail Energy Markets, the California Coalition of Large Energy Users, the Direct Access Customer Coalition, the Regents of the University of California, Shell Energy North America and the Western Power Trading Forum — asked the CPUC to reverse its 2021 recommendation against expanding the program. The PD does not decide whether changed conditions justify expansion: it finds the petition lacks declarations or record citations for several factual claims and was filed nearly five years after the 2021 decision.

► Details
The petitioners argued that the conditions underlying the 2021 recommendation have changed, citing stronger resource-adequacy and renewable-procurement performance by electric service providers, a shift from RA scarcity in 2020 to a current surplus, and rapid load growth from data centers and electric vehicles. They also argued that the CPUC’s 2026 IRP decision (D.26-02-057) requires ESPs to procure a share of 6 GW of new renewable capacity for forecast load growth while the Direct Access cap prevents them from serving much of that new load.

The PD concludes that the effects of the cap and of load-based procurement obligations were known or reasonably foreseeable within one year of the 2021 decision, and that reversing it and resolving previously undecided cost-shift questions would require a fuller evidentiary record.

Note: four of the petitioners separately filed a same-day application for rehearing of the IRP decision challenging its allocation of procurement obligations to ESPs. This PD addresses only the petition to modify the 2021 Direct Access decision and does not resolve that application.

If adopted, the PD would close the old proceeding, leaving the underlying issue intact — ESPs may receive procurement obligations tied to statewide load growth without being allowed to compete for much of that load. Further expansion would then likely require new legislation or a new CPUC proceeding.
AB 2109 · ALJ Ruling Sep 2026 · Joint Proposal Due +45 Days · Heat Recovery

ALJ Orders a Joint IOU Proposal Within 45 Days to Implement AB 2109’s Surcharge Exemption for Industrial Heat Recovery

A new ALJ ruling directs PG&E, SCE and SDG&E to submit a joint proposal within 45 days for implementing Assembly Bill 2109’s exemption from certain non-bypassable charges for electricity savings produced by industrial process heat-recovery systems. The proposal must identify which charges should and should not be exempted, establish technology and compliance requirements, and recommend a participation cap and its allocation among the utilities.

► Details
The joint proposal must also estimate rate and bill impacts on non-participating customers by customer class and consider limits or other measures to reduce cost shifts. Parties may comment on the proposal, on additional customer protections and on alternative approaches.

AB 2109 created the surcharge exemption but left the CPUC to define its financial and administrative reach. How the Commission defines the participation cap, the eligible charges and the cost-shift protections will determine how much industrial customers can save by reducing grid consumption through recovered heat. The joint proposal will also produce the first quantified estimate of the resulting effects on other customer classes.
IRP / TPP 2027-28 · Ruling Sep 2026 · Comments Sep 28 · Replies Oct 12

2027-2028 TPP Portfolio Ruling — Interim GHG Targets Raised to 38/30 MMT, Offshore Wind Dropped From the Base Case, 4,400 MW West LA Storage in Play

The CPUC is seeking comment on a proposed resource portfolio for CAISO’s 2027-2028 Transmission Planning Process that would raise California’s interim greenhouse-gas targets and stop forcing offshore wind into the base case. Staff recommends 38 MMT by 2030 and 30 MMT by 2035 instead of 30 and 25, while still reaching 8 MMT by 2045. Staff says the lower interim targets would require solar additions of about 8 GW per year through 2030 and cost at least $1 billion more by 2030 and $2 billion more by 2035 — even though the added resources are not needed to meet the CPUC’s reliability standard.

► Details
The recommended base case would no longer force offshore wind into the portfolio, reversing the approach used in the previous three TPP cycles. Staff cites federal policy and permitting uncertainty, terminated California leases and reduced offshore-wind interest in recent LSE plans. RESOLVE economically selects no offshore wind under the proposed assumptions, relying instead on solar, battery storage and increasing amounts of conventional and enhanced geothermal. The base case retains about half of the previously identified long-lead-time procurement need, excluding offshore wind.

For a sensitivity study, staff recommends limiting additional out-of-state resources to those deliverable over transmission already operating or under contract; RESOLVE then selects 54.8 GW of new solar and 20.1 GW of new eight-hour storage by 2035.

The ruling separately asks whether storage should be procured in the West Los Angeles Basin after CAISO cancelled the Serrano-Del Amo-Mesa 500-kV project. CAISO says at least 4,400 MW / 12,428 MWh should come online across specified West LA substations by 2032, and has recommended a CPUC procurement order for 2,900 MW / 2,336 MWh by Q2 2032. The ruling notes that amount would meet the identified need only if projects already in the interconnection queue are completed, and that the batteries would operate as market resources without special compensation for performing a transmission function. A 2022 decision (D.22-02-004) authorized similar storage procurement for the Kern-Lamont line and Mesa system, but PG&E found no viable offers able to meet the required online date. The ruling also raises whether SCE, as Local Central Procurement Entity for its area, could handle the West LA procurement.
SB 1221 Phase 2 · Ruling Sep 2026 · Comments Sep 18 · Replies Oct 2

SB 1221 Phase 2 Staff Proposal — 67% Owner Consent, Up to 25% of Net Savings to Shareholders, Priority Zones Expanded 151 → 304 Tracts

The CPUC is seeking comment on an Energy Division proposal for the next phase of Senate Bill 1221’s neighborhood decarbonization program — when pilot projects are considered “established,” how utilities could earn shareholder incentives, and when gas service can be retired within approved project areas. Staff proposes treating a project as established when the CPUC approves it, regardless of when property-owner consent is obtained. Utilities could earn up to 25% of verified net savings from qualifying projects completed in a given year. Projects would require binding consent from owners of at least 67% of properties before implementation.

► Details
Performance would be based on pipeline mileage retired, customer conversions, the share of converted customers in designated communities, and project performance against budget. Staff seeks comment on three alternative customer-conversion metrics.

The CPUC would determine whether proposed zero-emission alternatives provide affordable, adequate, efficient and just-and-reasonable substitute service, including a no-cost option. After completion the utility would file a Tier 3 advice letter; approval would relieve it of the obligation to serve the project area, after which remaining gas service could be ended even for owners who declined conversion. Staff also asks whether substitute service should cover only common gas end uses or every existing onsite gas use.

The proposal would expand the current 151 priority neighborhood decarbonization zones to 304 full census tracts plus nine partial tribal tracts across 26 counties. SB 1221 limits each utility’s pilots to no more than 1% of its customers. Recurring project reporting and annual updates to SB 1221 gas-system maps would begin in 2027.

Once a project receives CPUC approval and reaches the 67% consent threshold, the program can move toward full retirement of gas service within that area. The proposed incentive would also give utilities a financial reason to pursue locations where electrification costs less than replacing gas infrastructure; allowing shareholders to retain up to 25% of verified net savings could make avoided pipeline replacement more attractive. The 1% customer cap keeps the program limited in scale for now.
Draft Res. E-5472 · Issued Sep 2026 · Earliest Vote Oct 8 · Meter Socket Adapters

Draft Res. E-5472 — Meter Socket Adapter Filings Approved; Future Truck-Roll Fee Increases Pushed to Tier 3 Review

Draft Resolution E-5472 approves SCE’s meter socket adapter filing and SDG&E’s equivalent filing with modifications, while imposing new fee-transparency requirements on all three large electric IOUs. SDG&E must disclose its MSA “truck roll” fee on its public webpage. PG&E, SCE and SDG&E would have 60 days to revise their tariffs through Tier 2 advice letters to state the current fee and to require any future increase to proceed through a Tier 3 advice letter supported by calculations, cost data and methodology. PG&E currently charges $275 and SCE $279.22; SDG&E has not publicly listed its amount.

► Details
The draft resolution reiterates that the evaluation framework is technology-agnostic and extends beyond meter socket adapters to other customer-owned technologies that interface with utility equipment. MSAs can enable EV charging, battery storage and other electrification equipment without requiring panel replacement or service-line upsizing.

By requiring Tier 3 review and detailed cost support for future truck-roll fee changes, E-5472 would make those charges more transparent and less subject to informal utility adjustment.
Res. E-5475 · Adopted Sep 17, 2026 · Integrated Resource Planning · Ava Community Energy

Res. E-5475 Adopted — Ava’s New Sonrisa Project Counts as Incremental, Not Baseline; Baseline-Removal Waiver Expanded to Tier 2

The Commission adopted Resolution E-5475 on September 17. The resolution confirms that Ava Community Energy’s newly contracted Sonrisa project is distinct from a project of the same name included in the resource baseline established under the 2021 Mid-Term Reliability Decision (D.21-06-035). The new project is a 200 MW solar facility paired with 184 MW / 736 MWh of storage. The earlier project never advanced because of an infeasible interconnection configuration. On Ava’s unprotested showing, the draft resolution finds the new project differs in size, commercial operation date, design, technology, land footprint, interconnection configuration and permitting status — so it counts as incremental procurement rather than an existing baseline resource.

► Details
Ava — formerly East Bay Community Energy — requested the determination in Advice Letter 70-E, filed June 1. The resolution also allows load-serving entities to seek removal of baseline projects that were not developed, are no longer under contract and are no longer advancing. Such requests would be submitted through a Tier 2 advice letter, expanding a waiver process that D.23-02-040 previously limited to cases in which one LSE terminated a contract and another contracted with the same resource. Ava’s advice letter was not protested, and the resolution identifies no associated costs. It does not quantify how much of Ava’s procurement obligation the project will satisfy.
GO 95 / LRFD · PD issued Sep 2026 · Held to Oct 8 · Effective Jul 1, 2027

GO 95 PD Replaces Working Stress Design With Load and Resistance Factor Design for Overhead Facilities

A proposed decision replaces the Working Stress Design methodology in General Order 95 with Load and Resistance Factor Design for overhead electric and communications facilities. The initial load and strength factors would remain algebraically equivalent to existing requirements, but the proposal would allow factored loads to be used in certain structural calculations where doing so produces larger load effects. The revisions would take effect July 1, 2027. The Commission held the item at its September 17 meeting; it is now scheduled for consideration on October 8.

► Details
The proposal rejects utility-backed language expressly allowing older facilities to demonstrate compliance under the former methodology. Existing facilities would not automatically require redesign, but calculations required by GO 95 would use Load and Resistance Factor Design — preserving the Commission’s ability to apply future load-and-strength-factor changes to existing facilities.

Commission staff would also hold a workshop within 24 months to consider further GO 95 revisions. A statistical safety study is deferred because the initial change maintains algebraic equivalence.
Res. E-5476 · Draft Sep 2026 · Draft Resolution · Avoided Cost Calculator

Draft Res. E-5476 Adopts the 2026 Avoided Cost Calculator — Total Avoided Costs Rise in Every Hour, Driven by GHG Value

Draft Resolution E-5476 would adopt the 2026 Avoided Cost Calculator for evaluating demand-side distributed energy resources, implementing changes approved September 3 in D.26-09-007: a single electric-sector greenhouse-gas value for electric and gas resources, removal of GHG rebalancing, simplified treatment of hybrid solar-plus-storage resources and use of loss-of-load hours for allocating capacity value. The 2026 calculator produces higher total avoided costs in every hour than the 2024 version. Earliest CPUC vote: October 8.

► Details
The draft resolution also uses energy prices rather than temperature to identify high-value days, distinguishes weekday and weekend reliability risk, uses the Integrated Energy Policy Report forecast in peak capacity allocation factor calculations for transmission avoided costs, and applies the “Discounted Total Investment Method” across electric utilities.

Individual components move differently even as the total rises. Increased renewable penetration lowers avoided energy value; generation-capacity value falls in the near term, rises in later years and is distributed across more overnight hours to reflect storage dispatch. The largest increase comes from the GHG component, which rises substantially because the model incorporates expiring federal renewable-energy tax credits and new tariffs on imported solar and storage components.

The net effect should make DER programs appear more cost-effective where higher GHG benefits outweigh lower energy and near-term capacity values, with measures producing sustained emissions reductions benefiting most and resources relying heavily on near-term capacity value benefiting least. Federal policy enters the results primarily through the GHG component: reduced federal support and tariffs increase the modeled cost of utility-scale solar and storage used to reduce emissions, which increases the calculated value of demand-side resources that avoid those costs.
Res. E-5483 · Draft Sep 2026 · Draft Resolution · Diablo Canyon True-Up

Draft Res. E-5483 — PG&E’s $1.224B Diablo Canyon True-Up Clears the 115% Threshold; TURN’s Category-by-Category Test Denied

Draft Resolution E-5483 would authorize PG&E’s true-up of Diablo Canyon extended-operations costs and market revenues for September 1, 2023 through December 31, 2025. PG&E recorded approximately $1.224 billion in costs, below 115% of the applicable forecast under both the original and updated Resource Adequacy Market Price Benchmark calculations, so the draft finds that Public Utilities Code Section 712.8 requires no further reasonableness review. It would also approve allocation of Diablo Canyon’s greenhouse-gas-free attributes to 31 eligible load-serving entities for 2025. Costs are recovered from PG&E, SCE and SDG&E customers through non-bypassable charges already in rates; the resolution would authorize no additional rate increase. Earliest CPUC vote: October 8.

► Details
The draft resolution would deny TURN’s protest seeking to apply the 115% threshold separately to each cost category. TURN argued the aggregate calculation obscures approximately 10% overruns in operations and maintenance and in plant equipment and improvement costs, while a $132.2 million reduction in Resource Adequacy substitution capacity costs supplies much of the offset. The draft concludes that the statute calls for comparing total actual and forecast costs, that the same approach is used for other balancing accounts, and that neither disputed category exceeded 115% of its own forecast.

TURN’s proposal would not change the outcome for this record period, since PG&E remains below the statutory trigger under either calculation. The forward-looking effect is the aggregate reading itself: savings or methodology changes in one category can offset overruns elsewhere, including in categories more directly within PG&E’s control. TURN’s examples show an individual category exceeding its forecast by 30% to 65% without triggering review, but the draft reads Section 712.8(h)(1) as providing no category-specific test.

The draft appears internally inconsistent about the updated forecast: its discussion identifies an updated Market Price Benchmark forecast of $1.193 billion, while Finding 4 associates the $1.325 billion original forecast with both calculations. The stated conclusion remains mathematically correct under either figure.
2027 Wildfire Fund NBC · Ruling Sep 2026 · ALJ Ruling · Non-Bypassable Charge

2027 Wildfire Fund Charge Proposed at $5.42/MWh — Down 8.3%, but a True-Up Rather Than a Revenue-Requirement Cut

A ruling seeks comment on the Department of Water Resources’ proposal to set the 2027 Wildfire Fund Non-Bypassable Charge at $5.42/MWh ($0.00542/kWh), effective January 1, 2027 on non-exempt load in the PG&E, SCE and SDG&E service territories. That is $0.49/MWh, or 8.3%, below the 2026 charge of $5.91/MWh. DWR’s 90-day notice projects collections of $854.6 million during 2027, $47.8 million less than the fixed $902.4 million annual revenue requirement, with the difference offsetting the cumulative overcollection projected through the end of 2026. Comments were due September 21, replies September 28.

► Details
DWR calculated the rate using actual collections through June 2026, projected collections for the remainder of the year and the utilities’ 2027 load forecasts. The forecast includes 158.7 million MWh of non-exempt load — 67.9 million MWh bundled and 90.8 million MWh of direct access, community choice aggregation and other departing load — and accounts for uncollectible amounts and the roughly 30-day lag between customer billing and remittance. An attached memo projects $849.1 million in transfers to the Wildfire Fund and $6.4 million in administrative and operating costs during 2027, with no bond debt-service expense.

The reduction does not lower the Fund’s $902.4 million annual revenue requirement; it returns the cumulative overcollection expected through 2026. At 1,000 kWh of monthly usage the charge falls from $5.91 to $5.42. The Commission has limited discretion over the annual revenue requirement: the Wildfire Rate Agreement requires it to maintain collections sufficient to meet the requirement and has the force of an irrevocable financing order. The comment process is therefore more likely to examine DWR’s load forecasts, collection assumptions and calculation than the amount dedicated to the program.
DAC-SASH PD · Issued Sep 2026 · Proposed Decision · Low-Income Rooftop Solar

DAC-SASH PD — Accrued Interest Redirected to Administration and Outreach; GRID’s $1,000/kWh Battery Incentive Rejected

A proposed decision would modify the Disadvantaged Communities–Single-Family Solar Homes program, which has a $10 million annual budget and provides no-cost rooftop solar to income-qualified homeowners in disadvantaged communities and California Indian Country. As of December 2024 it had supported 2,886 interconnected systems totalling more than 11.5 MW with approximately $53.2 million in incentives. The PD would let PG&E, SCE and SDG&E use accrued interest in their DAC-SASH balancing accounts for utility administration and marketing, education and outreach through 2030 — $3.588 million accrued against $2.349 million in forecast remaining costs, leaving about $1.239 million. Earliest CPUC vote: October 8.

► Details
Public Purpose Program charges became the program’s sole funding source on July 1, 2026, and the program is scheduled to sunset December 31, 2030. Recovery of the accrued interest would be limited to the forecasts absent further authorization and would occur without a rate of return through annual Energy Resource Recovery Account applications. SDG&E would be prohibited from transferring more than its authorized 10.3% share of annual program funding into its balancing account.

GRID Alternatives would be required to report external funding used to complete individual projects, tracking DAC-SASH and external costs, total project cost and the external-funding percentage. GRID could use $50,000 of accrued interest to develop the reporting system and must file an implementation plan through a Tier 2 advice letter, with the new information appearing in its first semiannual report for 2027.

The PD adopts the revised Version 7 handbook, which retains the $3/W incentive and the Expected Performance Based Buydown Calculator, requires GRID to track enrollment in related assistance programs, and prohibits combined incentives from exceeding project costs. It makes qualifying meter socket adapters eligible while removing job-training, trainee-hiring and energy-efficiency-education requirements, and rejects GRID’s proposed $1,000/kWh battery incentive.

Rejecting storage and eliminating workforce requirements preserves more of the fixed budget for installations, favouring household count over resilience or employment benefits. The external-funding requirement addresses a gap in the Commission’s information: GRID’s ability to supplement DAC-SASH with outside funds helped it win the administrator role, but the CPUC has lacked data on how much external support individual projects require. GRID would not have to identify funding sources or allocate external support among cost categories.
BUILD / TECH ACR · Issued Sep 15, 2026 · Assigned Commissioner Ruling · Refrigerant GWP

Houck Ruling Extends High-GWP Heat-Pump Deadlines and Eliminates the Installation Cutoff for Other HVAC Systems

Assigned Commissioner Darcie Houck’s September 15 ruling extends several eligibility deadlines and eliminates another for heat-pump equipment using refrigerants with a global warming potential above 750 under the BUILD Program and the TECH Initiative. Variable refrigerant flow HVAC systems manufactured before January 1, 2026 and installed before January 1, 2027 remain eligible — both deadlines extended by one year to align with California Air Resources Board and U.S. EPA requirements.

► Details
For self-contained heat pump products — packaged terminal, room and rooftop systems — the ruling retains the requirement that equipment be manufactured before January 1, 2025 but extends the installation deadline from January 1, 2026 to January 1, 2028. For other heat pump HVAC systems it retains the January 1, 2025 manufacturing cutoff but eliminates the installation deadline entirely. It also extends eligibility to high-GWP heat pump water heaters and dryers installed before January 1, 2028.

The refrigerant restriction originated in a 2020 decision implementing Senate Bill 1477 and was extended through assigned commissioner rulings issued in 2022 and 2025. The new ruling separates HVAC equipment into the categories used by CARB and the EPA, and notes that federal requirements supersede the CPUC’s rules by limiting new VRF and self-contained systems to refrigerants below 700 GWP after the applicable federal deadlines.

The most consequential change is the elimination of the installation deadline for high-GWP heat pump HVAC systems outside the VRF and self-contained categories: equipment in that category manufactured before 2025 remains eligible for BUILD and TECH incentives without a separate installation cutoff. The ruling otherwise leaves the transition away from high-GWP refrigerants intact while giving manufacturers and installers more time to use qualifying equipment; heat pump water heaters and dryers receive another year because of limited market development.
Earlier Period
Aug 16 – Aug 31, 2026
14 items
R.25-10-003 · Amended Scoping Memo Aug 26, 2026 · Resource Adequacy · Track 2

RA Track 2 Scoping Memo — UCAP Implementation, 2028–2030 LCRs and the Planning Reserve Margin, Concluding June 2027

Assigned Commissioner Reynolds issued an amended scoping memo setting the scope and schedule for Track 2 of the Resource Adequacy proceeding, expected to conclude by the end of June 2027. Track 1 was resolved last month in D.26-07-008, which adopted an Unforced Capacity (UCAP) framework beginning with the 2028 RA compliance year. Track 2 focuses heavily on implementing that framework, along with setting 2028–2030 Local Capacity Requirements, the 2028 Flexible Capacity Requirements and the Planning Reserve Margin for 2028 and 2029.

► Details
A substantial portion of Track 2 concerns unresolved UCAP implementation details: how UCAP should be implemented for energy storage under the Slice-of-Day framework; the appropriate basis for RA must-offer obligations once UCAP replaces installed capacity as the qualifying-capacity methodology; development of Equivalent Forced Outage Rate during Demand values for the energy component of storage; a UCAP methodology for hybrid storage resources; treatment of foldback limitations during the fifth RA Measurement Hour; how UCAP values should interact with flexible RA; and application of the four-hour discharge requirement for storage to qualify for RA capacity.

Track 2 will also consider a method for accounting for open-loop pumped-storage hydropower that recognizes both its hydro and storage characteristics; whether energy-only resources can contribute to storage charging-sufficiency requirements following CAISO transmission-planning studies; and improved accreditation for solar, wind and other non-dispatchable resources, including a methodology intended to address over-counting of solar in summer and under-counting in winter. The Commission will revisit the RA penalty structure, specifically how penalty points should apply to charging deficiencies, and may address coordination between RA and Integrated Resource Planning.

Schedule: the 2028 LOLE and PRM study is expected in October 2026, with final LOLE studies and PRM proposals due October 13, opening comments November 12 and replies December 3. Most other Track 2 proposals are due January 15, 2027. CAISO’s local- and flexible-capacity studies arrive in spring 2027 ahead of a June decision.
A.26-06-014 / A.26-06-015 · Scoping Memo Aug 2026 · Sempra 2028 GRCs · PD Targeted Dec 2027

Sempra 2028 GRC Scoping Memo — Earnings Sharing Begins Only Beyond 200 Basis Points; SDG&E Keeps 2024–2027 Wildfire Costs Out

Commissioner Douglas issued a scoping memo for the Sempra utilities’ 2028 General Rate Cases, whose possible consolidation with other proceedings is pending. SoCalGas requests a $5.1 billion revenue requirement, up $485 million (10.5%) from 2027, raising the average non-CARE residential gas bill by $5.67/month (7.7%). SDG&E seeks a combined $3.8 billion ($2.9B electric, $900M gas), up $280 million (8.1%) — about $22.48/month (8.6%) for a typical combined customer. Both also seek additional increases for 2029 through 2031.

► Details
The CPUC will examine whether the proposed 2028 costs and recovery mechanisms are just and reasonable, along with post-test-year adjustment mechanisms, balancing and memorandum accounts, safety and risk-management proposals, workforce impacts, and consistency with California’s climate, decarbonization and future natural-gas-demand outlook.

Both utilities propose an earnings-sharing mechanism for 2029–2031: shareholders would retain all gains or losses within 200 basis points of the authorized rate of return; amounts between 201 and 250 basis points would be shared equally with ratepayers; and amounts beyond 250 basis points would flow entirely to ratepayers, with a reciprocal structure on the downside.

The scope incorporates the Commission’s affordability framework, grid-modernization guidance and requirements linking RAMP work to the GRC. SDG&E is not seeking reasonableness review or recovery in this GRC of incremental wildfire-mitigation costs incurred from 2024 through 2027, saying it will seek those costs in another venue; the CPUC will nevertheless consider what future wildfire costs may qualify as “unforeseen” or “incremental” for memorandum-account treatment under Senate Bill 254.

Schedule: intervenor testimony February 15, rebuttal March 31, proposed decision targeted December 1, 2027.
AMI Scoping Memos · Aug 2026 · Three Scoping Memos · Smart-Meter Replacement

Three AMI Scoping Memos Raise the Evidentiary Bar — SCE’s Application Called Incomplete; SoCalGas Must Explain Retiring the ~86% Still Working

The CPUC is subjecting major smart-meter replacement proposals from SDG&E, SCE and SoCalGas to parallel scrutiny, with new scoping memos focused on whether the utilities have adequately justified replacing first-generation metering systems, demonstrated customer benefits, and considered less costly alternatives. SDG&E seeks about $825 million in Smart Meter 2.0 spending through 2031; SoCalGas seeks roughly $3.76 billion for a systemwide replacement covering about six million customers. For SCE, the Commission finds the record does not adequately explain the four AMI 2.0 configurations considered or why its preferred “Value Upgrade” was optimal, calls the application incomplete, and requires supplemental testimony by September 11.

► Details
For SDG&E, the CPUC will examine whether the project is necessary and least-cost, whether meter-failure forecasts support the proposed replacement schedule, whether repair or life-extension alternatives could reduce costs, and whether lessons from the original AMI deployment have been incorporated. The scope also includes vendor warranties and performance guarantees, phased deployment, alternative financing or ownership structures, cybersecurity, and allocation of costs between gas and electric customers.

For SCE, supplemental testimony must detail the methodology used to compare its baseline, limited, value and advanced options; the costs and benefits of each; risks that projected benefits will not materialize; and detailed hardware, software and subscription costs.

For SoCalGas, the scoping memo puts the necessity of mass replacement, the reasonableness of its cost forecasts and potential stranded investment at issue, and requires supplemental testimony by October 5. SoCalGas must substantiate projections that significant meter-module battery failures will begin around 2030 and explain why systemwide replacement is warranted. One Commission question notes that 2013-vintage modules are projected to have only a 14.18% failure rate in year 20 and asks how SoCalGas would account for removing the approximately 86% projected still to be working. The proceeding will also consider how stranded costs should be allocated between shareholders and ratepayers.

SCE and SoCalGas are not facing wholesale re-litigation of their original AMI deployments, though past performance may inform the new proposals. SDG&E’s review goes further, expressly requiring a retrospective accounting of whether AMI 1.0 delivered its promised benefits.
A.26-05-002 · Scoping Memo & Ruling Aug 2026 · SAP Migration · $348M

SAP Migration Scoping Memo — $348M for Phases 1B and 2; the Memorandum Account Will Be Decided Ahead of the Rest

Commissioner Baker issued a scoping memo and ruling for review of SoCalGas/SDG&E’s proposed $348 million revenue requirement for phases 1B and 2 of their SAP Migration Program. The utilities say the work is needed because SAP will discontinue maintenance for several applications used in their enterprise platform at the end of 2027, requiring migration to supported systems before they become obsolete. Notably, the Commission will decide the request to establish a SAP Migration Memorandum Account separately and ahead of the bulk of the case.

► Details
The Commission will examine whether the program’s estimated costs, benefits and requested revenue requirement are reasonable and adequately supported, as well as the proposed memorandum and balancing accounts. Specific questions include whether a two-way balancing account or another ratemaking mechanism should be used; how over- and under-collections should be handled; whether memorandum-account costs should ultimately be transferred to the balancing account; and whether the proposed system average percent change (SAPC) and equal percentage of authorized margin (EPAM) allocation methodologies are appropriate, including whether some EPAM-allocated revenue should be recovered through fixed rather than volumetric charges.

The key ratemaking issue is how much financial risk the CPUC will allow the utilities to shift to customers while the migration is underway. The choice of balancing-account treatment will determine whether forecast errors and cost overruns remain primarily with the utilities or are trued up through rates, and the allocation methodology will determine which customers ultimately bear the approved costs. The separate, expedited decision on the memorandum account is therefore significant: if authorized, it could allow the utilities to begin recording eligible migration costs before the Commission decides how much of the broader $348 million request is reasonable and recoverable.

Schedule: intervenor testimony November 20, concurrent rebuttal December 20.
Draft Res. O-0101 · On Sep 3 Agenda · Crude Oil Pipeline · 10% Increase

Draft Res. O-0101 — Torrance Basin Pipeline Granted a 10% Increase to $0.5122/bbl, Against a Claimed 178.1% Entitlement

Draft Resolution O-0101 approves a 10% rate increase for Torrance Basin Pipeline Company’s M-131 crude oil pipeline, raising its tariff to $0.5122 per barrel for shipments from the Kinder Morgan Carson Terminal to Torrance Refining Company and the Valero Asphalt Plant. The increase would raise annual pipeline revenue — and shipper costs — by about $101,966. The draft resolution finds the increase just and reasonable and deems it effective as of December 1, 2025.

► Details
The filing shows that even after the increase, Torrance Basin’s $2.84 million cost of service would exceed expected revenue of $1.12 million by about $1.71 million. The company says those costs could support a 178.1% increase but requested only 10%. The larger shortfall compared with its previous filing is attributed to higher outside-services expenses, which rose by $215,892.
R.25-02-005 · PD issued Aug 18, 2026 · Proposed Decision · PCIA / Banked RECs

PCIA Reform — PD Would Value Pre-2019 Banked RECs at Zero, Rejecting CalCCA’s Bid for an Additional Departing-Load Credit

A proposed decision in the PCIA/ERRA reform docket would require PG&E, SCE, and SDG&E to value renewable energy credits generated before 2019 and banked for later use at $0 in the PCIA calculation, finding their value was already allocated to departing load under the prior methodology. Comments are due September 2; earliest Commission vote September 17, 2026.

► Details
ALJ Eileen Odell concludes that the newer valuation method — valuing RECs when sold or used for RPS compliance — applies only to RECs generated on or after January 1, 2019; bundled customers already credited departing load for the market value of the underlying renewable resources in the generation years under the then-effective PCIA methodology, so a further credit would itself violate the customer-indifference mandate. The PD also treats CalCCA’s claim as barred by laches: CalCCA acquiesced in the prospective-only reach of the post-2018 rules, and other stakeholders relied on the finality of the earlier decisions. If adopted, the zero-dollar treatment takes effect immediately and flows into the utilities’ October updates for 2027 ERRA forecasts, affecting 2026 true-ups and 2027 rates.
R.25-02-005 · Ruling Aug 2026 · Amended Scoping Memo · PCIA Structural Review

PCIA Reform — Second Amended Scoping Memo Opens Tracks 3A/3B/4, Putting the PCIA’s Structure Itself on the Table

Assigned Commissioner Baker’s second amended scoping memo splits Track 3 into Track 3A (refinements within the existing PCIA: RPS and Energy Price Index benchmarks, GHG-free allocation, re-vintaging rules) and Track 3B (whether alternatives such as securitization, mandatory resource allocation, cost-allocation mechanisms, or rate-stabilization funds should replace it), and defines a Track 4 on further benchmark, Slice-of-Day/ERRA, and volatility reforms. Load-serving entities must meet and confer on disputed access to utility portfolio data within 60 days, with a joint report due within 75 days.

► Details
The memo acknowledges the PCIA already satisfies the statutory indifference standard between bundled and departing customers, then asks whether the same result could be achieved through a less cumbersome design — including market mechanisms to recover and transact the value of new “legacy assets” created through ongoing procurement. Stated goals include reducing year-to-year PCIA volatility, improving benchmark accuracy, assigning costs more accurately by resource vintage, and increasing portfolio-cost transparency within confidentiality limits. The ordered meet-and-confer addresses CCA requests for more utility portfolio data, which the utilities have resisted on relevance and confidentiality grounds.
PG&E 2027 ERRA · Ruling Aug 2026 · Motion to Compel Granted · Data-Center Forecast

PG&E Must Break Out How Much of Its Data-Center Forecast Rests on Signed Agreements — Detail Due August 31

A CPUC ruling granted Cal Advocates’ motion to compel PG&E to disclose how much of the data-center load in its 2027 ERRA forecast comes from projects with signed service agreements, versus active applications, versus inquiries. The ruling rejects PG&E’s confidentiality and relevance objections, holding that the Commission may need to look beneath an aggregate forecast to test whether its assumptions are realistic — notable because PG&E itself says data centers are the main driver of its industrial-load growth.

► Details
Cal Advocates argued it needs the assumptions beneath the forecast to determine whether emerging data-center load could have an outsized effect on ratepayers; PG&E countered that the aggregate industrial forecast suffices. The ruling sides with Cal Advocates, noting its broad statutory authority to obtain confidential material and that PG&E should have used the Commission’s existing confidentiality protections rather than withholding. PG&E must provide fully responsive information by August 31 and, within two business days, the draft fall-update data-center forecast it had offered during the discovery dispute. The signed-agreement / application / inquiry breakdown lets parties measure how much projected growth is committed versus speculative before it starts setting rates.
R.25-10-003 · Ruling Aug 17, 2026 · Draft LOLE Studies · 2028 Reserve Margins

Resource Adequacy — Dueling 2028 LOLE Studies Find CAISO Long on Capacity; ED Headroom of ~6,150 MW vs. SCE’s 16.4% UCAP PRM

ALJ Chiv’s August 17 ruling attached Energy Division’s draft 2028 loss-of-load-expectation study: the projected CAISO portfolio produces no loss-of-load events under base assumptions and could absorb about 6,150 MW of added demand while holding near the one-in-ten-years standard. SCE’s independent PLEXOS study calculated a 16.4% UCAP-based September Planning Reserve Margin. A final ED study and PRM recommendation are due in October, after a September workshop.

► Details
The ED baseline carries roughly 18,300 MW more nameplate than the 2026-study baseline, led by storage and solar. Adding 6,150 MW of flat demand monthly yielded a 0.113 annual LOLE and an unadjusted 21.9% September PRM (HE 20); applying the UCAP methodology adopted in D.26-07-008 (forced-outage and ambient-temperature derates) cut results to about 20.5% (Jul–Oct) and 17% otherwise, and the system stays above standard even with imports zeroed out (0.028 LOLE). SCE used ED’s published assumptions where practicable but ran PLEXOS rather than SERVM, removing 20,935 MW of nameplate (about 19% of non-hydro resources, imports cut ~19%, DR held to 1,700 MW) to produce a 0.085 LOLE within standard. Both studies agree the 2028 portfolio holds more capacity than needed; the open question is how much can come out. ED’s pro-rata capacity-reduction scenario — the design closest to SCE’s — remains unfinished, with the nearest published staff comparator (17.2% September UCAP, flat-load calibration) just 0.8 points above SCE’s figure.
Bundled Procurement Plans · Ruling Aug 2026 · First Rewrite Since 2015 · Comments Nov 13

CPUC Reopens the IOUs’ Procurement Rulebook — Preapproval Frameworks Under §454.5 Face First Major Update in a Decade

An ALJ ruling asks parties to weigh the June 1 proposals of PG&E, SCE, and SDG&E to update their Bundled Procurement Plans — the Pub. Util. Code §454.5 frameworks that let specified transactions clear upfront standards and win preapproval instead of after-the-fact reasonableness review, last rebuilt in 2015. The utilities seek broader standing authority over RECs, RA (contracts up to 10 years), energy, fuel, and new CAISO day-ahead products, with batch quarterly reporting replacing per-transaction advice letters. A hybrid Energy Division workshop is set for mid-September; opening comments are due November 13.

► Details
PG&E asks for RPS delivery terms up to five years, RA up to 10, and other electric and fuel transactions up to five; SCE proposes parallel authority plus Day-Ahead Market Enhancement products; SDG&E requests preapproval of short-term RPS deals and RA contracts of 10 years or less. Common questions cover standardized REC purchase/sale limits, absorption of the new unforced-capacity counting framework, treatment of CAISO imbalance-reserve and reliability-capacity products, excess RA sales, and GHG compliance instruments. The ruling also revisits the 2006 restrictions on utility participation in CAISO congestion revenue rights auctions — potentially the larger financial question, since loosening them could deepen auction competition and return more congestion revenue to customers. The utilities must file a matrix showing where their plans align and defend each difference.
Climate Credit · Ruling Aug 2026 · Reform Proposal Requirements · Proposals Due Sep 14

Climate Credit Reform — ALJ Sets Ground Rules: Implementable Designs, Transparent Impact Data, Proceeds Held Constant

ALJ Sotero’s ruling establishes requirements for proposals to change the California Climate Credit, due September 14. Proposals may address the timing or number of distributions, calculation methodology, or eligibility, and must address equal treatment of bundled and unbundled customers, equity considerations, and implementation time, cost, and complexity — including whether changes could be implemented by 2028. Parties must meet and confer by August 28.

► Details
Impact estimates are optional, lowering the barrier to submitting proposals — but any estimates must come with underlying spreadsheets or CSV files and source citations, hold total distributed allowance proceeds at the 2026 forecast level, use 2025 recorded consumption where available, and compare against the existing credit for typical CARE and non-CARE customers across climate zones for at least one large IOU. The design lets the Commission compare how each proposal would redistribute the existing credit rather than obscure effects through differing revenue assumptions. The ruling encourages “office hours” with utility staff and allows data requests, which utilities must answer within 10 business days.
Tribal Policy · PD issued Aug 2026 · Proposed Decision · Earliest Vote Sep 17

Commissioner Houck PD Would Expand Tribal Consultation and Extend the Land-Transfer Policy to All IOU Property Sales

Commissioner Darcie Houck’s proposed decision revises the CPUC’s Tribal Consultation Policy and Tribal Land Transfer Policy: “early, often and meaningful” engagement on actions with tribal implications, escalation of inadequate consultations to the Executive Director, quarterly Tribal Information Forums starting 2027, and application of the land-transfer policy to all real-property dispositions by covered IOUs — including surplus property that would otherwise never receive Pub. Util. Code §851 review. Comments due September 2; earliest vote September 17, 2026.

► Details
Utilities would obtain tribal contacts from the Office of the Tribal Advisor, notify relevant tribes of dispositions, and provide interested tribes a virtual data room with the property’s current appraisal, recorded easements, and related information; energy utilities would report dispositions quarterly. Disputes among tribes seeking the same property would run first through the tribes, then the CPUC’s ADR program. Implementation depends on the currently vacant, governor-appointed Tribal Advisor position; the PD does not extend the policy to telecommunications providers, require utilities to map all holdings, or reach harder issues of tribal taxation, tribal law, and energization delays.
Res. G-3622 / G-3623 · Sep 17, 2026 · G-3623 Adopted · G-3622 Held to Oct 8 · Gas RD&D Oversight

Gas Research Oversight Splits — G-3623 Adopted Denying PG&E’s $1.95M 2024 Spend; G-3622 Held on the CEC’s $31.1M Drawdown

The Commission adopted Resolution G-3623 on September 17 and held Draft Resolution G-3622 to October 8. Both tighten CPUC oversight of ratepayer-funded gas research. Draft Res. G-3622 approves in part the CEC’s two $24 million RD&D plans but requires the agency to draw down $31.1 million in previously authorized, unspent funds first — limiting new ratepayer funding to $13.5 million — and bars hydrogen-related research pending a Commission determination on gas ratepayers’ role. Res. G-3623, as adopted, denies PG&E’s $1.95 million 2024 plan with no further resubmission authorized because the money was spent before plan approval, while authorizing $6.13 million (2025) and $7.87 million (2026) subject to revisions. PG&E may still record $611,440 in its balancing account for Commission-required planning, reporting and workshop costs.

► Details
As adopted, G-3623 preserves $6.31 million for integrity-management research, $3.15 million for gas decommissioning and electrification planning tools and $3.15 million for clean fuels integration across the 2025 and 2026 budgets; it removes proposed evaluation and database funding and reduces administrative allocations to the 10% cap. PG&E must submit revised plans through Tier 2 advice letters within 60 days. Implementation of the 2025 plan must await approval of revisions demonstrating additional research value and avoiding duplication, while the 2026 plan may proceed as PG&E clarifies benefit metrics and accounts for AI and machine-learning costs in integrity-management research. Unspent funds return to ratepayers at the funding cycle’s close except amounts committed or encumbered for continuing work — so approval timing affects how much of the 2025 budget PG&E can commit before the balance becomes refundable.

G-3622, still pending, gives the CEC 90 days to revise both plans to improve financial reporting, demonstrate coordination with other research administrators, and address duplication. G-3623 permits no resubmission of the denied 2024 request and conditions the 2025–2026 budgets on revised plans within 60 days that distinguish PG&E’s work from similar SoCalGas research, quantify expected benefits, and — for 2026 artificial-intelligence work — account for energy, cloud-computing, data-storage, and processing costs while retaining human decision-making authority. Together the drafts establish a common oversight framework emphasizing unspent balances, measurable ratepayer benefits, and non-duplication; SoCalGas’s four pending 2024–2027 research plans suggest these standards will soon apply to the remaining major gas RD&D administrator.
I.17-02-002 · Petition Aug 2026 · Petition for Modification · Aliso Canyon

Aliso Canyon — SoCalGas and Indicated Shippers Ask to Push the Next Biennial Assessment to June 15, 2028

The Indicated Shippers and SoCalGas filed a joint petition for modification to move the next Aliso Canyon Biennial Assessment Report deadline by one year, from June 15, 2027 to June 15, 2028. They argue the pending A.26-01-009 proceeding — which is reconsidering both the storage level and the D.24-12-076 Attachment A assessment methodology — is unlikely to finish before 2027, leaving Energy Division too little time to incorporate whatever methodological changes emerge.

► Details
The petitioners also argue a 2028 report would better align with commercial and planning timelines: SoCalGas’s current Backbone Transportation Service contracts run through October 31, 2029; SB 1221’s second-round pilot deadline falls in January 2028; and the CEC’s next full IEPR is due in 2027. A June 2028 report would give market participants relatively current information approaching the next BTS cycle. A counterargument available to the Commission: Energy Division already moved the first report from June 15 to October 1, 2025 when it needed more time, and SoCalGas later received a separate extension before filing its application — so the CPUC could keep the biennial schedule and grant targeted relief when necessary rather than fixing the next report in 2028 now.
No matches for selected IOU.

Miscellaneous

Voting-meeting results, agenda previews, advice letters, CAISO and FERC filings, litigation, and other items that are not a formal Application or Rulemaking/Decision.

Current Period
Sep 16 – Sep 30, 2026
1 item
Voting Meeting · Held Sep 17, 2026 · Results · San Marcos, Agenda 3587

September 17 Voting Meeting Results — PCIA Banked RECs Affirmed at Zero, AB 825 Rulemaking Opened, Four Marquee Items Pushed to October 8

At its September 17 voting meeting the Commission affirmed zero-dollar treatment of pre-2019 banked renewable energy credits in the PCIA (D.26-09-047) and opened the AB 825 regional-markets rulemaking (R.26-09-009). It also adopted distribution-planning equity metrics (Res. E-5480), the revised tribal land-transfer and consultation policies (D.26-09-072), Ava’s Sonrisa incremental-resource determination (Res. E-5475), PG&E’s gas RD&D budgets (Res. G-3623) and closure of the SGIP rulemaking (D.26-09-048). Four items were held to October 8.

► Details
Held to October 8: Draft Resolution E-5455, approving PG&E’s agreement to energize a 250-MW Google data center in San Jose while requiring an additional refundable capital advance of $600,000/MW; the proposed decision approving SCE’s request to add 47 areas totalling about 208 square miles to the High Fire-Threat District; the proposed decision replacing Working Stress Design in General Order 95 with Load and Resistance Factor Design for overhead electric and communications facilities; and Draft Resolution G-3622, approving in part the California Energy Commission’s research plans for fiscal years 2024–2025 and 2025–2026.

The Google resolution has now been held at four consecutive meetings — July 2, July 16, August 13 and September 3 — and the SCE fire-map item was held from September 3. Each adopted item has its own card in Proposed Decisions & Rulings. The meeting was held at the San Marcos City Council Chambers under agenda 3587.
Prior Period
Sep 1 – Sep 15, 2026
2 items
Voting Meeting · Sep 17, 2026 · Agenda Preview · Regional Markets / PCIA / Google

September 17 Voting Meeting Preview — AB 825 Rulemaking, PCIA REC Valuation, and the Repeatedly Postponed Google Data-Center Resolution

The CPUC on September 17 is expected to open a new rulemaking determining whether and how PG&E, SCE and SDG&E may participate in the regional electricity markets authorized by AB 825. The Commission is also scheduled to decide whether pre-2019 banked Renewable Energy Credits should be valued at zero in calculating the PCIA. Repeatedly postponed Draft Resolution E-5455 would approve PG&E’s agreement to energize Google’s 250-MW San Jose data center, requiring a fixed refundable advance of $600,000/MW — as much as $150 million. Other items include distribution-planning equity measurements, overhead-line design standards, revised tribal policies and gas-research spending.

► Details
Outcome: see the September 17 results card in this section for what the Commission actually adopted and what it held to October 8.

Correction carried from the September 3 meeting: the CPUC did not approve changes to SCE’s Fire-Threat Map on September 3. Commissioner Darcie Houck held that item until September 17 to allow further review. See the Fire-Map PD card in Proposed Decisions & Rulings for the substance of the item.

Also on the agenda: Draft Resolution E-5475 (Ava Community Energy’s Sonrisa project and the IRP baseline), Draft Resolution E-5480 (distribution-planning equity metrics), the GO 95 Load and Resistance Factor Design proposed decision, the tribal consultation and land-transfer policy proposed decision, and Draft Resolutions G-3622 and G-3623 on gas research, development and demonstration spending — including whether gas ratepayers should fund hydrogen research.
DPEP 2026-2027 · Filed Sep 2026 · Compliance Reports · Independent Engineer

Independent Engineer’s Preliminary Data-Adequacy Reports — SCE Ahead on Demonstrations, PG&E and SDG&E Still Owe Materials

PG&E, SCE and SDG&E filed preliminary data-adequacy reports prepared by independent professional engineer Resource Innovations for the CPUC’s 2026–2027 Distribution Planning and Execution Process cycle. The reviews cover the utilities’ 2025–2026 Grid Needs Assessments and Distribution Upgrade Project Reports, including load and DER forecasts, pending loads, project selection and execution. Distribution Planning Advisory Group reports presenting verification and validation findings are due November 6, followed by a cross-utility report on March 15, 2027.

► Details
PG&E provided adequate data for circuit loads, system and circuit-level forecasts, known and pending loads, and extreme-weather adjustments; materials covering no-cost solutions, GNA tables, recommended investments and the continued need for earlier projects were expected in early September, with load-tracking, project-prioritization and execution information due later.

SCE completed most of its scheduled early forecasting demonstrations, including base, high and low scenarios, hot spots and extreme-weather adjustments. Additional GNA demonstrations were scheduled for September 25, followed by project-planning demonstrations October 9 and prioritization and execution information October 13.

SDG&E provided adequate data for most forecasting, pending-load, GNA and planned-investment steps, but the engineer requested additional information because data on 2025 circuit loading and extreme-weather adjustments were incomplete. Load-tracking data were due September 15, with other project information expected through early October.

These reports assess whether the independent engineer has enough information to conduct its review; they do not validate the utilities’ forecasts or investment plans, and because the verification approaches differ the statuses are not a direct ranking of data or planning practices. The engineer cautioned that it received more detailed information than parties received through the service list, so its adequacy findings do not establish that stakeholders can evaluate the same forecasts and projects. The November DPAG reports will provide the first substantive verification findings.
Earlier Period
Aug 16 – Aug 31, 2026
2 items
CAISO · Aug 2026 · Markets & Forecasting · Large Loads

CAISO Flags Forecasting Challenges from Large Loads; Sept. 30 FERC Seams Report Due with SPP

CAISO is developing four responses to forecasting problems posed by large loads: better visibility into projected new load additions, typical operating profiles (median daily demand), schedules and actual metered demand for intraday tracking, and operating limits and flexibility/curtailment capabilities. Separately, CAISO and SPP face a September 30 deadline to report to FERC on seams issues, and the West-Wide Governance Pathways Initiative recommended the future ROWE board retain CAISO’s market-monitoring functions with a robust data-sharing framework.

► Details
The forecasting workstream parallels the CPUC’s scrutiny of data-center load in PG&E’s 2027 ERRA forecast (see Proposed Decisions & Rulings) — both turn on distinguishing committed from speculative load before it enters planning and rate-setting. On EDAM, Energy Division staff comments questioned whether currently available public data allow stakeholders to reproduce the calculations behind some of CAISO’s key load-balancing results. Related Sacramento activity in the period: SB 886 (preventing data centers from raising costs for other customers) and SB 887 (clean-energy investment incentives) advanced from a key committee as the session nears its close.
CEC · Adopted Aug 2026 · Efficiency Standard · First in Nation

CEC Adopts First-in-Nation Replacement-Tire Efficiency Standard — Projected ~$1B/yr Driver Savings, 2 MT CO₂ Reduction

The California Energy Commission unanimously approved a rule phasing in the nation’s first efficiency standards for replacement tires, designed to ensure replacement tires sold in the state are on average at least as energy-efficient as original-equipment tires, with a consumer “leaf” labeling system. The state projects roughly $1 billion per year in driver savings and a 2 million-ton annual CO₂ reduction — equivalent to removing about 400,000 cars from the road.

► Details
Industry opposition was on the record: Goodyear told the Commission the rule would raise consumer costs and that technical and legal issues remained unresolved, disputing the CEC’s estimate of roughly $6.50 average per-tire price increases in phase 2 and warning increases could reach several hundred dollars. Rolling-resistance efficiency interacts with electric-vehicle range, making the standard relevant to transportation-electrification load forecasts as well as gasoline savings.
No matches for selected IOU.

Sources: CPUC News · CPUC Docket Search · Document Portal · CalRegulatory · Utility Dive Updated September 21, 2026